|
SCOPE OF WORK
Southeast Issaquah Bypass
NEPA Environmental Impact Statement and Preliminary Engineering Design
Change Order Summary
CO#1 09/17/96 – Original SOW replaced entirely by CO#2
CO#2 04/23/98 – Complete Replacement of SOW
CO#3 10/02/98 – Funds Transfer, no change to SOW
CO#4 11/18/98 – Funds Transfer, no change to SOW
CO#5 07/16/99 – Modified/added SOW requirements
CO#6 07/25/00 – Funds Transfer, no change to SOW
CO#7 03/12/01 – New tasking for Entranco
CO#8 10/01/01 – Modified/added SOW requirements
CO#9 10/22/01 – Modified/added SOW requirements
CO#10 04/19/02 – Modified/added SOW requirements (06/05/02
– Second Version of CO#10v2)
Note:
Change Order #10 was adopted by a vote of the City Council on
Agenda Bill 4892 on 05/20/02.
Therefore, the Change Order version dated 06/05/02 could not be the official
version because it was dated after the adoption.
CO#11 06/05/03 – Modified/added SOW requirements
TASK 1 PROJECT
MANAGEMENT
1.1 Project Management
Plan
The CONSULTANT will prepare a project management plan that will set the tone
for every task of the PROJECT — from mobilization through the Final
Environmental Impact Statement (FEIS) and Design Report. The plan will organize
the scope into a work breakdown structure in which a specific budget, schedule,
and dates for deliverables are identified for each individual task.
The plan will identify the interrelationships among the tasks in the work
breakdown structure, and define the key project management activities as they
relate to work assignments, reporting, responsibilities, schedule, and cost
control. The plan will include a project summary, schedule, procedures guide,
budget and cost control summary, organization plan, documentation format and
filing guidelines, and reporting and review procedures.
The schedule will include all tasks identified herein, identify their
duration and sequencing, and identify the critical path. The project schedule
will identify review periods to be allowed for the CITY and cooperating
agencies.
PRODUCT
Draft Project Management Plan (4 copies)
Final Project Management Plan (15 copies)
1.2 Monthly Billings and Progress Reports
The CONSULTANT will prepare monthly progress reports describing the status of
the PROJECT. These reports will:
Highlight significant accomplishments
Target potential problem areas needing special attention or
coordination
Compare actual work progress with contractual obligations on a design
task basis
The progress reports will be presented in a task oriented format and will
include updated scheduling reports, indicating all progress to date and
resources expended. This update will include any changes in schedule, sequence,
or resource loading. If any schedule slippage has occurred, a plan for bringing
the work back on schedule and budget will be included.
Progress reports and billings will be prepared by the CONSULTANT and
submitted on a monthly basis. These items will be supported by detailed record
keeping sufficient to closely track the PROJECT budget and expenditures and
support the billings.
PRODUCTS
Monthly Progress Reports (approximately 31 33
progress reports), incorporating Project Schedule revisions as appropriate, and
Monthly Billings (approximately 31 33 billings).
1.3 Direction, Meetings, and Coordination This task includes the following
project management items:
Technical direction to project staff
Coordination meetings with the CITY on a bi-monthly basis
Periodic Meetings with Project Advisory Committee up to 18 meetings
Up to 4 meetings with the Army Corps. Of Engineers to provide
coordination on wetland issues.
Meetings with third parties such as CITY, State, and Federal
officials, and other consultants, as necessary up to 72
4 meetings
Coordination with subconsultants
Technical review
TASK 2 QUALITY CONTROL
2.1 Quality Control Plan
A project quality control plan will be prepared by the CONSULTANT and
submitted to the CITY as part of the Project Management Manual. This task will
include both the preparation and implementation of this quality control plan.
2.2 Quality Assurance Review
The work products will be reviewed by consultant team staff with expertise in
the appropriate discipline areas. This will be an ongoing activity during the
duration of the project with emphasis on major deliverable work products.
PRODUCTS
Project Quality Control Plan section of Project Management Manual (4 copies)
Quality Assurance Review Summaries up to 24 Deliverable Reviews
TASK 3 EIS SCOPING
3.1 Prepare Scoping Notice/Notice of Intent
The CONSULTANT will coordinate with the CITY and WSDOT to prepare SEPA
Determination of Significance/Scoping Notice and a draft NEPA Notice of Intent.
The scoping process will be completed by the CITY and WSDOT with assistance from
the CONSULTANT. The CITY, WSDOT and the CONSULTANT will jointly develop the
purpose and need, statement as part of the NEPA Notice of Intent. The statement
will be developed to provide a general framework for alternatives development.
3.2 Scoping Meeting and Preparation
The CONSULTANT will prepare displays and attend one agency scoping meeting
and one public scoping meeting. The CONSULTANT will assist the CITY with
briefings following the scoping process.
3.3 Revise Scope of EIS
Copies of all written comments received by the CITY during the scoping
process will be transmitted to the CONSULTANT for review. The CONSULTANT will
revise the Scope of the EIS based on comments received during the scoping
process.
TASK 4 PUBLIC AND AGENCY INVOLVEMENT
The CONSULTANT will review the Public Involvement Plan which will be prepared
under a separate contract. The CONSULTANT will work closely with CITY staff in
assisting the CITY's implementation of the Public Involvement Plan.
The CONSULTANT will support the implementation of the Public Involvement Plan
through limited assistance with the following tasks:
4.1 Public Involvement Plan
The CONSULTANT will review and modify the Public Involvement Plan being
prepared under a separate contract.
PRODUCTS
Comments on the Public Involvement Plan
4.2 Newsletter Articles/Coordination
The CONSULTANT will assist on the development and preparation of up to six
(6) newsletters. PRODUCTS
Comments on the six (6) newsletters
4.3 Discipline Meetings
The CONSULTANT will attend and prepare for up to fifteen (15) meetings to
support discipline studies. Five of these meetings will be to coordinate with
the on-going area-wide flood studies being conducted by RH2.
PRODUCTS
Meeting attendance at up to fifteen (15) meetings (five of which will be with
RI-12).
4.4 Open Houses
The CONSULTANT will attend and prepare for up to six (6) public open house
meetings.
PRODUCTS
Meeting attendance and preparation for meetings
4.5 Special Interest Group Meetings
The CONSULTANT will attend and support the CITY at up to sixteen (16)
meetings with special interest groups including neighborhood and trails groups.
PRODUCTS
Attendance and preparation for up to sixteen (16) meetings
4.6 Council Briefings
The CONSULTANT will attend and support up to six (6) Council Briefings.
PRODUCTS
Attendance and preparation for up to six (6) Council Briefings
4.7 Public Outreach
The CONSULTANT will develop additional public outreach tools including
potential electronic media items such as a site on the world wide web with
information relating to the Southeast Issaquah Bypass project including only the
following components: project, schedule, status, City and Project Team contact
lists, location listing of project and information prepared by the Public
Involvement Consultant. This site will be updated monthly with up to eighteen
(18) updates.
PRODUCT
A site on the world wide web with up to eighteen (18) updates.
TASK 5 SURVEYING AND MAPPING
The aerial mapping for the PROJECT will be developed from existing city maps
in AutoCAD format. The CITY will provide mapping in hard copy and CADD to the
CONSULTANT. The CONSULTANT will update the mapping to conceptual design level
accuracy. New areas of development and obscure areas will be supplemented, as
required, with field surveys
conducted by the CONSULTANT. New aerial mapping will be required during the
final design phase but is not included in this scope of work. The study area for
the surveying and mapping task will include the corridor within which the two
build alternatives are anticipated to lie.
5.1 Data Collection and Research
Field survey activities performed by the CONSULTANT will include:
Collect existing aerial maps, section breakdown, horizontal and
vertical control. Data collection activities performed by the CITY will
include:
Collect updated tax parcel information.
Collect existing utility as-built information.
5.2 Control Survey and Supplemental Topography
Corridor survey control planning, reconnaissance, and traverse
Control to be tied to existing Section and Quarter Section Comers,
vertical benchmarks, and control from previous aerial survey.
Obscure area topography
CONSULTANT to provide supplemental survey along the two north and two south
route options in areas obscured by vegetation.
Update topography
Update topography and planimetric features for improved areas adjacent to
alignments, such as gun club and new ball field. The survey will provide mapping
of sufficient resolution for route selection but not National Map Accuracy
Standards.
5.3 Sensitive Areas Survey
Wetland boundary survey
CONSULTANT will field locate and map flags from delineated wetland
boundaries. Assume three wetlands.
Stream centerline location and profile
CONSULTANT to survey designated streams and profile within the corridor study
area. Assume three streams.
5.4 Base Mapping
Aerial topography, existing utility and sensitive areas mapping
CONSULTANT to create base maps for route study of the proposed bypass
corridor study area as shown on Exhibit A. Existing utility information and new
sensitive area data will be combined with existing aerial planimetric mapping.
Merging of Supplemental mapping
Revise and upgrade existing base map to reflect supplemental survey along
proposed routes and revise topography and planimetric features of new
improvements within the bypass corridor study area.
CONSULTANT to develop a new topographic map TIN and contours for Sheets King
11 and King 12, encompassing more accurate topographic ground data.
Preliminary ROW Boundary Map
The CITY will provide an updated right-of-way map for the corridor in hard
copy and AutoCAD formats showing existing right-of-way and tax lot parcel
information as well as current ownership. The CONSULTANT will review the
boundary map prepared by the CITY and incorporate the data into the Base Mapping
as needed for design and Environmental Studies.
TASK 6 PRELIMINARY ENGINEERING
The CONSULTANT will identify and conduct conceptual engineering for the two
north and two south build alternative routes from the northern terminus along
the I-90 corridor to Issaquah-Hobart Road.
Existing related studies will be used to the extent possible. This includes:
Alignment studies previously conducted for the Southeast Issaquah
Bypass
The initial tasks will summarize work completed to date and provide necessary
closure for some of the already identified alignment options which will not be
carried forward.
Public Involvement will be instrumental in conducting preliminary
engineering alternative identification
6.1 Preliminary Alignment Plans
The CONSULTANT will prepare preliminary alignment plans for the Bypass
corridor from the northern terminus of the Bypass to Issaquah–Hobart Road at a
1:1000 horizontal and a 1:200 metric vertical scale. These will include
alternative horizontal and vertical alignment. A maximum of two alternatives
within the Bypass corridor will be considered. The CONSULTANT will submit plans
for CITY review at the completion of alignment studies and working drawings as
requested by the CITY.
PRODUCTS
Working Drawings as requested by the CITY
Draft Preliminary Alignment Plans (2 sets)
Final Preliminary Alignment Plans (2 sets)
6.2 Alternative Alignment Memorandum
The CONSULTANT will prepare an Alternative Alignment Memorandum of the
corridor based on the alignments considered in Task 6.1 for CITY review that
provides planning level information on the following areas:
Traffic operations and city land use serviceability (function)
Roadway alignments
Intersection configurations
Speed limit alternatives for consideration by City of Issaquah
Required road design variances
Impacts to existing side-streets
Major retaining wall and bridge locations
Drainage
Geotechnical concerns
Impacted sensitive areas per the City of Issaquah Critical Areas
Ordinance (CAO), the NEPA/SEPA/404 Merger Agreement requirements, and
impacts to 4(f) and 6(f) properties, wetlands and hazardous waste
sites
Preliminary right-of-way and easement requirements
Potential Displacements
The Alignment Memorandum will discuss alignments considered after the
completion of the EIS Scoping Process and be the basis of the alternatives
chapter of the DEIS. The alignment memorandum will also discuss all other
alignment alternatives considered prior to EIS scoping and identified during the
scoping process. The Memorandum will identify up to two alternatives studied for
the EIS.
The CONSULTANT will provide the CITY with two copies of a draft Alternative
Alignment Memorandum for review. The CITY will review and provide consolidated
comments to the CONSULTANT, and the CONSULTANT will revise the report for the
final publication. The CONSULTANT will provide 6 copies of the finalized
Alternative Alignment Memorandum to the CITY for distribution.
PRODUCTS
Draft Alternatives Alignment Memorandum (2 copies) Final Alternatives
Alignment Memorandum (6 copies)
6.3 Preliminary Geotechnical Investigations
6.3.1 Preliminary Geotechnical Report
The CONSULTANT will perform a preliminary geotechnical investigation within
the Southeast Issaquah Bypass corridor (the corridor within which the two north
and south build alternatives are expected to lie) and prepare a report according
to the City of Issaquah Critical Areas Ordinance (CAO) and EIS requirements. The
geotechnical investigation will be performed to allow for early identification
of sensitive areas to be avoided or mitigate during the initial stages of
pre-design (Phase 2).
Phase 1 of the geotechnical investigation will be a detailed field
reconnaissance and review of available soils information to identify areas of
unstable soil/rock and other earth-related factors associated with environmental
and construction cost issues. Based on the review and field investigations, the
CONSULTANT will prepare a technical memorandum summarizing the results of the
investigation for CITY review. The memorandum will include a discussion of the
following:
Review available documents regarding geologic and geotechnical
conditions in the site area. These documents include published
geologic maps and reports, archived coal mine records, geotechnical
reports from our files and geotechnical reports by others in the site
area.
Detailed surface reconnaissance of the road corridor including
observations and evaluation the performance of nearby road
excavations, embankments and structures in the road corridor area.
Subsurface explorations include two test borings located along the
abandoned railroad grade at the north end of the Southeast Issaquah
Bypass corridor where deep cuts are proposed.
Describe site topography, geology, soils and ground water and
provide maps and cross sections showing the distribution of geologic
units and Soil Conservation Service soil units.
Summary of all known subsurface explorations accomplished within
the Southeast Issaquah Bypass road corridor area.
Identification of areas that meet the City of Issaquah CAO criteria
for erosion, landslide and seismic hazard areas and provide maps
showing those areas.
Description and delineation of unstable or potentially unstable
slopes within the road corridor.
Identification of areas within the Southeast Issaquah Bypass
corridor where additional geotechnical evaluation is appropriate.
6.3.2 DEIS Supplement Field Program
The purpose of this supplemental services is to obtain subsurface information
regarding soil and ground water conditions in the south part of the Southeast
Issaquah Bypass project area as a basis for evaluating environmental and
preliminary road design issues for the route alternatives. These tasks are for
the design studies of the selected alternative based on the "bridge" alternative
described above. The scope of services includes the following:
Drill eight to nine borings in the south part of the Southeast Issaquah
Bypass corridor. Three of the borings will be located along Alternative A and
four to five of the borings will be along Alternative B. The borings will be
drilled to depths ranging from 20 to 60 feet.
Obtain soil samples from the borings at five-foot depth intervals. The soil
samples will be field classified, placed in heavy plastic sealable containers
then returned to our office additional classification.
Install a peizometer casing in the borings for ground water monitoring. The
peizometer casing will be protected with a steel monument at the surface.
Monitor ground water levels in the peizometers on a monthly basis for six
months.
Evaluate the subsurface information obtained from the explorations as a
basis for describing the existing conditions, impacts and mitigation of
identified environmental and preliminary road design issues consistent with
ICE's tasks described in the Tasks 6.3, 7.10 and 7.13 of the Agreement.
Six of the test borings will be conducted using a hollow-stem auger
drilling rig mounted on an all-terrain vehicle (ATV). Two or three borings
will be completed in a "wet" area using a portable drill rig that can be hand
carried to the proposed locations. We do not expect to conduct grading other
than disturbance of the surficial soils that will result from moving the ATV
and portable drilling equipment to the proposed exploration locations. We
expect that ground disturbance caused by the exploration equipment will
require covering disturbed soils areas with straw mulch. No other site
restoration activities are planned.
PRODUCTS
Draft Alternatives Preliminary Geotechnical Investigation Technical
Memorandum (2 copies) Final Alternatives Preliminary Geotechnical Investigation
Technical Memorandum (6 copies)
6.3.3 Design Studies
Explore subsurface soil and ground water conditions by drilling 35 borings.
Twenty-two of the borings will be drilled along the bridge segment (two borings
at each pier or abutment). Eight borings at four detention ponds (two borings at
each pond), and five borings along the central and north part of the road
alignment. Peizometers will be installed in each boring.
Perform laboratory test on selected soil samples to determine pertinent
engineering characteristics of the soils.
Monitor ground water levels in the peizometers on a monthly basis for six
months.
Evaluate the existing local and regional ground water regimes based on our
explorations, monitoring and available literature.
Develop foundation support recommendations for the new bridge, including
allowable bearing pressures for spread footings and capacity-penetration
relationships for piles, as appropriate.
Evaluate the expected settlement behavior of bridge foundations.
Provide site preparation criteria for the new roadways, including
recommendations regarding the required depth of stripping and excavation of
peat.
Provide earthwork criteria for the project including types of fill material
and compaction requirements.
Evaluate the expected settlement behavior of fill embankments, particularly
with regard to differential settlements along the roadway alignment and between
the bridge and approach fills, taking into account the time sequence of
construction.
Develop recommendations, if required, for the design of retaining walls for
roadway fills, including allowable bearing pressures, active and passive lateral
soil pressures, sliding friction and settlement.
Provide recommendations for cut and fill slopes, including recommendations
for cut slopes in soil and rock.
Evaluate site ground water conditions and developing appropriate drainage
recommendations.
Evaluate pavement support conditions and develop a roadway design pavement
section based on forecasted traffic conditions provided by the City of Issaquah.
Provide recommendations for seismic design criteria, as appropriate.
Provide geotechnical recommendations for detention ponds including berm
configuration and stability, soil types and compaction criteria, and pond bottom
liner design, as appropriate.
Prepare a written report containing our conclusions and recommendations along
with the supporting field and laboratory data.
6.4 Open House Exhibit Preparation
The CONSULTANT will provide exhibits based on working drawings depicting the
two north and two south proposed Southeast Issaquah Bypass build alternatives
for inclusion in the DEIS and for displays at up to six (6) open houses.
PRODUCT
Exhibits for Open House Display
6.5 Preliminary Engineering for EIS
The CONSULTANT will prepare a Draft and Final Design Memorandum for the
Southeast Issaquah Bypass roadway. The Memorandum will discuss in detail two
north and two south build alternatives and will provide recommendations on
structural and mitigation measures for the PROJECT. The CONSULTANT has not
included work alternatives that may result from the 404 Merger process. If the
404 Merger process identifies subsequent alternatives it shall be considered
extra work. A more detailed analysis of the elements included in the Alternative
Alignment Memorandum. The Memorandum will provide a more detailed cost analysis
and identify any additional studies that should be conducted prior to completion
of the design not included in the current scope of work.
6.5.1 Verify Geometric Design Criteria
A detailed summary of relevant geometric design criteria applicable to CITY
designated speed limits, will be prepared, based on applicable Design Standards
in accordance with the CITY Design Manual and the WSDOT Local Agency Guidelines
as well as the AASHTO Green Book. Particular emphasis will be placed on
identifying those elements which may be subject to interpretation, engineering
judgment or modification due to adverse field conditions. All elements will be
reviewed with CITY staff prior to the start of detailed horizontal and vertical
alignment design.
6.5.2 Initiate Utility Contacts/Analyze Relocation
Needs
All public and private utilities known or thought likely to have existing or
planned facilities in the PROJECT area will be identified, and a request for
"as-built' information will be made through the CITY.
After information has been obtained and potential impacts to utilities have
been identified, a meeting will be held with all affected utilities, the
CONSULTANT and CITY staff to discuss utility involvement in the PROJECT. The
CITY will coordinate this meeting.
Relocation needs will be identified and documented including cost estimates
where appropriate.
6.5.3 Preliminary Drainage Technical
Memorandum
The CONSULTANT will develop a Preliminary Drainage Technical Memorandum based
on Surface Water Management (SWM) requirements for the Environmental Phase.
Requirements of the Sensitive Areas Ordinance (SAO) and basin plans will be
addressed. Additionally, the CONSULTANT will work with RH2 and the CITY to
develop flooding evaluations of the Lewis Lane neighborhood including field
investigations, coordination, investigation of water quality treatment
facilities for storage, investigation of re-routing up stream ditches,
documenting deficiencies and recommend corrective actions.
6.5.4 Horizontal and Vertical Alignment Plans
The horizontal and vertical alignments will be developed to a level of such
refinement that horizontal and vertical clearances can be checked, drainage
concepts resolved, utility conflicts identified and right-of-way requirements
accurately estimated. No separate utility plans are required. Utility conflict
determination will be based on information supplied by utility companies and the
CITY and on surface topographic information collected by the CONSULTANT.
6.5.5 Roadway Sections
Roadway sections for each type of roadway proposed for consideration by the
CITY for use on the PROJECT will be prepared. Similar through lane and bridge
sections will be combined.
6.5.6 intersection Design
Recommend the number and configuration of traffic lanes for the intersections
based on an analysis of traffic data, public input, and other PROJECT
information developed by the CONSULTANT and information provided by the CITY.
Prepare 1:500 metric scale intersection plans.
6.5.7 Bicycle, Pedestrian and Trail Facilities
The CONSULTANT will identify existing and proposed pedestrian and bicycle
facilities within the corridor, as well as appropriate connections and
extensions of existing trails. Type II lanes and sidewalks are anticipated
although some sections may use a rural section with separate paths/trails.
Improvements to existing trailheads within the corridor will be reviewed for
possible expansion and/or improvement.
6.5.8 Road/Driveway Approach Design
Opportunities will be identified for consideration by the CITY for
consolidation or minimization of driveway and cross street access to the
arterial. The CONSULTANT will identify possible new intersection locations and
develop preliminary designs and analyze operations.
6.5.9 Landscape/ Restoration Development
The CONSULTANT will prepare conceptual drawings of proposed
landscape/restoration improvements in response to the proposed roadway alignment
and widening alternatives. The conceptual design will respond to the various
site conditions.
Available materials including views, safety, visual screening, maintenance
requirernents, etc., will be examined. Evaluation of alternative
landscape/restoration treatment options will utilize visual imaging and computer
aided video modeling technology to accurately represent the proposed roadway and
landscape design solutions. Photo imaging and characterization of the roadway
will be used during public information and presentations to graphically depict
the visual impact of the proposed improvements. This element will include
summaries of maintenance impacts.
6.5.10 Structures
The CONSULTANT will identify any proposed and existing structures within the
PROJECT. The layout plan of the necessary walls will include recommendation of
wall types, the vertical profile, and the horizontal alignment.
6.5.11 Cost Estimate
The CONSULTANT will prepare a budgetary cost estimate to be included with the
Design Memorandum. Costs will be based on standard bid item tables published by
WSDOT and the CITY. The CITY will provide estimated right-of-way costs based
upon right-of-way requirements identified by the CONSULTANT.
6.5.12 Cross Sections
The CONSULTANT will prepare cross-sections at 20-meter intervals for up to
two north and two south alignments to identify right-of-way/easement needs and
cut-and-fill volumes.
6.5.13 Preparation and Submittal of Draft and Final
Design Memorandum
The CONSULTANT will compile and summarize the results of the preliminary
engineering tasks in a Design Memorandum.
6.5.14 Right-of-Way Needs Map
The CONSULTANT will prepare a Preliminary Right-of-Way needs map base for one
north and one south alternative on CITY supplied Right-of-Way information. This
map will be adequate for the CITY to estimate property acquisition costs and to
begin Right-of-Way purchase.
Existing right-of-way parcel research, boundary resolution and mapping scope
of work
Collect current tax parcel information and record survey data for
approximately 40 parcels and adjoining roads rights-of-way for proposed
road alignment design extending from Front Street to Sunset Way.
Field survey boundary control; locate sufficient Section, plat and
street monuments
Update existing property and right-of-way lines in existing property
base maps supplied by the CITY. Revised information to be based upon
current tax parcel information and record survey data. Title reports to
be supplied by the City of Issaquah.
PRODUCTS
Draft Preliminary Engineering Report (2 copies)
Final Preliminary Engineering Report (10 copies)
Design Plan/Profile Drawings
Two (2) copies of final right-of-way needs map
Draft and Final Drainage Design Report
Geotechnical Report
6.5.15 Interchange Refinements Study
The CONSULTANT will prepare modifications to the I-90/Sunset Interchange
designs to meet the needs of independent utility. This interchange design will
assume the South SPAR/Sunset Way Interchange modifications are not constructed.
The Full Build scenario will also be assessed assuming the South SPAR and
connection of the Bypass to the Sunset Interchange modifications.
DESIGN GUIDELINES
The CITY will designate the basic premises and criteria for the design.
Reports and plans, to the extent feasible, will be developed in accordance with
the latest edition and amendments to the following:
City of Issaquah Publications
Issaquah Design Standards
Critical Areas Ordinance
King County Publications
Road Standards 1994
General Special Provisions 1991
Surface Water Design Manual
Community Plan
Basin Studies
Sensitive Areas Ordinance
Washington State Publications
Standard Specifications for Road, Bridge, and Municipal Construction
(M41-10)
Standard Plans for Road, Bridge, and Municipal Construction
(M21-01)
Amendments and General Special Provisions
Standard Item Table
Highway Design Manual
Bridge Design Manual
Construction Manual
Local Agency Guidelines
DOE Stormwater Management Manual for the Puget Sound Basin
J. Hydraulics Manual
American Association of State Highway and Transportation Officials
Publications
a Policy on Geometric Design of Highways and Streets (1990) (Green
Book)
Standard Specifications for Highways Bridges,
Twelfth Edition (1977)
a Guide for Highway Landscape and Environmental Design (1970)
Highway Design and Operational Practices Related to Highway Safety
(1974) (Yellow Book)
Any American Association of STATE Highway Officials policy applicable
where said policy is not in conflict with CITY standards
U.S. Department of Transportation Publications
Manual on Uniform Traffic Control Devices for Streets and Highways
Other Publications
National Electrical Code
Transportation Research Board Highway Capacity Manual (1994)
Standard drawings and sample documents prepared by the CITY and
furnished to the CONSULTANT will be used as a guide in all cases where
they fit design conditions.
Items To Be furnished To The CONSULTANT By The CITY
The CITY will furnish for the CONSULTANT copies of documents which are
available to the CITY that will facilitate the preparation of the plans and
studies within the limits of the PROJECT. These are:
Aerial mapping in hard copy and digital (AutoCAD) format
A list of utilities and other agencies having jurisdiction in the
PROJECT area • Rights of Entry to affected properties as requested by
the CONSULTANT • "As Built' plans, as available
Assessor's maps (in digital and hard copy format)
Archaeological and historical information
Timely review of all CONSULTANT submittals and collation of all
review comments into a single document for submission to the
CONSULTANT at one time
Average weekday traffic volumes, accident data, and other related
transportation data and plans
Existing right-of-way and parcel information in AutoCAD format
PRODUCTS
Draft Alternatives Design Memorandum (2 copies) Final Alternatives Design
Memorandum (6 copies) Working Drawings
6.6 Photo Imaging of Alternatives
The CONSULTANT will provide up to ten (10) photographic imaging (renderings)
depicting the proposed. Southeast Issaquah Bypass alternatives for inclusion in
the DEIS and FEIS and for displays at public meetings and other public outreach.
TASK 7 ENVIRONMENTAL TECHNICAL STUDIES
The alignment Study addressing two north and two south build
alternatives and one no-build alternative within the Bypass corridor will be
used as the basis for the research conducted in the preparation of the technical
reports. Existing information available from work underway or completed for the
North SPAR and South SPAR/Sunset Interchange EISs will be used for the Southeast
Issaquah Bypass EIS. New information will be developed as required up to the
levels of effort specified in the projects "Person Hours Estimate."
7.1 Transportation
7.1.1 Methodology
The CONSULTANT will document the methodology and assumptions used to guide
the transportation analysis. The methodology and assumptions used in this
analysis will be consistent with those applied in the South SPAR/Sunset
Interchange, and North SPAR EISs
7.1.2 Existing Conditions
The CONSULTANT will document existing transportation conditions as described
in Subtasks 7.1.2.1 through 7.1.2.6. The documentation of existing conditions
compiled as part of the South SPAR/Sunset Interchange, and North SPAR EISs will
form the basis for this task.
Data Collection
Existing traffic information will be reviewed by the CONSULTANT, including
data presented in the East Sammamish Alternatives Feasibility Study, the
I-90/Sunset Way Interchange Study (June 1996), the Grand Ridge Environmental
Documents (June 1995), the City of Issaquah Comprehensive Plan, and the King
County Comprehensive Plan.
These reports, along with data collected for the South SPAR/Sunset
Interchange, and North SPAR EISs, will provide much of the information needed to
document the existing conditions of the study area with respect to
transportation, and will form the basis of subsequent analysis and environmental
documentation.
The existing conditions inventory will include documentation of the
following:
Street system, classifications and traffic control
Traffic operations
Transit and ridesharing
Bicycle travel
Pedestrian travel (including trails)
Accidents (last 3 years) and safety
Parking
Truck Traffic
Base Year Model Refinement
An existing traffic model will be utilized along with the documentation of
existing conditions for use in subsequent tasks. The model is essentially the
same that was used in preparation of the Grand Ridge DEIS, the I-90/Sunset Way
Interchange Additional Access to Interstate 90 Study, and the Issaquah
Comprehensive Plan. The model, developed by Michael R. Birdsall, is compatible
with the Puget Sound Regional Council's model, and can readily accommodate data
transfer. The model includes both arterials and many local streets within the
focused area.
The existing traffic model, allowing for unique modifications needed for this
Southeast Issaquah Bypass analysis, will be employed for all new traffic
forecasts prepared in this study. This approach will provide for consistency of
all new alternatives with the traffic forecasts and analysis conducted for the
South SPAR/Sunset Interchange, and North SPAR EISs.
Intersection Operations
The intersection analysis will focus on the AM and PM peak hours.
Intersection analysis will be conducted by the CONSULTANT. For signalized
intersections, the operational analysis methodology outlined in the
Transportation Research Board Special Report 209 Highway Capacity Manual will be
used. Intersection levels-of-service will be calculated for key intersections
using NCAP and TRANSYT-7F software and will be determined by the CONSULTANT and
the CITY.
Roadway Operations
Portions of the proposed Southeast Issaquah Bypass may be described as urban
arterials (HCM terminology) and will be analyzed as such. Where this is
appropriate, the CONSULTANT will conduct level-of-service calculations based on
the urban arterial methodology documented in the 1994 HCM. The CONSULTANT
will analyze one section of urban arterial.
Construction impacts
The CONSULTANT will prepare a narrative description of potential
transportation related construction impacts.
Documentation of Existing Transportation Conditions
The CONSULTANT will document the results of Tasks 7.1.1.1 – 7.1.1.5. The
CONSULTANT will provide the CITY with 2 draft copies of the report for review.
The CITY will review and provide consolidated-comments to the CONSULTANT.
The CONSULTANT will revise the draft and provide 6 copies of the final
Existing Transportation Conditions Technical Memorandum to the CITY for
distribution and revise after review by the City, County, and WSDOT.
PRODUCTS
Draft Existing Transportation Conditions Technical Memorandum (2 copies)
Final Existing Transportation Conditions Technical Memorandum (6 copies)
Alternative Corridor Identification and Documentation
In conjunction with the CITY, the CONSULTANT will identify and document
alternative corridors to the Southeast Issaquah Bypass that could potentially
accommodate forecast travel demand. This documentation will be based in large
part on a compilation of findings from previous reports and studies. The
documentation will be done utilizing a matrix supplemented by a narrative
description.
7.1.3 Land Use Assumptions (For Transportation
Modeling)
Land use data used to develop and calibrate the traffic assignment model were
provided by King County and the City of Issaquah, and are consistent with those
used in the South SPAR/Sunset Interchange and North SPAR EISs. The land uses
were divided into several categories (single-family, multi-family,
general-retail, social-retail, hotel-motel, general office, medical office,
industrial, active land, and park & ride) and trip generation rates were
assigned to the land use categories based on ITE trip generation studies.
Future year land use assumptions were developed for the years 2005 and 2015.
The land use data for these future years was provided by the PSRC, King County
and the City of Issaquah. The data is based on regional forecasts of economic
activity and local land use plans, including the East Sammamish Community Plan
and the Issaquah Comprehensive Plan.
The CONSULTANT will summarize, update, and revise as necessary, the land use
assumptions provided by the CITY for the existing conditions and the forecast
years (2005 and 2015) using, in part, traffic projections developed as part of
the Sunset Interchange Six Point Access Study.
A 2015 build land use scenario will be evaluated, as used in the South
SPAR/Sunset Interchange, and North SPAR EISs.
For the analysis of air quality impacts, opening day traffic forecast will be
conducted based on year 2015 land use and transportation forecasts.
7.1.4 Model Network
The transportation networks for model years 2005 and 2015 were developed from
planned and programmed improvements to be implemented by WSDOT, King County and
the City of Issaquah.
The CONSULTANT will review and revise these networks as necessary to ensure
continued consistency with adopted Plans. Further refinements to the future year
networks will be made to reflect the alignment alternatives.
7.1.5 Prepare Future Baseline and Alternative
Alignment Travel Demand Forecasts
Based on future land use assumptions supplied by the CITY and on the
definition of the roadway alignment alternatives, year 2005 and 2015 travel
demand forecasts will be prepared using the traffic model. The travel
forecasting scenarios being evaluated as part of the South SPAR/Sunset
Interchange, and North SPAR EISs contain the range of scenarios to be evaluated
for the Southeast Issaquah Bypass.
7.1.6 Modal Share Sensitivity
This task will build upon the Transportation Demand Management (TDM) analysis
conducted as part of South SPAR/Sunset Interchange, and North SPAR EISs.
This analysis includes a sensitivity analysis of the broad effects of varying
travel demand assumptions such as ridesharing and transit mode shares in the
peak hour. This exercise will identify the range of potential demand for
alternative modes, and the range of effects on road system travel demand, and
support a preliminary estimation of the level of transit and other services
needed to justify the assumptions.
7.1.7 Evaluation of Alternatives for Transportation
Element
The alignment alternatives will be evaluated based on transportation criteria
related to the following areas:
Arterial operations including service to CITY planned land uses
Interchange operations
I–90 operations
Roadway alignment
Future transportation network operations
Public transportation service levels and operations
HOVs and park-and-ride facilities
Person throughput capacity,
Non-motorized transportation (including trails)
Traffic operations during construction (construction impacts)
Safety
Ease and impacts of construction phasing
Results of the transportation evaluation will be summarized in an evaluation
matrix.
Mitigating Measures
Qualitative analyses will be performed by the CONSULTANT to identify and
discuss the potential effectiveness of measures designed to mitigate any
significant adverse impacts of each of the alternatives.
High Capacity Transportation Improvements
As an independent task, the CONSULTANT will develop a scope and budget to
evaluate High Capacity Transportation Opportunities for nine potential project
areas. They include:
South Issaquah Park-and-Ride Lot
Southeast Issaquah Bypass
I-90 Sunset Interchange HOV Improvements
I-90 Front Street Interchange Ramp and Signal Improvements
Issaquah Park-and-Ride Lot Expansion
Non-Motorized Improvements
Grand Ridge Park-and-Ride Lot
South SPAR HOV Treatments
The CONSULTANT will develop a briefing paper identifying High Capacity
improvements at the areas listed above. The CONSULTANT will support two
workshops, developing agendas, providing staff support and facilitating
discussion to further identify the scope and potential benefits of these types
of improvements. The CONSULTANT will prepare preliminary sketches and order of
magnitude cost estimates for potential projects. The CONSULTANT will
incorporate the findings from the Workshop and the cost estimates and
sketches into a Technical Report.
PRODUCTS
Workshop support materials including Agendas and Briefing materials
Draft High Capacity Opportunities Technical Report (2 copies)
Final High Capacity Opportunities Technical Report (1 Camera Ready Copy)
Transportation Issue Support
The CONSULTANT will provide on-going support and advise on the following
transportation technical issues:
Access Management - The CONSULTANT will provide documentation and exhibits
supporting access management and provide examples of implementation of access
strategies. The CONSULTANT will be able to provide this information for Council
Briefings.
Evans Street connection - The CONSULTANT will document the localized changes
in travel patterns and resulting intersection operations related to connecting
Evans Street to the Southeast Issaquah Bypass.
Truck Access and Uses - The CONSULTANT will investigate the current
travel patterns of trucks and their potential use of the Southeast Issaquah
Bypass. The CONSULTANT will then identify design requirements to accommodate
trucks on the Bypass and identify benefits to alternative routes.
7.1.8 Transportation Technical Report
The CONSULTANT will prepare a technical report documenting the findings of
Task 7.1.2 to 7.1.7. The CONSULTANT will provide the CITY with 10 draft copies
of the report. The CITY will review and provide consolidated comments to the
CONSULTANT.
The CONSULTANT will submit 15 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for final
publication. The CONSULTANT will provide 15 copies of the Final Transportation
Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Transportation Technical Report (10 copies)
2nd Draft Transportation Technical Report (15 copies)
Final Transportation Technical Report (15 copies)
7.2 Air Quality
7.2.1 Methodology
The air quality analysis will meet the requirements of WAC 173-420. The
microscale analysis will be performed to determine carbon monoxide (CO)
concentrations using the EPA CAL3QHC or other EPA approved computer models.
Vehicular emissions will be computed by using the EPA's latest emission factor
algorithm - MOBILE5a. Predictions will be made at all identified receptors and
sensitive receptors for the maximum 1-hour and 8-hour periods. CO concentrations
will be predicted for the Build and No Action alternatives and will be completed
to STATE and National Ambient Air Quality Standards (NAAQS). Predictions of CO
concentrations will be made at intersections where the Level of Service (LOS) is
worse than LOS C. The air quality analysis will be developed in a format that
will allow it to be easily adapted to the needs of the environmental document.
For the microscale analyses, based on a review of traffic data, previously
developed or monitored air quality data, and the location of sensitive land
uses, the CONSULTANT will develop an initial list of four (4) potential analysis
sites (i.e., congested intersections, residential, and sensitive receivers)
adequate in number to allow complete, accurate and full air quality analysis and
submit it to the CITY for review. It is anticipated that from this list of sites
(which could be expanded to include the consideration of other locations
recommended for consideration by the CITY or others) a sufficient number of air
quality analysis sites will be chosen for detailed analysis. The final selection
of analysis sites will be made in consultation with the CITY. The following
information will be compiled for input into the Air Quality analysis:
LOS at intersections within the PROJECT limits where queues occur or
are expected to occur, including intersections with signals and stop
signs • Turning movement volumes for forecast years and alternatives at
intersections with signals and stop signs
Queue lengths developed from the 1994 Highway Capacity Manual;
AM and PM peak hour traffic volumes and speed estimates for both the
year of opening and the design year
Signal Phasing
Traffic signal cycle lengths
Intersection saturation flow rates
Air quality analyses will also be conducted at sensitive land use locations
directly adjacent to alternative alignments – with air quality levels estimated
at various distances from the right-of-way. These sites will be selected based
on traffic conditions, roadway geometry, and surrounding land uses.
Worst case meteorological conditions (i.e., wind speed, stability class,
ambient temperature, and persistence factor) and appropriate background levels
will be selected. The selection will be based upon review of the pertinent
meteorology and discussions with review agency personnel.
In consultation with the appropriate agency the proper credits to account for
the STATE's inspection and maintenance program, the STATE's anti-tampering
programs, and other inputs will be selected.
The Project Conformity Statement section will include the PROJECT's inclusion
in the pertinent conforming transportation plan and conforming transportation
improvements program (TIP), and relation to transportation control measures.
Note the emissions relationship between Build and No Action alternatives.
Indicate whether the PROJECT contributes to the reduction of frequency and
severity of violations of NAAQS (if any).
7.2.2 Affected Environment
Existing ambient air quality will be described qualitatively using available
monitoring data from the Puget Sound Air Pollution Control Agency and the
Washington State Department of Ecology (DOE). Existing CO levels will be
estimated by the CONSULTANT. At each of the analysis sites, existing maximum
one- and eight hour CO concentrations will be estimated. For the purpose of this
scope of work, it is assumed that two analysis hours will be modeled at each
location: weekday AM and PM peak periods. No field monitoring will be performed
as a part of this study. The discussion for the Affected Environment section
will include compliance status with the NAAQS as well as existing PROJECT area
attainment status.
7.2.3 Construction impacts
All impacts associated with construction of the PROJECT are to be addressed
in the Construction Impacts section. Under impacts, consider in general terms,
temporary construction effects such as (but not limited to) dust and particles,
slash disposal, burning, odors, emissions from construction equipment, and
emissions from asphalt plants, gravel plants, and other temporary stationary
sources. Discuss permit requirements. Under mitigation, describe mitigation
measures and commitments during construction such as dust abatement measures and
equipment pollution controls. Discuss mitigation measures considered or
available but not included and the reasons for non inclusion.
7.2.4 Long-Term Impacts
mesoscale Analysis
No mesoscale air quality modeling will be done for this project.
microscale Analysis
Carbon monoxide levels will be estimated by the CONSULTANT at each air
quality analysis site for each of the alternatives for the Southeast Issaquah
Bypass for the PROJECT's design year of 2015 and for the year of opening. At
each of the analysis sites, maximum one-and eight-hour CO concentrations will be
calculated for the AM and the PM peak.
Future CO levels estimated for each proposed alternative will be compared
with National Ambient Air Quality Standards (NAAQS), and with predicted
No–Action levels to determine the effects of each alternative.
The studies and Coordination section will include discussion of the National
Ambient Air Quality Standards (NAAQS) and non-attainment areas affected by the
PROJECT, the PROJECT's relation to the regional Transportation Plan and Regional
Transportation Improvement Program (TIP), the PROJECT's relation to the State
Implementation Program (SIP) requirements, including Transportation Control
Measures (TCM), and the method of air quality analysis. The air quality analysis
coverage will include a summary of conformity guidance. The following will be
included: site specific traffic, emissions, and concentration models used (microscale
analysis), assumptions used, and a map showing receptor locations. In
non-attainment areas, a summary of reference to the regional quantitative
analysis of the regional transportation plan and Transportation Improvement
Program (TIP), as documented in the latest TIP will be included. The results of
coordination with appropriate air quality agencies will be discussed in the
Studies and Coordination section.
7.2.5 Mitigation Measures
Qualitative analyses will be performed by the CONSULTANT to identify and
discuss the potential effectiveness of measures designed to minimize any
significant adverse impacts of each of the alternatives.
7.2.6 Air Quality Technical Report
The CONSULTANT will prepare a technical report documenting the results of
Tasks 7.2.1 to 7.2.5. The CONSULTANT will provide the CITY with 10 draft copies
of the report. The CITY will review the report and provide consolidated comments
to the CONSULTANT.
The CONSULTANT will submit 20 copies of submit a revised draft report to the
CITY for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT will submit 10 copies of the finalized report to the
CITY for distribution.
PRODUCTS
1st Draft Air Quality Technical Report (10 copies)
2nd Draft Air Quality Technical Report (20 copies)
Final Air Quality Technical Report (10 copies)
7.3 Noise
The EIS will complete a project-level noise analysis.
7.3.1 Methodology
The CONSULTANT will use FHWA and WSDOT-accepted noise analysis methodology
including STAMINA 2.0 noise prediction model. The following information will be
compiled for the Noise Analysis:
Traffic volumes for affected roadways;
Existing and future travel speeds;
Vehicle classification data;
7.3.2 Affected Environment
The CONSULTANT will conduct a reconnaissance of the PROJECT study area to
determine land uses to locate sensitive receptors, and determine their distances
from the proposed roadway alignments. The CONSULTANT will discuss with the CITY
any specific receptors that the CITY would like evaluated, including receptors
not immediately adjacent to the project area. All of the following land uses
must be identified: lands upon which serenity and quiet are of extraordinary
significance and serve as an important public need and where the preservation of
those qualities are essential if the area is to continue to serve its intended
purpose. Examples are picnic areas, recreation areas, playgrounds, active sports
areas, parks, residences, motels, hotels, schools, churches, libraries, and
hospitals. Selection of sensitive receptors for the study is based upon their
sensitivity to noise and their distance from the PROJECT. The CONSULTANT will
note physical and terrain features which may be altered during
construction and affect noise levels.
All measurements will be conducted for 15 minute sampling periods during
daytime off-peak hours (10 am to 4 pm) when traffic is moving freely. At each
measurement site, traffic counts will be conducted concurrently with the noise
measurements. Non-highway noise sources will be noted and measured. The
monitored noise levels will be adjusted to represent traffic noise levels during
peak hour traffic movements. Traffic volumes that were counted during the noise
measurement survey will be compared with the existing peak hour traffic volumes
and an adjustment will be made to the measured noise levels using the STAMINA
2.0 noise prediction or other approved model. Traffic counted during the noise
measurement will be used to calibrate the noise model. Existing peak hour
traffic will be used with speed limit speeds to calculate existing peak noise
levels. In locations where there are no existing roadways, the model output will
be used to represent the existing noise level.
7.3.3 Construction impacts
Construction activities that would result in noise impacts to nearby noise
sensitive land uses will be qualitatively assessed by the CONSULTANT in
accordance with CITY procedures.
7.3.4 Long-Terre impacts
The CONSULTANT will model the future year traffic noise level with and
without the proposed PROJECT using the FHWA STAMINA 2.0, or the most current
version, Highway Noise Prediction Model. Noise predictions will be modeled at
selected noise sensitive receptors and other noise sensitive land uses along the
corridor for each alternative alignment. Noise impact also will be modeled for a
number of residential receptors near Front Street to assess impacts in that
area. Modeled receptors must be adequate to assess all traffic noise impacts,
the noise levels at each of the impacted receptors, the increase in traffic
noise and amount of reduction to each outdoor area as a result of mitigation or
the lack of mitigation. Outdoor areas where future build noise levels would
exceed noise abatement criteria and those areas which will have a substantial
increase in predicted noise levels over existing noise levels will be identified
by the CONSULTANT for all land uses and impacts quantified.
7.3.5 Mitigation Measures
In accordance with FHWA requirements at locations along the alignments where
traffic noise impacts are predicted, noise abatement measures will be considered
and could include noise barriers, as well as other techniques. The CONSULTANT
will provide height, length, cost and benefits per impacted user for each
proposed barrier. It will contain a complete discussion of impacted areas that
do not meet the STATE criteria and specifically note reasons for not including
mitigation.
7.3.6 Noise Technical Report
The CONSULTANT will prepare a technical report documenting the results of
Task 7.3.1 – 7.3.5. The CONSULTANT will provide the CITY with 10 draft copies of
the report. The CITY will review and provide consolidated comments to the
CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 10 copies of the finalized Noise Technical
Report to the CITY for distribution. '
PRODUCTS
First Draft Noise Technical Report (10 copies) Second Draft Noise Technical
Report (20 copies)
Final Noise Technical Report (10 copies)
7.4 Land Use and Development
7.4.1 Affected Environment
The CONSULTANT will identify and document existing land use plans, policies
and related ordinances for all jurisdictions in the PROJECT area. To the extent
possible, documentation of land use will be coordinated with land use tasks
associated with the South Sammamish Plateau Access Road/I-90 Sunset Interchange
EIS and Design Report, and are expected to include the following:
1. Existing local land use plans, including the newly adopted City of
Issaquah Comprehensive Plan, zoning ordinances, and functional plans such as
the critical areas ordinance, drainage regulations and the Issaquah Area
Wildlife and Recreational Trails Plan
2. King County Comprehensive Plan
3. County-wide Planning Policies, as applicable
4. Issaquah Creek Basin and Non-Point Action Plan
5. West Tiger Mountain Natural Resource Conservation Area Management Plan
6. Proposed private development plans
7. Proposed private developments
8. Environmental documentation for the Grand Ridge project including the
Grand Ridge Joint Agreement, the Grand Ridge Annexation and Development
Agreement, and the Master Transportation and Finance Agreement.
The CONSULTANT will conduct a site reconnaissance to verify existing land
-use - information. Local jurisdictional staffs will be contacted to identify
any recently proposed projects in the area. Maps of existing land uses and
zoning will be prepared for the project area
The CONSULTANT will perform a "Relationship to Plans and Policies" analysis
that will address consistencies, inconsistencies, and potential inconsistencies
with applicable land use plans, policies, and ordinances. Documentation of
coordination with agencies will indicate that the preferred alternative is
compatible with, or will be made compatible with, all of the local plans,
policies, and ordinances. If any inconsistencies remain, actions to be taken for
resolution will be identified.
The CONSULTANT will inventory prime and unique farmlands in the corridor and
prepare a Form AD 1006 (Farmland Conversion Impact Rating), if necessary.
7.4.2 Construction Impacts
Temporary project impacts associated with construction of each of the
alternatives will be evaluated and documented by the CONSULTANT.
7.4.3 Long-Term Impacts
Long-term land use impacts associated with the two north and two south build
alternatives and the no build alternative will be evaluated and documented by
the CONSULTANT. Direct land use impacts to adjacent properties associated with
the footprint/right-of-way of each build alternative will be identified. Future
operation impacts related to issues such as noise, air, water, visual quality
and potential changes associated with corridor area mobility will also be
documented. Existing policies and proposed growth management plans including
development regulations and zoning will be considered when evaluating land use
impacts will be evaluated. Critical areas requirements and concurrence levels of
service will be summarized for use in other appropriate sections of the
environmental document. Potential indirect and cumulative impacts, such as
induced growth and development, will also be addressed.
7.4.4 Mitigation Measures
Mitigation measures for potential construction activity and long-term project
impacts will be developed and proposed by the CONSULTANT. Construction related
mitigation could be related to temporary disruptions, air and noise impacts,
traffic maintenance issues, and visual impacts. Mitigation measures for any
potential conflicts associated with comparison of PROJECT operational results
with the land use plans and level of service standards will be explored and
proposed.
7.4.5 Land Use and Development Technical Report
The CONSULTANT will prepare a technical report documenting the results of
Task 7.4 sub-tasks. The CONSULTANT will provide the CITY with 10 draft copies of
the report. The CITY will review and provide consolidated comments to the
CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 10 copies of the finalized Land Use and
Development Report to the CITY for distribution.
PRODUCTS
1st Draft Land Use and Development Technical Report (10 copies)
2nd Draft Land Use and Development Technical Report (20 copies)
Final Land Use and Development Technical Report (10 copies)
7.5 Wetlands
7.5.1 Wetland Identification and Delineation
Wetlands Reconnaissance
The CONSULTANT will conduct a reconnaissance of existing wetlands in the
project area. This Reconnaissance will be composed of a review of existing
literature and printed maps describing/depicting wetlands in the study area. The
CONSULTANT will also conduct a limited field study to confirm the relative
accuracy of the literature.
Wetlands Delineation
The CONSULTANT will delineate wetlands in the vicinities of the two build
alternatives using the methodologies described in the Corps of Engineers
Wetlands Delineation Manual (1987). The CONSULTANT will prepare data sheets,
a functions assessment, and written descriptions of delineated wetlands. The
CONSULTANT will survey wetland boundaries and prepare
map(s) of surveyed wetlands. The CONSULTANT will classify the wetlands
according to the U.S. Fish and Wildlife Service classification system (Cowardin
et al., 1979) and rate the wetlands using the Washington State Department of
Ecology's Wetlands Rating System.
Construction impacts
Temporary construction impacts on wetlands resulting from each alternative
shall be assessed by the CONSULTANT.
Long-Term impacts
Permanent, long-term impacts resulting from construction of project
improvements and the loss of existing wetlands shall be assessed by the
CONSULTANT. Indirect and cumulative impacts will also be assessed.
Mitigation Measures
Mitigation measures for potential short-term construction impacts and
long-term impacts shall be developed by the CONSULTANT. The CONSULTANT shall
determine mitigation ratios in accordance with recommendations made by the U.S.
Army Corps of Engineers and the CITY. The potential feasibility of mitigating
wetland impacts within the project corridor shall be assessed by the CONSULTANT,
but analysis and selection of mitigation sites shall not be conducted under this
subtask. The mitigation assessment under this subtask will provide the basic
information needed for subsequent, more detailed mitigation planning to be
conducted at a later date.
Wetlands Delineation Report
Prior to publication of the preliminary Draft EIS, the CONSULTANT will
prepare a draft Wetlands Delineation Report. The report will be submitted to the
CITY, WSDOT, and the USACOE for review and comment. The CONSULTANT will conduct
one site visit with the USACOE to verify wetland boundaries and classifications.
The draft report will be revised to incorporate the results of the
confirmation and will be completed for submittal with the preliminary Draft EIS.
The revised report will include discussions on construction impacts, long-term
impacts, indirect and cumulative impacts, and potential mitigation.
The CITY will provide consolidated comments on the revised draft report to
the CONSULTANT and CONSULTANT will revise the report for formal publication. The
CONSULTANT will provide 10 copies of the finalized Wetlands Delineation Report
to the CITY for distribution.
PRODUCTS
Draft Wetlands Reconnaissance Report (5 copies)
Final Wetlands Reconnaissance Report (20 copies)
1st Draft Wetland Delineation Report (10 copies)
2nd Draft Wetland Delineation Report (20 copies)
Final Wetland Delineation Report (10 copies)
7.6 Biological Resources (Wildlife and Vegetation)
7.6.1 Methodology
Methodologies to assess impacts to ecosystem elements will include literature
searches and field identification of wildlife and vegetation.
The CONSULTANT will map plant communities using aerial photographs (verified
by field work) in Task 7.6.2.1 to determine potential wildlife species using the
Wildlife Habitat Profile, and information pertaining to the West Tiger Natural
Resources Conservation Area provided by the King County Open Space Program
(Parks, Planning, and Resources Department, Natural Resources and Parks
Division, February 1987), Management of Wildlife and Fish in Forests of Western
Oregon and Washington, Appendix 8 (USDA Forest Service 1985), and data contained
in the East Sammamish Community Plan EIS and related studies.
7.6.2 Affected Environment Vegetation
Inventory will be taken of the vegetation community types in the corridor
vicinity. Vegetation will be mapped by the CONSULTANT using aerial photography;
mapped units will be field verified. The CONSULTANT will prepare
computer-generated map(s) of vegetation and will prepare a written description
of the vegetation.
Wildlife
The CONSULTANT will conduct a literature search and field identification of
wildlife and wildlife habitat features within the project corridor and adjacent
portions of Tiger Mountain.
An on-site investigation by the CONSULTANT will verify the results of an
aerial photographic interpretation of potential wildlife habitat. Field
investigations will be conducted to identify special habitat features such as
significant trees, snags, downed logs, nests, and ecotones. Evidence of wildlife
use in each vegetative community and along evident wildlife corridors will also
be noted. Following the preliminary and on-site investigations, a list of
wildlife characteristics of on-site vegetative communities will be generated.
Threatened and Endangered Species (T&E)
In compliance with the STATE's Endangered Species Program and the Federal
Endangered Species Act, T&E plant and animal species literature searches will be
undertaken. The U.S. Fish and Wildlife Service, the Washington State Fish and
Wildlife Department and the Washington State Department of Natural Resources
will be contacted.
7.6.3 Construction impacts
Temporary construction impacts resulting from the alternatives will be
assessed by the CONSULTANT. Vegetation and wildlife impacts resulting from
construction activities will be assessed by the CONSULTANT for on-site habitat
and wildlife corridors.
7.6.4 Long-Term Impacts
Permanent, long-term impacts on wildlife and vegetation resulting from the
construction of project improvements and the loss of existing habitat will be
assessed by the CONSULTANT. Indirect and cumulative impacts will also be
addressed.
7.6.5 Mitigation Measures
Mitigation measures for potential short-term construction impacts and
long-term impacts will be developed by the CONSULTANT with particular emphasis
on impacts to T&E vegetation and wildlife species.
7.6.6 Biological Resources Technical Report
The CONSULTANT will prepare a technical report documenting the results of
Tasks 7.6.1 to 7.6.5. The CONSULTANT will provide the CITY with 10 draft copies
of the report for review by the CITY. The CITY will review and provide
consolidated comments to the CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT will provide 10 copies of the finalized Biological
Resources Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Biological Resources Technical Report (10 copies)
2nd Draft Biological Resources Technical Report (20 copies)
Final Biological Resources Technical Report (10 copies)
7.7 Fisheries
7.7.1 Affected Environment
The CONSULTANT will conduct a literature search for information on fishery
resources in the project vicinity, perform field reconnaissance of the East Fork
and main stem of Issaquah Creek and unnamed tributaries to Issaquah Creek within
and near the project corridor and consult with affected Native American tribes.
The CONSULTANT will conduct the equivalent of a King County Level 1 Stream
Survey for two unnamed tributaries to Issaquah Creek that traverse the south end
of the proposed Bypass corridor. The CONSULTANT will flag the ordinary high
water mark of these tributaries. Electroshocking of fish and benthic analysis
will not be conducted as part of this analysis.
7.7.2 Construction impacts
Impacts of construction activities on fisheries will be assessed based on
anticipated temporary impacts to water quality in on-site and off-site streams,
and to placement of culverts (if any) in existing open water courses.
7.7.3 Long-Term impacts
Long-term impacts to fisheries will be assessed relative to anticipated
long-term water quality impacts and permanent alterations to stream channels (if
applicable). Indirect and cumulative impacts will also be addressed.
7.7.4 Mitigation Measures
Conceptual mitigation measures for impacts to fisheries will be proposed to
minimize and reduce potential negative construction and long-term impacts to the
quality of fish-bearing waters.
7.7.5 Fisheries Technical Report
The CONSULTANT will prepare a technical report documenting the results of
Tasks 7.7.1 to 7.7.4. The CONSULTANT will provide the CITY with 10 draft copies
of the report for review by the CITY. The CITY will review the report and
provide consolidated comments to the CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies and Native American tribes.
The CITY will provide consolidated comments and the CONSULTANT will revise the
report for formal publication. The CONSULTANT provide 10 copies of the finalized
Fisheries Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Fisheries Technical Report (10 copies)
1st Draft Fisheries Technical Report (20 copies)
Final Fisheries Technical Report (10 copies)
7.8 Water Quality (Surface and Ground Water)
This section of the Scope of Services addresses issues relating to surface
and ground water quality. Issues relating to ground and surface water
quantity are addressed in the sections: Drainage Design Facilities (Section
6.5.3), Waterways and Hydrological Systems (Section 7.12), and Floodplains
(7.1.4).
The CONSULTANT will conduct technical investigations of surface and ground
water quality issues on the PROJECT, including phosphorus loading impacts on
Lake Sammamish. The technical study addressing water quality will describe the
affected environment, potential impacts for alternatives considered and compared
and proposed mitigation. The Subtasks that will be involved in the water quality
investigations are outlined below.
7.8.1 Affected Environment
The description of the affected receiving water will include aspects of both
surface and ground waters. Because of special concerns about phosphorus in
stormwater runoff draining to Lake Sammamish, extra detail is needed in the
characterization of the existing phosphorus content in site area runoff. To the
extent possible, information and data developed for the Grand Ridge Water
Quality Technical report and for similar reports concurrently being developed
for the North and South SPAR projects will be used.
Existing surface and ground water quality in the PROJECT vicinity will be
characterized based on review of available reports and other data sources,
contacts with local experts familiar with the affected water bodies, and field
reconnaissance. Surface water quality conditions will be assessed for the East
Fork and main stem of Issaquah Creek, associated tributaries for which data is
available, and for Lake Sammamish. This assessment will focus on the PROJECT
areas potentially affected by construction of the Southeast Issaquah Bypass.
Existing ground water quality will be characterized for the project area
based on available data and reports. It is expected that the ground water
quality characterization will rely on data available from well records and from
information compiled for the Issaquah Creek Valley Ground Water Management Plan.
Measurements of on-site stormwater runoff pollutant concentrations will not be
collected for this PROJECT. Likewise, no new monitoring of ground water quality
will be conducted.
Soil samples will be collected at the site and analyzed for phosphorus
content to enable quantitative estimates of phosphorus delivery to the lake via
erosion. It is assumed that four soil samples will be collected at the PROJECT
site and analyzed for this study. Some or all of these samples may come from
depths beneath the ground surface representative of excavated road grade
elevations (i.e., the soils that will be exposed to precipitation for
long durations). It is assumed that the subsurface soil samples will be
collected by the geotechnicaI subconsultants' field crew in conjunction with
soil test pit work. The water quality subconsultant will coordinate with the
geotechnical subconsultant to specify the soil sample locations and provide the
sample containers. Following sample collection, the water quality subconsultant
will obtain the subsurface samples for delivery to a laboratory along with any
surface soil samples collected for the PROJECT.
7.8.2 Water Quality impacts
The analysis of surface water quality impacts will differentiate between
short-term construction impacts and long-term operational impacts. Construction
impacts will be quantified by estimating rates of soil erosion from disturbed
areas of the site using the Universal Soil Loss Equation, with input parameters
derived from literature references. The results of on-site soil sampling will be
used to support the erosion calculations and to determine the extent of
phosphorus transport that could be expected in runoff from disturbed areas.
Long-term surface water pollutant loadings and runoff concentrations will be
estimated for existing conditions and the development alternatives. Mass
loadings of several pollutants in site runoff will be estimated; the types of
pollutants to be analyzed will be determined in consultation with CITY staff.
These loading estimates will be based on loading factors derived from available
literature references and measurements of areas of various types of land cover.
Concentrations of these pollutants in runoff will also be estimated to enable
comparisons with STATE water quality standards.
The impacts of the proposed PROJECT on ground water quality will be evaluated
qualitatively based on knowledge of runoff characteristics, proposed storm
drainage systems, depths to ground water, and soil characteristics. The ground
water quality impact analysis will include evaluation of the long-term effects
of pollutants infiltrated in surface runoff and the potential for spills of
toxic materials to contaminate ground water. No analysis (i.e., modeling) of
subsurface contaminant transport will be conducted.
7.8.3 Phosphorus impacts
The total phosphorus loading in site runoff will be given greater emphasis in
the analysis of impacts than that provided for the other pollutants. The impacts
of the estimated phosphorus loadings on Lake Sammamish under each of the PROJECT
alternatives will be analyzed via comparisons with estimated watershed loadings
developed specifically for Lake Sammamish by the King County Department of
Metropolitan Services (released in August of 1995). The methods for estimating
phosphorus loadings and concentrations will, however, be the same as for the
other pollutants.
7.8.4 Water Quality /impacts Mitigation
Mitigation opportunities and recommendations will be developed for both
construction-phase and long-term operational impacts. These mitigation measures
will be discussed only in conceptual terms; runoff control facility designs will
be prepared in the Drainage Design Facilities portion of this Scope of Services
described under Section 6.5 - Preliminary Engineering.
7.8.5 Phosphorus /impacts Mitigation
Specific recommendations for mitigation of phosphorus-related impacts on
water quality will be provided in the technical report. If the potential impacts
are determined to be significant, estimates of spatial requirements for
phosphorus control facilities will be prepared.
7.8.6 Prepare Water Quality Technical Report
The CONSULTANT will prepare a technical report documenting the results of
tasks 7.8.1 through 7.8.5. The CONSULTANT will provide the CITY with 10 draft
copies of the report for review by the CITY. The CITY will review and provide
consolidated comments to the CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 10 copies of the finalized Water Quality
Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Water Quality Technical Report (10 copies)
2nd Draft Water Quality Technical Report (20 copies)
Final Water Quality Technical Report (10 copies)
7.9 Floodplains
7.9.1 Affected Environment
Issues related to the 100-year floodplain of East Fork Issaquah Creek in the
vicinity of the Sunset Interchange on Interstate 90 (the northern terminus of
the PROJECT) were adequately addressed in the Hydrologic Systems and Floodplains
Technical Report prepared for the South SPAR / Sunset Interchange project.
Therefore, floodplains issues associated with the East Fork will not be
addressed under this PROJECT. The floodplains analysis performed under this task
will focus on the main stem of Issaquah Creek and its tributaries in the project
area. Available floodplain mapping upstream, within, and downstream of the
project site prepared by King County Surface Water Management for the Issaquah
Creek Basin Plan and by FEMA will be used to characterize the existing 100-year
floodplain limits relevant to the proposed improvements. Hydraulic modeling of
stream flows will not be conducted for the purposes of calculating floodway
elevations. Field reconnaissance of the project site will be conducted to
confirm mapping of the existing 100-year floodplain limits.
7.9.2 Construction impacts
Impacts of construction activities floodplains will be assessed based on
anticipated impacts to streams, culverts, ditches, catch basins, and other
constructed drainage features in the site vicinity. If PROJECT construction
activities would occur within the 100-year floodplain limits of Issaquah Creek,
the probable area of floodplain that would be affected will be calculated. The
necessary permits to allow work within the 100-year floodplain will also be
detailed.
7.9.3 Long-Term impacts
The potential effects of proposed PROJECT improvements on the 100-year
floodplain of Issaquah Creek will be evaluated, including the potential for
flooding conditions to change downstream. The analysis will include specific
properties that could be affected in the immediate PROJECT area. The long-term
impacts of the PROJECT on natural and beneficial floodplain values will be
addressed. Exhibits showing the existing 100-year floodplain limits overlain
with proposed improvements will be included in the report. Cumulative and
indirect impacts will also be addressed.
7.9.4 Mitigation Measures
Mitigation opportunities and recommendations will be developed for potential
impacts on floodplain conditions. Mitigation measures will be discussed only in
conceptual terms; no design details or cost estimates will be prepared under
this task. Design details for surface water quantity controls will be addressed
under Task 6.5.3, Drainage Design Facilities.
7.9.5 Floodplains Technical Report
The CONSULTANT will prepare a Floodplains Technical Report documenting the
results of Tasks 7.9.1 through 7.9.4. The CONSULTANT will deliver 10 copies of a
draft report to the CITY for review. The CITY will review and provide
consolidated comments to the CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 10 copies of the finalized Floodplains
Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Floodplains Technical Report (10 copies)
2nd Draft Floodplains Technical Report (20 copies)
Final Floodplains Technical Report (10 copies)
7.10 Preliminary Environmental Site Assessment
The CONSULTANT will conduct an inventory of existing hazardous materials in
the Southeast Issaquah Bypass road corridor. The CONSULTANT will evaluate the
historic use of the corridor and relevant adjacent properties by review of
public records, aerial photographs and historic maps. The CONSULTANT will
conduct a field reconnaissance of the road corridor and associated structures to
evaluate the potential affected environment and risk levels for hazardous
materials.
Based on the review and field investigation, the CONSULTANT will prepare a
technical report summarizing the results of this investigation for CITY review.
The report will include a discussion of the following:
7.10.1 Review Available Information
Review readily available geotechnical or environmental reports for
the subject site including information provided by the City of Issaquah.
7.10.2 Regulatory List Review and Visual
reconnaissance
Review appropriate federal and state environmental databases for
listings of known or suspected environmental problems at the subject
site or nearby properties.
Review historical information including aerial photographs, fire
insurance maps, USGS (United States Geological Survey) maps and city
business directories, as available and appropriate, to identify past
development history on and adjacent to the site relative to the possible
use, generation, storage, release or disposal of hazardous materials.
Review the site property history and interview up to two current
property owners or others familiar with past and present uses of the
project corridor and the area immediately surrounding it.
Identification of the source(s) of potable water for the project
corridor and the type and age of the sewage disposal system(s) used
within the project corridor from appropriate information resources.
A visual reconnaissance of the site and adjacent properties to
identify any visible signs of possible contamination and potential
sources of contamination.
A written opinion regarding the potential environmental impacts
associated with the project construction and operation based on the
results of our study. We also will provide general recommendations for
project mitigation, as appropriate, depending on the potential
environmental impacts during construction and operation.
Recommendations for further environmental study, as needed, regarding
subsurface exploration and laboratory testing.
7.10.3 Draft preliminary ESA Report
The CONSULTANT will prepare a Preliminary Environmental Site Assessment
documenting the results of the task. The CONSULTANT will deliver 2 copies of a
draft report to the CITY for review. The CITY will review and provide
consolidated comments to the CONSULTANT.
7.10.4 Final Preliminary ESA Report
The CONSULTANT will submit 6 copies of a revised draft report to the CITY for
distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 6 copies of the finalized Preliminary
Environmental Site Assessment to the CITY for distribution.
PRODUCTS
1st Draft Preliminary Environmental Site Assessment (2 copies)
2nd Draft Preliminary Environmental Site Assessment (6 copies)
Final Preliminary Environmental Site Assessment (6 copies)
7.10.5 Geotech Design Environmental Studies
The following tasks will be conducted after the completion of the Preliminary
Environmental Site Assessment to meet the environmental needs of the project.
Conduct detailed site reconnaissance in the vicinity of residential
structures located along the alignment with regard to the potential
presence of hazardous materials that may impact soil and ground water
conditions at the site.
Conduct detailed interviews with a representative of the Issaquah
Sportsman Club and property owners or tenants of the residential
structures located along the alignment with regard to site history.
Drill two soil borings along the alignment located adjacent to the
Issaquah Sportsman Club. Install ground water monitoring wells. Obtain
ground water samples and submit for chemical testing of lead and other
potential contaminants.
Analyze the results of the test data with respect to current
regulatory criteria.
PRODUCTS
Prepare a memorandum/report summarizing the results of our reconnaissance,
interviews and ground water monitoring, along with our conclusions and
recommendations.
7.11 Historic, Archaeological, and Cultural Resources
Cultural resources in the proposed PROJECT area will be assessed by the
CONSULTANT using an approach combining archival research, agency coordination
and field reconnaissance.
Completion of Section 106 coordination for the proposed SE Bypass alignments
by Northwest Archaeological Associates (NWAA) as indicated in the attached scope
and budget dated July 5, 1999. NWAA will review the assessment of effects on the
White Swan Inn and the Issaquah Sportsman's Clubhouse, and complete consultation
with the Office of Archaeology and Historic Preservation and interested parties.
This will include a site visit to the Issaquah Sportsman's Clubhouse,
preparation of the Section 4(f) evaluation, and the Memorandum of Agreement if
necessary.
7.11.1 Archival and Literature Review-Research
Research will be conducted by the CONSULTANT to identify existing cultural
resources (archaeological resources) in, and adjacent to, the corridor study
area and to deterrnine the probability for cultural resource, including
archaeological sites and historic structures. Ethnographies, local histories,
maps, and government documents will be consulted. Repositories to be accessed
will include Special Collections, Suzzallo Library, University of Washington;
King County Public Library System; and Washington State Office of Archaeology
and Historic Preservation (OAHP).
7.11.2 Field Survey
A systematic field reconnaissance will be conducted by the CONSULTANT to
identify previously recorded and/or unrecorded archaeological sites for the
corridor where undeveloped surface is available. All new sites would be mapped,
photographed, and recorded on Washington State Archaeological Inventory forms
and submitted to the OAHP for Smithsonian numbers. Soil coring and willow pit
excavations will be used where appropriate in the opinion of the archaeologist.
7.11.3 Agency Coordination
A technical report will be prepared by the CONSULTANT, describing cultural
resources identified in the corridor, using the OAHP standards. The report would
include summary background information appropriate to a cultural resources
assessment of the study area, including a description of the PROJECT,
environment, ethnography/ethnohistory, previous archaeology and history,
methodology, results of the investigation, and maps of the sites located.
Pertinent graphics and photographs will also be included. Project impacts from
construction and/or operation will be discussed, and recommendations will be
extended for sites that have been, located that are listed on or
eligible for the National Register of Historic Places (NRHP).
Coordination will be undertaken with the CITY, County and the OAHP to
determine not only the existence of historic properties, but the likelihood of
adverse effects to extant historic properties within and/or adjacent to the
PROJECT area. Cultural resource personnel at the CITY, King COUNTY and OAHP
would be consulted for information on Historic properties and their opinions on
eligibility. Any affected tribes will also be contacted for their insight into
the ethnohistoric potential of the area and to determine the existence of
traditional cultural properties. If the Section 106 process is triggered, a
Section 106 Report will be prepared and agency coordination will also include
the Advisory Council on Historic Preservation (ACHP).
7.11.4 Historical, Archaeological, and Cultural
Resources Technical Report
The CONSULTANT will prepare a technical report documenting the results of the
task. The CONSULTANT will provide the CITY with 5 draft copies of the report for
review-by the CITY. The CITY will review and provide consolidated comments to
the CONSULTANT.
The CONSULTANT will submit 10 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 5 copies of the finalized Historical,
Archaeological, and Cultural Resources Technical Report to the CITY for
distribution.
PRODUCTS
1st Draft Historical, Archaeological, and Cultural Resources Technical Report
(5 copies) 2nd Draft Historical, Archaeological, and Cultural Resources
Technical Report (10 copies) Final Historical, Archaeological, and Cultural
Resources Technical Report (5 copies)
Draft Section 106 Report (if required) (5 copies)
Final Section 106 Report (if required) (10 copies)
7.12 Waterways and Hydrological Systems (Surface and Groundwater Quantity)
This section addresses issues relating to surface and surface water
Quantity. Issues relating to surface and groundwater quality are addressed
in Water Quality (Section 7.8).
7.12.1 Affected Environment
Existing surface and ground water quantity characteristics in the PROJECT
vicinity will be determined based on available reports, contacts with local
experts, and field reconnaissance. The characterization of surface water
hydrologic conditions in the PROJECT area prepared by the CONSULTANT will focus
on existing drainage patterns, including constructed drainage systems, and
documented stream flow data for the East Fork and main stem of Issaquah Creek.
Quantitative information on surface water drainage will be supplied from work
completed under Task 6.5.3, Drainage Design Facilities.
The description of existing ground water conditions prepared by the
CONSULTANT will focus on depths to ground water, locations of existing water
wells, areas of significant recharge potential, and general subsurface flow
patterns in the PROJECT area. It is assumed that descriptions of geologic
characteristics as they relate to local ground water conditions will be provided
by others.
7.12.2 Construction Impacts
Impacts of construction activities on surface drainage systems will be
assessed based on anticipated impacts to streams, culverts, ditches, catch
basins, and other constructed drainage features in the site vicinity. Erosion
calculations prepared for the Water Quality Technical Report (Task 7.8.2) will
be referenced to assess potential reductions in flow conveyance capacity of
these drainage systems. Impacts of construction activities on ground water flow
conditions will not be addressed in this section as they are considered to be
negligible.
7.12.3 Long-Term Impacts
Potential long-term operational impacts on surface and ground water resources
will be analyzed. This analysis will focus on potential changes in surface water
flows and ground water recharge that may occur within the immediate PROJECT
area, and the associated effects on streams and ground water supplies for local
well users. Potential impacts to surface waters and local ground water supplies
will be estimated by calculating average surface runoff and infiltration volumes
in the site area under existing conditions and post-developed conditions for
each of the PROJECT alternatives. Estimated differences in surface water runoff
volumes will be used to characterize the potential for stream flow changes in
Issaquah Creek and its tributaries within the PROJECT limits. Likewise,
estimated differences in infiltration volumes will be used to represent
reductions or increases in shallow ground water recharge. Modeling of subsurface
flow patterns and water table fluctuations will not be conducted. Indirect and
cumulative impacts will also be addressed.
7.12.4 Mitigation Measures
Mitigation opportunities and recommendations will be developed for potential
impacts on surface water flows and ground water flow conditions. Mitigation
measures will be discussed only in conceptual terms; no design details or cost
estimates will be prepared under this task. Design details for surface water
quantity controls will be addressed under Task 6.5.3, Drainage Design
Facilities.
7.12.5 Waterways and Hydrologic Systems Technical
Report
The CONSULTANT will prepare a Waterways and Hydrologic Systems Technical
Report documenting the results of Tasks 7.12.1 through 7.12.4. The CONSULTANT
will deliver 10 copies of a draft report to the CITY for review. The CITY will
review and provide consolidated comments to the CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 10 copies of the finalized Waterways and
Hydrologic Systems Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Waterways and Hydrologic Systems Technical Report (10 copies)
2nd Draft Waterways and Hydrologic Systems Technical Report (20 copies)
Final Waterways and Hydrologic Systems Technical Report (10 copies)
7.13 Earth
7.13.1 Affected Environment/Impacts
The CONSULTANT will prepare a description of the geologic setting and
potential geologic hazards based on the information compiled in Task 6.3. Maps
showing the surficial geology and soils will be prepared and each of the soil
types will be described. Description of problems in the project area and
recommendations on areas that should be avoided, including steep slope areas,
landslide hazard areas, erosion hazard areas, seismic hazard areas and coal mine
hard areas will be prepared. Impacts of each alternative on geology and soils
will be identified. Mitigation measures including retaining structures and
temporary and permanent erosion control will be described.
Based on the review and detailed investigation, the CONSULTANT will prepare a
technical report summarizing the results of this investigation for CITY review.
The report will include a discussion of the following:
Evaluation of geomorphic processes that are currently active on and
adjacent to the site (affected environment).
Description of long-term and construction related impacts for
project.
Description of unavoidable earth- and ground water-related adverse
impacts associated with the proposed project and alternatives.
Evaluation and description of potential measures to mitigate
identified adverse impacts.
7.13.2 Draft Earth Technical Report
The CONSULTANT will prepare an Earth Technical documenting the results of the
task. The CONSULTANT will deliver 5 copies of a draft report to the CITY for
review. The CITY will review and provide consolidated comments to the
CONSULTANT.
7.13.3 Final Earth Technical Report
The CONSULTANT will submit 10 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 5 copies of the finalized Earth Technical
Report to the CITY for distribution.
PRODUCTS
1st Draft Earth Technical Report (5 copies)
2nd Draft Earth Technical Report (10 copies)
Final Earth Technical Report (5 copies)
7.14 Additional Studies
7.14.1 Energy
The CONSULTANT will prepare an analysis of the direct and indirect energy
impacts and the energy conservation potential of each of the alternatives.
7.14.2 Visual
The CONSULTANT will provide an assessment of the visual impacts of each
alternative. The approach will be to:
Identify the major vantage points, or view sheds
Identify visually sensitive landscape settings
Describe major existing and future No–Action visual elements
Discuss the PROJECT impacts with respect to potential views of and
from the roadway and interchange
Discuss illumination and glare caused by the alternatives
Include visual simulations of the hillside impacts caused by proposed
improvements
Address issues related to the re-establishment of vegetation and
landscaping
Discuss alternative aesthetic treatments to mitigate impacts, if
warranted
The following criteria will be used to provide relative comparisons among the
alternatives:
Vividness
Intactness
Unity
7.15 Displacement and Relocation
7.15.1 Draft Displacement and Relocation Report
The CONSULTANT will analyze the implications of two build alternative's and
one no-build alternative's right-of-way requirements on businesses and
residences, in study area following WSDOT guidelines, and NEPA requirements. The
report will include the estimated number of households and businesses displaced,
a discussion of comparable available housing in the area, affected
neighborhoods, public facilities, non-profit organization and families having
special composition.
Residential displacements will be identified by property owner and parcel
number. Business displacements will fall into two categories: the direct taking
of the business or and the taking of the business due to loss of access. For
each business, and a list will be prepared identifying the business, the type of
business, and the number of employees. Availability of similar replacement
facilities will be evaluated.
The mitigation section will identify measures which conform to the Uniform
Relocation Assistance and Real Property Acquisition Policies Act of 1970 and
non-discrimination guidelines.
The CONSULTANT will prepare a draft technical report, and will provide the
CITY with 10 copies of the report for review. The CITY will review and provide
consolidated comments to the CONSULTANT.
7.15.2 Final Displacement and Relocation Report
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 10 copies of the finalized Displacement and
Relocation Report to the CITY for distribution.
PRODUCTS
1st Draft Displacement and Relocation Technical Report (10 copies)
2nd Draft Displacement and Relocation Technical Report (20 copies)
Final Displacement and Relocation Technical Report (10 copies)
7.16 Social Elements
7.16.1 Affected Environment
The CONSULTANT will describe the existing social environment of the project
area and surrounding community, including neighborhood structure, recreational
facilities, public services, and growth and development potential.
The CONSULTANT will collect demographic and employment data from the PSRC and
King County as available. U.S. Census Bureau data for affected areas will be
obtained and reviewed. Corridor land use plans, housing plans and any
redevelopment plans will be identified and documented. Documented demographic
characteristics would include household size and composition, ethnic mix and
age.
7.16.2 Impacts
Community Cohesion
The CONSULTANT will address the PROJECT's potential impacts to community
cohesion and community character as result of possible splitting of
neighborhoods, isolating a portion of a neighborhood, and potential incompatible
development within the neighborhood. Regional and community growth patterns will
be described. Population changes anticipated or accommodated as a result of the
proposed project will be analyzed qualitatively.
Executive Order 12898 (Environmental Justice)
Using available Census and regional planning data, the CONSULTANT will
inventory the population affected by the proposed project, including
identification of the proportion of low income minorities. The CONSULTANT will
address Environmental Justice dealing with the PROJECT's potential to
disproportionately affect minority or low-income persons.
Title VI
The CONSULTANT will address the Title VI of the Civil Rights Act dealing with
the PROJECT's potential to discriminate against persons based on their race,
color, national origin, sex, age, or disability, in terms of impacts on
transportation, housing, community, and health and social services.
Services and Utilities
The CONSULTANT will describe how each public service, including schools,
police and fire protection, ambulance, and public or private busses, will be
affected by the PROJECT, including service disruptions, circuitry of access,
changes in service and travel times both during and after construction, changes
in service area, and the need for any new or additional services.
The CONSULTANT also will describe impacts to existing or proposed utilities,
including natural gas, electrical power, telephone, cable television, water
supplies, sanitary and storm sewer, and solid waste routes.
Recreation
The CONSULTANT will identify all the parks, open spaces and recreation
facilities in the PROJECT area. The inventory will describe the location, the
function, the significant features, type of facility and population served. The
CONSULTANT also will identify and document existing recreational trails, current
ownership/plan status and condition, volumes of use, etc. for use in addressing
potential construction and long-term impacts.
7.16.3 Mitigation Measures
Mitigation measures for potential construction and long-term impacts will be
developed and proposed by the CONSULTANT.
7.16.4 Social Elements Discipline Report
The CONSULTANT will prepare a draft technical report, if needed, documenting
the results of Tasks 7.17.1 to 7.17.3. The CONSULTANT will provide the CITY with
10 copies of the report for review. The CITY will review and provide
consolidated comments to the CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 10 copies of the finalized Social Elements
Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Social Elements Technical Report (10 copies)
2nd Draft Social Elements Technical Report (20 copies)
Final Social Elements Technical Report (10 copies)
7.17 Section 4(f) Resources
7.17.1 Affected Environment
It is assumed the consultant will be required to prepare a Section 4(f)
evaluation addressing potential impacts to recreational sites, and any
feasible and prudent alternatives. The CONSULTANT will identify and describe
each Section 4(f) resource in the project area, their function, facilities,
access, relationship to other similarly used lands in the vicinity, applicable
causes affecting ownership, and any unusual characteristics that reduce or
enhance their value.
7.17.2 Construction Impacts
Short-term impacts on Section 4(f) resources associated with construction of
each of the alternatives will be evaluated and documented by the CONSULTANT.
Factors to be considered in may include acquisition of land and facilities,
access, aesthetics, air quality, noise, water, and land use in the vicinity.
7.17.3 Long-Term Impacts
Long-term impacts on Section 4(f) resources associated with the two build
alternatives and the no build alternative will be evaluated and documented by
the CONSULTANT. Factors to be considered may include acquisition of land and
facilities, access, aesthetics, air quality, noise, water, and land use in the
vicinity. Potential indirect and cumulative impacts to land uses resulting from
the PROJECT will also be addressed.
7.17.4 Mitigation Measures
Mitigation measures for potential construction and long-term impacts will be
developed and proposed by the CONSULTANT. Mitigation for Section 4(f) resources
will include a discussion of avoidance alternatives and their impacts, and
possible measures to minimize impacts. If the preferred alternative includes
Section 4(f) resources, the final Evaluation will include a discussion of why
alternatives that avoid or reduce Section 4(f) impacts are not feasible or
prudent.
7.17.5 Section 4(f) Evaluation
The CONSULTANT will prepare a Section 4(f) Evaluation documenting the results
of Task 7.18.1 to 7.18.4. The CONSULTANT will provide the CITY with 5 draft
copies of the Evaluation for review. The CITY will review and provide
consolidated comments to the CONSULTANT.
The CONSULTANT will submit 10 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 5 copies of the finalized Section 4(f)
Evaluation to the CITY for distribution.
PRODUCTS
1st Draft Section 4(f) Evaluation Report (5 copies)
2nd Draft Section 4(f) Evaluation Report (10 copies)
Final Section 4(f) Evaluation Report (5 copies)
7.18 Economic Elements
7.18.1 Existing Conditions
The CONSULTANT will use existing applicable information to describe the
existing economic conditions in the project area, including number and type of
businesses, employment, property values and tax base. The role of the proposed
roadway plays in the overall economic activity of the PROJECT area will be
documented with an emphasis on access to major land use categories. Data
outlining the capacity enhancements provided by the proposed improvements will
be evaluated against potential impacts on the economic vitality of the corridor
and region.
7.18.2 Construction Impacts
Short-term economic impacts associated with construction of each of the
alternatives will be evaluated and documented by the CONSULTANT.
7.18.3 Long-Term Impacts
Long-term economic impacts associated with the two build alternatives and the
no build alternative will be evaluated and documented by the CONSULTANT. Impacts
associated with long-term changes in traffic and shaping patterns, loss of
businesses and jobs as a result of Right-of-Way acquisition, long term
employment, and business growth will be addressed. Potential indirect and
cumulative impacts resulting from the PROJECT will also be addressed.
7.18.4 Mitigation Measures
Mitigation measures for potential impacts on economic activity and employment
will be developed and proposed by the CONSULTANT.
7.18.5 Economics Technical Report
The CONSULTANT will prepare a draft technical report, if needed, documenting
economic conditions and impacts. and will provide the CITY with 5 copies of the
report for review. The CITY will review and provide consolidated comments to the
CONSULTANT.
The CONSULTANT will submit 10 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT provide 5 copies of the finalized Economics
Technical Report to the CITY for distribution.
PRODUCTS
1st Draft Economics Technical Report (5 copies)
2nd Draft Economics Technical Report (10 copies)
Final Economics Technical Report (5 copies)
7.19 Biological Assessment
7.19.1 Affected Environment
The CONSULTANT will perform a biological assessment for any threatened or
endangered plant and animal species identified in the project area, in
compliance with 50 CFR, Part 402 which establishes the procedural regulations
governing interagency cooperation under Section 7 of the Endangered Species Act.
This assessment will involve a general evaluation of species that could
potentially be present in the project area. Based on available information, it
is expected that no federally listed species are present in the immediate
project area, with the exception of several salmon species that are under
consideration for federal listing.
The CONSULTANT will coordinate with experts and agency staff to identify
species and will conduct a field investigation.
7.19.2 Construction Impacts
Temporary impacts resulting from the construction of each alternative will be
assessed on a general basis by the CONSULTANT.
7.19.3 Long-Term Impacts
Permanent, long-term impacts will be assessed on a general basis by the
CONSULTANT. Potential indirect and cumulative impacts to threatened and
endangered species resulting from the project will also be addressed. If
threatened or endangered species are present in the project area, extensive
mitigation measures may be required. Development of those mitigation measures is
not included in this scope of work.
7.19.4 Mitigation Measures
The need for mitigation measures for potential construction and long-term
impacts will be assessed by the CONSULTANT.
7.19.5 Biological Assessment Report
The CONSULTANT will prepare a Biological Assessment report documenting the
results of Tasks 7.7.1 to 7.7.4. The CONSULTANT will provide the CITY with 10
draft copies of the draft Assessment for review by the CITY. The CITY will
review and provide consolidated comments to the CONSULTANT.
The CONSULTANT will submit 20 copies of a revised draft report to the CITY
for distribution and review by cooperating agencies. The CITY will provide
consolidated comments and the CONSULTANT will revise the report for formal
publication. The CONSULTANT will provide 10 copies of the finalized Biological
Assessment to the CITY for distribution. .
PRODUCTS
First Draft Biological Assessment (10 copies)
Second Draft Biological Assessment (20 copies)
Final Biological Assessment (10 copies)
TASK 8 DRAFT ENVIRONMENTAL IMPACT STATEMENT
8.1 Preliminary Draft EIS Document Preparation
The Draft EIS will follow the format consistent with the revised WSDOT
Environmental Impact Statement Outline (March 1993), WSDOT EIS Format
Guidelines, and FHWA Technical advisory T6640.8A. The CITY will provide
close coordination with WSDOT and FHWA throughout the process. The document will
be in compliance with SEPA and NEPA.
The Draft EIS is anticipated to include the following sections and appendices
(however the final EIS format may change in response to the CITY's needs):
8.1.1 Introductory Material and NEPA Chapters 1 and 2 Cover Letter
A one-page cover sheet will be the first page of the DEIS and will indicate
the necessary information to allow the identification of PROJECT name,
responsible parties and the date that comments on the DEIS are due, as required
under NEPA and SEPA. Following the cover sheet will be a SEPA Fact Sheet.
Following that will be a page with the ADA logo and message and a metric unit
message on the reverse side.
Title Sheet (for signatures)
This sheet will conform to the content and format specified in the FHWA
Technical Advisory T 6640.8A. It will be restricted to one side of one
right-hand page. Signature lines will be provided for the City, State, and FHWA
administration officials.
Fact Sheet
The content and format of the Fact Sheet will conform to SEPA rules, WAC
197-11-440.
Table of Contents
This section will include a table of section and subsection headings, and a
list of tables and figures.
Chapter 1: History and Purpose of the Proposed Action
This section will identify and describe the proposed action and the
transportation problems or other needs which it is intended to address. This
discussion should clearly demonstrate that a need exists for the PROJECT and
describe the problems which it is to correct. This section will be written in
terms understandable to the general public.
Chapter 2: Alternatives
The EIS will describe the roadway and other transportation alternatives under
consideration for the SE Bypass. The analysis will focus on identifying impacts
and mitigation measures and providing information appropriate to choosing a
preferred alternative from among roadway design concepts and non-roadway
alternatives. The description of the alternative design concepts will be in
sufficient detail to allow identification of the specific characteristics of
each design concept to be evaluated. These characteristics include PROJECT
layout, roadway and interchange configurations, structural measures and other
related road facilities. This will include maps, alignment drawings, road
sections, cost estimates, a proposed construction schedule with milestones, and
other exhibits to allow the alternatives to be identified.
The Alternatives Chapter will also summarize the NEPA/SEPA 404 Avoidance and
Alternatives Analysis (Section 7.5.2.2 of this Scope of Work). This analysis
will describe other alternatives considered and why they were eliminated from
further consideration and detailed study.
8.1.2 Chapter 3: Affected Environment
This section will concisely describe the existing social and environmental
setting for the area affected by all alternatives presented in the EIS. The
following elements of the environment will be discussed: transportation, air
quality, noise, energy, geology and soils, water quality (surface and ground
water), flood plains, waterways and hydrological systems (surface and ground
water quantity), wetlands, wildlife, fisheries, vegetation, T&E species, land
use, social elements, archaeological and historical elements, hazardous
materials, and visual quality. It will also discuss the adopted land use and
transportation plans as they relate to the proposed PROJECT. These discussions
will be limited to data, information, issues, and values which will have a
bearing on possible impacts, mitigation measures, and on the selection of an
alternative. Information on each element of the affected environment will be
drawn from the EIS Technical Reports prepared in Task 7.
8.1.3 Chapter 4: Environmental Consequences
Project Impacts
This section will document direct, long-term impacts associated with the two
build alternatives and the no-action alternative. Each element or major
sub-element described in Task 7 of this Scope of Work will be discussed. The
environmental effects of each alternative, including probable unavoidable
adverse impacts and the potential benefits of the alternative, will be
described, as will measures to mitigate adverse impacts. The discussions will
include any major assumptions made and supporting information on the validity of
the environmental assessment methodology used. If details beyond those included
in the affected Environment chapter are necessary to clarify the impacts,
they will be addressed in this chapter. For each element of the environment each
alternative will be analyzed separately.
Construction Impacts
This section will discuss the temporary impacts associated with the
construction of the two build alternatives. These impacts include dust and
particles, noise, energy, erosion and sedimentation, traffic congestion,
detours, safety, disposal of excavated materials, and other construction related
impacts. This section will also discuss impacts caused by project staging.
Mitigation measures and commitments during construction, such as dust abatement
and measures and noise and pollution controls.
Irreversible and Irretrievable Commitment of Resources
This section will discuss in general terms the irreversible and
irretrievable commitment of natural, physical, human, and fiscal resources that
would result from each of the alternatives.
Relationship of Short-Term uses of the Environment and Long-Term Productivity
This section will discuss in general terms the relationship between local
short-term impacts and use of resources, and maintenance and enhancement of
long-term productivity for each of the alternatives.
Indirect and Cumulative Impacts
This section will discuss indirect and cumulative impacts, and any associated
mitigation measures, to environmental resources that function as integral parts
of a larger system.
8.1.4 Closing Sections Public and Agency
Coordination
This section will summarize the results of coordination with federal, state,
and local agencies, their level of involvement, and any unresolved issues or
areas of conflict. This section will also address the results of the scoping
process and public involvement process.
List of
Preparers
EIS Distribution List
Appendices
8.1.5 Summary
This section will include a brief description of the proposed action, other
governmental agencies actions in the geographic area, a summary of alternatives
and options considered, summary of major environmental impacts in table format
with proposed mitigation measures, areas of concern or controversy, unresolved
issues, list of required permits, and a list of other actions required for the
proposed PROJECT.
8.1.6 First Draft for Client Review
The CONSULTANT will produce a first preliminary Draft EIS and submit 10
copies to the CITY for review of format and content.
PRODUCTS
Preliminary Draft EIS (15 copies)
8.2 Draft Environmental Impact Statement
8.2.1 Draft EIS for Client Review
The CITY will provide consolidated comments on the Preliminary Draft EIS to
the CONSULTANT. The CONSULTANT will make requested revisions and prepare a
camera-ready draft EIS for review by the CITY.
8.2.2 Publish Draft EIS
Upon approval of the camera ready draft, the CONSULTANT will reproduce a
Final Draft EIS for distribution. The CITY will provide the
distribution list and be responsible for distributing the document to the
agencies and the public.
PRODUCTS
1st Draft Environmental Impact Statement (1 Camera Ready and 5 copies)
Final Draft Environmental Impact Statement (150 copies)
8.4 Draft Environmental Impact
Statement/Section 404 Hearing
An open house will be conducted following publication of the Draft EIS. The
CONSULTANT will prepare materials for the open house and provide originals to
the CITY for reproduction and distribution. Relevant activities will include:
Preparing hearing packet
Developing and mailing notices
Preparing exhibits and handouts
Coordinating/attending an Open House
TASK 9 FINAL ENVIRONMENTAL IMPACT STATEMENT
9.1 Respond to Comments on Draft EIS
The CITY will provide the CONSULTANT with the comment letters and public
hearing testimony on the DEIS. Revisions to the Draft EIS will be based on the
comment letters, public hearing testimony and agency comments received during
the review period.
The CONSULTANT will compile a summary of comments received on the Draft EIS,
provide responses to comments, and make recommendations on additional studies to
be completed. Where appropriate, the participating agencies will prepare
responses to comments and the CONSULTANT will include the responses in the Final
EIS. For budgeting purposes, it is assumed that there will be a maximum of 100
comment letters. If there are more than 100 comment letters, this extra level of
analysis will be considered "extra work."
9.2 Revise Analysis of Discipline Issues
The consultants shall revise the discussion of the various elements of the
EIS, if necessary, to reflect changes in the project design, impacts, and
proposed or required mitigation that have occurred since publication of the
Draft EIS. Any proposed additional studies and detailed analyses will be
considered "extra work."
9.3 Prepare Preliminary Final EIS Document
The CONSULTANT will prepare a preliminary Final EIS for review by the CITY
and appropriate agencies. The EIS will incorporate changes that reflect changes
in the PROJECT scope, impacts, technical analysis and mitigation analysis that
have occurred since the DEIS. The Final EIS will include comments received on
the Draft EIS, a summary of the comments, responses to comments, and an updated
fact sheet.
PRODUCTS
Preliminary Final Environmental Impact Statement (25 copies)
9.4 Final EIS Production
The CITY will provide consolidated comments on the preliminary Final EIS to
the CONSULTANT. The CONSULTANT will revise the preliminary Final EIS to address
the CITY's comments and prepare a camera ready Final EIS. The CITY will conduct
a second review to check and approve the changes and authorize reproduction and
issuance of the Final EIS.
The CONSULTANT will make the second, minor revisions based on the review and
reproduce 150 copies of the FEIS for distribution. The CITY will provide the
distribution list for the FEIS and will be responsible for distributing the
document to the public and agencies.
PRODUCTS
Camera Ready Final Environmental Impact Statement (1 camera ready
and 5 copies)
Final Environmental Impact Statement (150 copies)
9.5 Record of Decision
The CONSULTANT will assist the CITY in preparation of the draft NEPA Record
of Decision (ROD) that will accompany the Final EIS through the review and
approval process.
PRODUCTS
Draft Record of Decision
TASK 10 NEPA/SEPA/404 MERGER PROCESS
Based on preliminary determination by the USACOE, WSDOT, and FHWA, the SE
Bypass EIS is not required to comply with the "Interagency Working Agreement to
Integrate Special Aquatic Resources (404) Permit Requirements into the NEPA and
SEPA processes in the State of Washington," (NEPA/SEPA/404 Merger Agreement). If
it is alter determined that the Merger Process is applicable to the PROJECT, the
extra level of analysis required to comply with the NEPA/SEPA/404 Merger
Agreement will be considered "extra work." Task 10 describes the additional work
that would be required. If a decision to invoke the Merger Process is made at
some point after work on the EIS has begun, the sequence for completing the
following tasks and list of deliverables may require modification.
10.1 1st NEPA/SEPA/404 Merger
Concurrence
The CONSULTANT will coordinate and meet with regulatory agencies to gain
concurrence on the following items, as specified in the NEPA/SEPA/404 Merger
Agreement; the scope of the EIS; purpose and need/Section 404 basic project
purpose; project description and overall project objective; criteria for
alternatives selection; and role of cooperating agencies. The CONSULTANT will
prepare the purpose and need statement following guidance in Appendix D of the
NEPA/SEPA/404 Merger Agreement.
Review and research related to project purpose and need including
documentation of background on purpose and need development. Analysis of purpose
and need definitions in the Transportation Technical Report and Final
Alternatives Analysis report, and approach to defining SE Bypass purpose and
need for meeting with resource agencies on March 31. Review of SE Bypass purpose
and need, NEPA and FHWA guidelines on purpose and need, and preparation of
revised SE Bypass purpose and need statement for April 27 meeting with resource
agencies.
10.2 Wetlands Avoidance and Alternative
Analysis
Prior to distribution of the preliminary Draft EIS, the CONSULTANT will
prepare a draft Wetlands Avoidance and Alternatives Analysis following guidance
in Appendix E of the NEPA/SEPA/404 Merger Agreement. The Analysis will discuss
alternatives considered but rejected, and reasons why; impacts of each
alternative; minimization and avoidance of impacts for each alternative; and
identification of a preliminary preferred alternative, if known. The CITY will
provide consolidated comments on the draft Analysis to the CONSULTANT. The
CONSULTANT will attend one Highway design meeting with the CITY, WSDOT, and the
Merger Agencies, if necessary, to discuss comments on the Avoidance and
Alternatives Analysis. These tasks will be completed prior to distribution of
the preliminary Draft EIS.
The CONSULTANT will revise the draft Wetlands Avoidance and Alternatives
Analysis to address comments made by the merger agencies. The revised draft
Analysis will be completed for inclusion in the Draft EIS.
A final Wetlands Avoidance and Alternatives Analysis will be completed for
distribution with the Final EIS. The final Alternatives Analysis will clearly
demonstrate that alternatives that have less impacts on aquatic resources than
the preferred alternative are not practicable.
10.3 2nd NEPA/SEPA/404 Merger
Concurrence
Following the CITY's review of the preliminary Draft EIS (Task 8.1.6 of this
Scope of Work), the CONSULTANT will make the requested revisions and submit 25
copies of a second preliminary DEIS for review by the cooperating agencies. The
project Wetland Delineation Report, Biological Assessment, and Section 404
permit application will be submitted to the cooperating agencies along with the
preliminary Draft EIS. The CITY will provide one set of consolidated review
comments to the CONSULTANT.
The CONSULTANT will coordinate with regulatory agencies to gain concurrence
on the preliminary Draft EIS regarding project alternatives to be evaluated in
the Draft EIS and the preliminary preferred alternative. Additional studies
required to gain concurrence, or development and analysis of additional
alternatives will be considered "extra work." Preparation of the Draft EIS (Task
8.2) can not proceed without issuance of a letter of concurrence from the
cooperating agencies.
Review and research related to alternative alignments including evaluation of
the previous SE Bypass Final Alternatives Analysis. Documentation of previous
consideration of alternative alignments in 1-90 Access, Sunset Interchange, East
Sammamish Alternatives Feasibility, and Issaquah High Capacity Transit studies.
Review of fatal flaws for May Valley Road and Newport Way Alternatives; land use
project assumptions used in Issaquah traffic modeling; existing conditions
modeling for Issaquah traffic; evaluation of approaches to defining the No
Action alternative; background on TDM/CTR programs in Issaquah; strategies for
making greater use of existing infrastructure in Issaquah; future plans for
transit service and additional transit funds; Issaquah's commitment to access
control for the SE Bypass; environmental impacts resulting from the proposed
wetland bridging alternative; and fish usage in the North Tributary stream in
the project for the March 31 meeting with resource agencies. (CO#5 added)
Background on independent utility for the SE Bypass project; additional
analysis of traffic impacts of the May Valley Road and Newport Way alternatives
including interchange and arterial volumes, and level of service associated with
these approaches; qualitative assessment of potential environmental impacts
associated with May Valley Road and Newport Way alternatives; and additional
information on shading impacts and fish usage associated with the SE bypass
alternatives for the April 27 meeting to discuss concurrence issues. This task
also includes engineering design of the proposed bridging alternative for South
A and B alignments.
10.4 Initial Mitigation Plan for Preferred
Alternative
Upon issuance of the Agency Concurrence Letter regarding alternatives to be
evaluated in the Draft EIS and identification of the preferred alternative, the
CONSULTANT will conduct a preliminary investigation of candidate mitigation
sites to determine if there are suitable sites to support the required
mitigation. Upon identification of candidate sites, the CONSULTANT will prepare
a draft Initial Mitigation Plan for the preferred alternative, as described in
Appendix F of the NEPA/SEPA/404 Merger Agreement. The draft Plan will identify
unavoidable impacts to aquatic resources; establish the goals and objectives of
the mitigation; the timing of the mitigation; a general description of the
candidate sites; and proposed monitoring of the mitigation. No drawings will be
included in the Plan. The draft Plan will be submitted to the CITY for review
and comment.
The draft Initial Mitigation Plan will be revised to address the CITY's
comments. The revised Plan will be submitted to the CITY for distribution to
other merger agencies for review and comment. The CITY will provide consolidated
comments on the Plan to the CONSULTANT. The CONSULTANT will conduct a site visit
with the USACOE to review candidate sites. The CONSULTANT will prepare a final
Initial Mitigation Plan for inclusion in the Draft EIS.
10.5 Section 404 Permit Application
Preparation
Prior to submittal of the Preliminary Draft EIS, the CONSULTANT will attend
one pre-application meeting with the USACOE to identify issues of concern and
confirm Section 404 permitting requirements and scheduling. The CONSULTANT will
then prepare draft Section 404 permit application materials for submittal to the
CITY. The CITY will process the permit to the USACOE. Prior to publication of
the Final EIS, the CONSULTANT will prepare a final Section 404 permit
application for submittal to the permitting agencies. The final application will
include a detailed Mitigation Plan (Section 10.7 of this Scope of Work).
10.6 Section 404 Public Hearing
Issuance of the Section 404 Public Notice will be coordinated with
publication of the Draft EIS. An Open House will be conducted following
publication of the Draft EIS and the Section 404 Public Notice, as described in
Task 8.5 of this Scope of Work.
10.7 3rd NEPA/SEPA/404 Merger
Concurrence
Following the CITY's review of the preliminary Final EIS (Task 9.3 of this
Scope of Work) EIS, the CONSULTANT will make the requested revisions and
submit 25 copies of a second preliminary Final EIS for review by the cooperating
agencies. The CITY will .provide on set of consolidated review comments to the
CONSULTANT. The CONSULTANT will coordinate and meet with regulatory agencies to
gain concurrence on the preliminary Final EIS regarding the apparent final
mitigation plan and the preferred alternative/least environmentally damaging
alternative, as specified in the NEPA/SEPA/404 Merger Agreement. Additional
studies or revisions to alternative that may be needed to obtain concurrence
will be considered "extra work." Publication of the final EIS (Task 9.4 of this
Scope of Work) can not occur without issuance of a letter of concurrence from
the cooperating agencies.
10.8 Detailed Mitigation Plan and Report
Prior to publication of the Final EIS, the CONSULTANT will prepare a draft
Detailed Mitigation Plan and Report for the preferred alternative, as described
in Appendix F of the NEPA/SEPA/404 Merger Agreement. The draft Plan will include
a summary of wetland impacts, description of proposed mitigation and mitigation
site(s), mitigation design (hydrology source, grading plan, soil preparation,
planting plan, and schedule), standards of success, and monitoring and
contingency plans. The draft Plan will be submitted to the CITY for review and
comment. The draft Plan will be revised to address the CITY's comments. The
revised Plan will be submitted to the CITY for distribution to the merger
agencies with the pre-final EIS.
Upon issuance of concurrence on the preliminary Final EIS by the cooperating
agencies, the CONSULTANT will prepare a final Detailed Mitigation Plan for
inclusion in the Final EIS. A Final Mitigation Plan as required by the NEPA/SEPA/404
Merger Agreement is not included in this Scope of Work.
10.9 Meetings and Coordination
CONSULTANT attendance at March 31 and April 27 meetings with resource
agencies. Preparation and distribution of revised concurrence forms. Meetings
with King County (May 10), Corps of Engineers (May 26), Mike Birdsall from
EarthTech (June 23), and communication and coordination with resource agencies
regarding revisions in purpose and need, and agency issues related to
alternative alignments.
10.9.1 Attend Meetings and Coordinate with
Agencies and Subconsultants
The CONSULTANT will coordinate with the City of Issaquah, King County,
resource agencies and subconsultants as required to complete additional
alternatives analysis and Merger Process concurrence. Up to 10 meetings will be
attended.
10.9.2 Present Findings to Resource Agencies
The CONSULTANT will prepare for, and attend, one meeting with the Merger
Resource agencies to present results of the additional alternatives analysis
completed in Tasks 13-16 below. This task will include preparation of any
display boards or other presentation materials needed for this meeting.
PRODUCTS
1`t Draft Purpose and Need Statement (10 copies)
2nd Draft Purpose and Need Statement (20 copies)
Final Purpose and Need Statement (included in Draft EIS)
1st Draft Wetlands Avoidance Alternatives Impacts Analysis Report
(10 copies)
2nd Draft Wetlands Avoidance Alternatives Impacts Analysis Report
(20 copies)
Final Wetlands Avoidance Alternatives Impacts Analysis Report (included in
Draft EIS)
2nd Draft Preliminary Draft EIS for review by Merger Agencies
1st Draft Initial Wetlands Mitigation Plan and Report (10 copies)
2nd Draft Initial Wetlands Mitigation Plan and Report (20 copies)
Final Initial Wetlands Mitigation Plan and Report (10 copies)
Draft 404 Wetland Permit Application (5 copies)
Final 404 Wetland Permit Application (10 copies)
2nd Draft Preliminary Final EIS for review by Merger Agencies
1st Draft Detailed Wetland Mitigation Plan (10 copies)
2nd Draft Detailed Wetland Mitigation Plan (20 copies)
Final Detailed Wetland Mitigation Plan (10 copies)
Task 13 Research Congestion Pricing
Alternative
13.1 Research and Analyze Transportation Impacts
The CONSULTANT will provide research and analysis of an alternative involving
the use of congestion pricing in Issaquah to encourage the use of alternative
routes, alternative modes of transportation, or a shift in driving to off-peak
periods. Tasks included in this research include the following: research impacts
of congestion pricing in other areas; describe assumptions included in the
congestion pricing scenario; review assumptions with City of Issaquah and
revise; develop two scenarios for inclusion in the network model; develop ranges
for the potential cost for each scenario; for each scenario analyze model
results for potential changes in vehicle trips for the year 2015; for each
scenario analyze model results for potential changes in VMT for year 2015;
evaluate the potential queue area required for 3 toll booths; for each scenario
evaluate impacts to operations at twelve signalized intersections for year 2015
(see section 15.1 for a list of intersections); prepare presentation;
incorporate comments and feedback; and prepare final results in tech memo or
presentation. The development of a congestion pricing scenario will include an
overview of opportunities for coordinated expansion of transit service to
support this alternative (see Transit Service Alternative below). This
alternative will be evaluated individually, and also in combination with the
proposed SE Bypass project. This analysis will provide information for a
combined approach to be included in the alternatives matrix (Task 16.2 below) as
SE Bypass with Congestion Pricing alternative.
13.2 Environmental Impacts of Congestion Pricing
The CONSULTANT will provide a qualitative description of potential impacts to
the elements of the natural and social environment that may result from this
alternative. A general discussion of toll booths and other facilities (such as
parking) that would be needed to support this alternative will be provided. The
CONSULTANT will identify the effectiveness of this alternative in meeting the
purpose and need to be addressed by this project. The environmental analysis
also will include the combined SE Bypass with Congestion Pricing alternative
identified above.
Task 14 Research Transit Service Alternative
14.1 Research and Analysis
The CONSULTANT will provide research and analysis of transit service
improvements that could be implemented as a separate alternative to constructing
the SE Bypass roadway. Tasks included in this research include the following:
The CONSULTANT will describe potential use of an expanded shuttle/transit
service in the city. Potential use of an expanded shuttle/transit service in the
city will be based on discussions with King County Metro transit service
planners, and an analysis of previously collected data. Activities included in
this subtask include the following: develop assumptions included in preliminary
transit alternative; prepare overview of alternative for King County and City of
Issaquah; develop two transit alternative scenarios for inclusion in network
model; for each scenario, analyze model results; for each scenario, develop
range for costs; evaluate impacts to twelve signalized intersections for each
scenario; analyze potential change in vehicle trips; analyze potential change in
VMT; prepare presentation materials; incorporate comments and feedback from
presentation; and prepare final results in a tech memo or presentation. This
alternative will be evaluated individually, and also in combination with the
proposed SE Bypass project. This analysis will provide information for a
combined approach to be included in the alternatives matrix (Task 16.2 below) as
SE Bypass with Transit alternative.
14.2 Environmental Impacts of Transit Service
The CONSULTANT will provide a qualitative description of potential impacts to
the elements of the natural and social environment that may result from this
alternative. The CONSULTANT will identify the effectiveness of this alternative
in meeting the purpose and need to be addressed by this project. The
environmental analysis also will include the combined SE Bypass with Transit
alternative identified above.
TASK 15 ALTERNATIVES ALIGNMENT REVIEW
The CONSULTANT will review only the Newport Way, May Valley, and Front Street
to I-90 alternative corridors previously studied in the Alternatives Alignment
Study completed in May 1997 for this project.
15.1 Transportation Analysis
The CONSULTANT will review existing transportation conditions for both the
Newport Way and May Valley alternatives. New network modeling will be required
for this task. Year 2015 volumes will be used to determine intersection Level Of
Service along each of the proposed alternatives and along Front Street. This
information will be used to evaluate the alternatives for the "Decreases Traffic
Congestion" criterion in the Alternatives Alignment Study. Based on the purpose
and need, the determining factor will be whether the alternative significantly
decreases congestion in the future along the Front Street corridor.
Intersections evaluated using Transyt-7F or HCS/NCAP are the following: SR 900
and WB Ramps; SR 900 and EB Ramps; SR 900 and Gilman; SR 900 and Maple; Front
St. WB Ramps; Front St. EB Ramps; Front and Gilman; Front and Sunset; SR 900 and
Newport, May Valley Road and Hobart; May Valley Road and 128`h; and
May Valley Road and SR 900.
Tasks involved include data collection and coordination with the network
modeling subconsultant; an initial set-up for each intersection for the
Transyt-7F/HCS analysis, Transyt-7F and HCS analysis for each scenario for each
intersection for the AM and PM peak periods; and summarizing of results.
15.2 Alternative Definition
Both the Newport Way and May Valley build alternatives will be further
defined. This will include number of additional lanes required, approximate
lengths of widening, and any structural elements needed to accomplish the
widening. The above transportation analysis will aid in defining the need for
additional lanes.
Geometric feasibility with respect to deviations from standards will be
reviewed. A rough cost estimate will be computed for each of the two
alternatives to provide a relative comparison to the Bypass.
15.3 Environmental Review
The CONSULTANT will review the Newport Way and May Valley build alternatives
to determine environmental impacts consistent with the Alternatives Alignment
Study. The number of residential and commercial displacements will be counted.
The approximate area of recreational space affected and approximate right-of-way
requirements will be determined. Sensitive areas impacted by the proposed
alternative such as streams, vegetation, wetlands, and slopes, will be
determined. This task may include a field visit to review sensitive areas along
these routes.
TASK 16 ADDENDUM TO ALTERNATIVES ALIGNMENT
STUDY
16.1 Report Addendum
The CONSULTANT will use the information obtained in tasks 13 through 15 to
prepare an addendum to the Alternatives Alignment Study completed in May of
1997. This addendum will be written for the Newport Way, May Valley, Congestion
Pricing, Transit, Front Street to 1-90, Front Street to 1-90 in combination with
Congestion Pricing, and Front Street to 1-90 in combination with Transit
alternatives only. The addendum will include descriptions of the alternatives,
as well as discussion on each of these alternative's merits and shortfalls as
related to Project Goals, Social/Economic Impacts, Natural Environment Impacts,
Transportation Improvements, and Cost. Part of this effort will include revising
the criteria for the study and providing more detailed descriptions of all
criteria.
Products
Draft Addendum to the Alternatives Alignment Study (6 copies) Final Addendum
to the Alternatives Alignment Study (12 copies)
16.2 Matrix Addendum
An update to the existing Southeast Issaquah Bypass Corridor Alternative
Fatal Flaw Matrix will be provided by the CONSULTANT with ratings on the Newport
Way, May Valley, Congestion Pricing, Transit, Front Street to 1-90, and
Combination alternatives only. These ratings will be on a one to three basis
rather than a pass/fail basis. The matrix completed in this task, together with
the addendum prepared in the above task, will be the basis for the decision to
cant' forward any of these seven alternatives into the DEIS.
Products
Draft Addendum to the Fatal Flaw Matrix (6 copies) Final Addendum to the
Fatal Flaw Matrix (12 copies)
Task 17 Incorporate Results of Additional
Alternatives Analysis in SE Bypass DEIS
17.1 Expand Draft EIS Alternatives Discussion
The CONSULTANT will be responsible for incorporating the results of the
additional alternatives analysis provided for in the tasks above, within the SE
Bypass Draft EIS. This would involve supplementing the discussion of
'Alternatives Considered but Rejected for Further Analysis,' and may include
adding new alternatives for analysis throughout the DEIS. The cost estimate
provided here is for supplementing the 'Alternatives Considered but Rejected'
discussion only. If the additional alternatives analysis results in a
determination that new alternatives are to be analyzed throughout the Draft EIS,
a separate contract amendment to the Draft EIS contract, based on the additional
alternative(s) to be analyzed, would be prepared and submitted by the
CONSULTANT.
Task 19 Supplemental Environmental Impact
Statement
19.1 Project Management
19.1.1 Project Management Plan
The CONSULTANT shall update the project management plan for the Supplemental
EIS through the Final Environmental Impact Statement (FEIS) and Design Report.
The plan will include new information related to preparation of the SEIS, and a
new project
schedule will be prepared.
19.1.2 Monthly Billings and Progress Reports
The CONSULTANT shall prepare monthly progress reports describing the status
of the PROJECT. These reports will:
Highlight significant accomplishments
Target potential problem areas needing special attention or
coordination
Compare actual work progress with contractual obligations on a design
task basis
The progress reports will be presented in a task oriented format and will
include updated scheduling reports, indicating all progress to date and
resources expended. This update will include any changes in schedule, sequence,
or resource loading. If any schedule slippage has occurred, a plan for bringing
the work back on schedule and budget will be included.
Progress reports and billings will be prepared by the CONSULTANT and
submitted on a monthly basis. These items will be supported by detailed record
keeping sufficient to closely track the PROJECT budget and expenditures and
support the billings.
PRODUCTS
Monthly Progress Reports, incorporating Project Schedule revisions as
appropriate, and Monthly Billings. Approximately 4 progress reports and
billings will be provided.
19.1.3 Direction, Meetings, and Coordination
This task includes the following project management items:
19.1.3.1 Team Coordination/General Direction
This task includes internal staff meetings and discussions to direct efforts
and facilitate completion of project tasks.
19.1.3.2 Meetings with City Staff
Regularly scheduled meetings (two per month) with Issaquah staff to review
progress and discuss upcoming actions will be held. This task would also include
additional meetings with City staff members as needed to obtain information or
resolve project issues. The CONSULTANT shall prepare meeting minutes to
summarize issues discussed.
19.1.3.3 Meetings/Coordination with Others
This task would provide for meetings and coordination with outside agencies
to provide information or discuss project issues. The CONSULTANT shall prepare
meeting minutes to summarize issues discussed with participating agencies.
PRODUCTS
Meeting notes documenting topics discussed and future action items will be
prepared and distributed as appropriate.
19.2 QUALITY CONTROL
19.2.1
Quality Assurance
The work products will be reviewed by consultant team staff with expertise in
the appropriate discipline areas. This will be an ongoing activity during the
duration of the project with emphasis on major deliverable work products.
19.3 Supplemental EIS
19.3.1 Transportation Study
Phase 1 will include those tasks necessary to define alternatives to be
evaluated in the Supplemental EIS based on a design year 2030 traffic model.
Included will be updated traffic modeling data, new analyses of traffic
operations based on new model data, a review of potential refinements to the
north alignments, as well as the study of one new possible south alignments.
19.3.1.1 Traffic Model Refinement
A future year 2030 traffic model (TMODEL Software), which will include a
highway network of all freeways, freeway interchanges, arterials and other
streets in the study area will be developed for use in subsequent tasks for the
SE Bypass SEIS. This model will replace the traffic model used for preparation
of the SE Bypass Draft EIS (June, 2000). The 2030 SE Bypass model will be
developed using the CITY’s Concurrency model and will be updated to incorporate
2030 land use and demographic data, based on the 2030 PSRC model. Input data
like model growth rates at external stations will also be updated for the 2030
SE Bypass model.
19.3.1.2 Land Use Assumptions For
Transportation Modeling
Future year land use assumptions will be developed for the year 2030. The
land use data for 2030 will be provided by the PSRC and the City of Issaquah
(concurrency model). The data is based on regional forecasts of economic
activity and local land use plans, including the East Sammamish Community Plan
and the Issaquah Comprehensive Plan. The CONSULTANT shall summarize the land use
assumptions based on the 2030 PSRC model along with the CITY’s updated
Concurrency model. The land use assumptions may differ from those used for the
Draft EIS, since those used in the 2030 SE Bypass model will be based on the
most current information available.
19.3.1.3 Model Network
The transportation networks for model year 2030 will be developed from
planned and the programmed improvements to be implemented by WSDOT, King County,
and the City of Issaquah. The CONSULTANT shall review and revise the 2030 SE
Bypass model network as necessary to ensure continued consistency with adopted
Plans.
For year 2030, up to three Model runs (one model run shall include both AM &
PM traffic forecasts) will be performed. Each model run may require further
post-processing of the AM and PM Peak hour forecasts. If necessary,
post-processing will include converting the model traffic forecasts into hourly
volumes for the AM and PM peak hours that can be utilized for corridor and
intersection analysis. The PM peak hour generated trip tables from the 2030 SE
Bypass model will be transposed and if necessary scaled to represent AM peak
hour demand. Additionally, these hourly volumes will be balanced for the SE
Bypass corridor.
Each model run will contain differing assumptions regarding programmed and
planned roadway projects. One model run may include alternative land use
assumptions as determined by the CITY.
The Model runs include:
· 2030 Model Run 1 - Year 2030 No Action: Included will be
the following projects: North SPAR, South SPAR, Sunset Interchange
modification, and SR 900 widening. with baseline 2030 assumptions for land
use
· 2030 Model Run 2 - Year 2030 No-Action w/SR 18: Included
will be the following projects: North SPAR, South SPAR, Sunset Interchange,
SR 900 widening, and SR 18 widening (this will require using the King County
or PSRC model rather than the SE Bypass Model)
· 2030 Model Run 3 - Year 2030 Full Build: Included will be
the following projects: NSPAR, SSPAR, Sunset, SR 900, and SE Bypass (with no
widening of SR 18)
19.3.1.4 Prepare Future Alternative Alignment
Travel Demand Forecasts
Based on future land use assumptions supplied by the CITY and on the
definition of the roadway alignment alternatives, year 2030 travel demand
forecasts will be prepared using the traffic model. For the 2030 build model,
the three north alignments (North A, North B, North S) and the new south
alignment alternatives for the SE Bypass may be refined. Additionally, the
southern alignment may be evaluated for channelization and alignment design.
The 2030 SE Bypass model will be created using the TMODEL software. Available
output from TMODEL includes specific roadway volumes, intersection volumes and
select link data for the AM and PM Peak hours. This information will be
extracted from the model for the various 2030 model runs. For the 2030 build
scenario, the traffic information extracted from the 2030 build model will be
applied to the various proposed design alignment alternatives.
19.3.1.5 Modal Share Sensitivity
As part of development of the 2030 SE Bypass Model, the CONSULTANT shall
prepare a summary of the varying travel demand assumptions) incorporated into
the 2030 SE Bypass Model. Most travel demand assumptions will be based primarily
off of the assumptions made in the CITY’s concurrency model along with the
PSRC’s 2030 model. The travel demand assumptions will be presented in the SEIS.
19.3.1.6 Evaluation of Alternatives for
Transportation Element
The alignment alternatives (North and South alignments) will be evaluated
based on transportation criteria related to the following areas:
Arterial operations including service to CITY planned land uses
Interchange operations
Non-motorized transportation (including trails)
Safety
Recommendations from the Draft EIS
Results of the transportation evaluation will be documented in the SEIS.
19.3.1.7 Intersection/Roadway Operations
Intersection/Roadway operational analysis of key intersections/roadways (as
determined by the CONSULTANT and CITY) will be conducted by the CONSULTANT.
2030 No Action
The CONSULTANT shall perform intersection analysis for up to twenty-four (24)
intersections as determined by the CITY and CONSULTANT. The AM and PM peak hours
will be analyzed for each intersection; the LOS and intersection delay will be
recorded. The intersections that will be analyzed are:
SR 900 & NW Sammamish
SR 900 & I-90 WB Ramps
SR 900 & EB Ramps
SR 900 & Gilman
SR 900 & Maple
E Sammamish & 56th
Issaquah-Fall City & E. Lk Sammamish
Front St. & WB Ramps
Front St. & EB Ramps
Front St & Gilman
Front St & Sunset
Issaquah-Fall City & Black Nugget Rd
Issaquah-Fall City & Issaquah Pine
Sunset & WB I-90 Ramps
Sunset & EB I-90 Ramps
E Sammamish & 43rd
Front Street & Clark
Front St & Dogwood – South
Front St & Dogwood – North
Sunset & Second
Front St & Second
SR 900 & Newport
E. Lake Sammamish & Black Nugget
Second Avenue SE & Bush Street
2030 Build-Intersection Analysis
For the 2030 Build scenario, a preliminary operational analysis will be
conducted based on SE Bypass configuration assumptions provided by the CITY.
Based on the results of this preliminary operational analyses, additional
operational analyses will be performed as needed to evaluate alternative SE
Bypass configurations (e.g., shorter or longer turning pockets, more or fewer
lanes, etc.), in order to determine the preferred SE Bypass design alternative.
The Synchro software will be utilized in determining corridor and
intersection operations for the various roadway combinations. The operational
analyses will be conducted for the AM and PM peak hours and intersection LOS
along with intersection delay (sec/veh) will be recorded.
A roadway combination will be defined as inclusion of one north alignment
alternative and one south alignment alternative. Up to three (3) road
combinations will be considered (this is contingent upon the assumption that all
three north alignments and the new south alignment are not fatally flawed at
this point). Up to four (4) versions (or iterations) will be conducted per
roadway combination as directed by the CITY. A version (or iteration) may
include:
· Modifications to the number of lanes assigned at a particular
intersection or corridor
· Modifications to design lengths (this can be either storage
lengths or distance between intersections)
Once the preferred design alternative is determined, other local intersection
analysis will be conducted. Please refer to the 2030 No Action section
(above) for a list of the twenty-four intersections to be analyzed.
19.3.1.8 Mitigating Measures
Qualitative analyses will be performed by the CONSULTANT to identify and
discuss the potential effectiveness of measures designed to mitigate any
significant adverse impacts of each of the alternatives.
19.3.1.9 Draft Transportation Study
The CONSULTANT shall prepare a Draft Transportation Study to document the
results of the new traffic modeling and analysis. Up to 20 copies of the draft
study will be provided for review and comments.
19.3.1.10 Final Transportation Study
Following review of the draft Transportation Study, the CONSULTANT shall
revise the draft Transportation Study to incorporate review comments. Up to 10
copies of the Final Transportation Study will be provided.
PRODUCTS
Approximately 20 copies of the Draft Transportation Study will be provided
for review by the City and other agencies.
Following review, approximately 10 copies of the Final Transportation Study
will be provided.
19.3.2 Preliminary Design
The CONSULTANT shall revise the chanellization plan features of the current
north and south alignments to reflect the traffic needs as required by the
Transportation Study for the year 2030. The CONSULTANT will then use this
revised roadway template, including stormwater facilities, to develop new cross
sections and revised slope lines to further determine their impact with respect
to wetlands, streams, existing property boundaries and structures. The
CONSULTANT shall develop up to three (3) Typical Sections to further clarify the
roadway prism at selected locations throughout the project length.
Based on the results of this effort and the corresponding impacts, the
CONSULTANT shall revise the horizontal and vertical alignments in an effort to
mitigate unfavorable impacts to wetlands, streams, existing properties and
structures. With each horizontal revision, the CONSULTANT shall revise the
channelization plan features throughout the length of the horizontal shift. With
each vertical alignment revision, the CONSULTANT shall rerun cross sections
throughout the length of the vertical alignment revision and revise slope lines
to further determine their impact with respect to wetlands, streams, existing
properties and structures. The CONSULTANT shall make any revisions to the
Typical Sections that may result from the shifts in horizontal and vertical
alignments.
Consideration will be given to a diverging, separated pedestrian trail, along
the south roadway alignment, that would better serve the adjacent high school.
If this is determined desirable, one (1) separate horizontal alignment and
vertical profile will be developed for the pedestrian trail. The separated trail
alignment will be modeled to determine cut and fill limits and their location
with respect to wetlands, streams, existing properties and structures.
PRODUCTS
Up to three (3) alignment drawings identifying the proposed project design
for the northern and southern alignments will be provided.
Up to (2) two vertical profiles of the proposed project design will be
provided.
19.3.3 Section 4(f) Issues
The CONSULTANT shall investigate Section 4(f) resource issues and how they
might affect decisions regarding the project’s northern alignments. The
necessity of identifying the Issaquah High School facilities as Section 4(f)
resources will be explored. The Department of Natural Resources will be
contacted regarding potential impacts on Tiger Mountain NRCA property. Further
coordination with the Office of Archaeology and Historic Preservation will be
pursued regarding the need to confirm determinations of effect on the Sportsman
Clubhouse. Potential balancing of impacts on historic properties with impacts on
school facilities under Section 4(f) [if it is agreed to consider high school
property under Section 4(f)] will be evaluated.
19.3.4 Additional Wetlands and Streams Study
The CONSULTANT shall provide additional study of wetlands and streams in the
project area to determine impacts on these resources from the new alignment
design resulting from the updated 2030 traffic model. This work will involve
additional wetland and stream reconnaissance of the North Tributary stream in
the vicinity of Front Street, south of 2nd Avenue. It will also involve review
of potential impacts to Wetland HS and Wetland GW (identified in the Draft EIS)
associated with the new alternative.
The results of this task will be documented in a Wetlands Technical
Memorandum. A draft technical memorandum will be submitted for review and
comment. A final technical memorandum will be prepared incorporating comments on
the draft.
PRODUCTS
Approximately 20 copies of the Wetlands technical memorandum will be
provided for review and comments.
Approximately 10 copies of the Final Wetlands Technical Memorandum will be
provided.
19.3.5 Drainage Design Review
The CONSULTANT shall review the conceptual drainage design of the new
southern alignment in relation to the new 2030 model results to assure that
adequate consideration of drainage requirements is provided. A review of the
conceptual drainage design for the three northern alignments will be done to
confirm that the current changes have not altered the previous design.
Preliminary calculations of runoff volumes and flow rates to support preliminary
sizing of the stormwater control ponds needed to serve the updated roadway
design will be prepared. These calculations will be prepared for each of the
northern alignment alternatives as well as the new southern alignment
alternative. The CONSULTANT will also evaluate the approximate sizes and
locations of runoff conveyance systems that would be needed to deliver roadway
runoff to the stormwater ponds. Hard copy markups of preliminary conveyance
system alignments to will be prepared for transfer onto the project base maps.
The results of this task will be documented in a Drainage Design Technical
Memorandum. A draft technical memorandum will be submitted for review and
comment. A final technical memorandum will be prepared incorporating comments on
the draft.
PRODUCTS
Approximately 20 copies of the Drainage Technical Memorandum will be
provided for review and comments.
Approximately 10 copies of the Final Drainage Technical Memorandum will be
provided.
19.3.6 Merger Process Coordination
The CONSULTANT shall coordinate with regulatory agencies to gain concurrence
on the alternatives to be evaluated in the Supplemental EIS. Additional studies
to gain concurrence, or development and analysis of additional alternatives will
be considered "extra work." Preparation of the preliminary draft SEIS cannot
proceed without issuance of a letter of concurrence from the cooperating
agencies.
Task 20
Supplemental Environmental Impact Statement and Preliminary Design
20.1 Project Management
20.1.1 Project
Management Plan
The CONSULTANT shall update the project management plan to incorporate
staffing changes, changes in deliverables or other updates required by this work
plan.
20.1.2 Monthly
Billings and Progress Reports
The CONSULTANT shall prepare up to twenty (20)
additional monthly progress reports describing the status of the project. These
reports shall continue to report the following:
Significant accomplishments
Potential problem areas needing special attention or coordination
Actual work progress compared with contractual obligations on a task
by task basis
Billings shall continue to be prepared by the CONSULTANT and submitted on a
monthly basis. The CONSULTANT shall monitor project progress and provide up to
ten (10) MS Project schedule updates.
PRODUCTS
· Monthly Progress Reports and Monthly
Billings (up to 20 assumed)
· Updated MS Project Schedule (up to
10 assumed)
20.1.3 Direction, Meetings, and Coordination
This task includes the following project management items:
20.1.3.1 Team
Coordination/General Direction
Periodic team coordination meetings shall be held to direct team efforts and
facilitate completion of project tasks identified in this work plan. This task
assumes up to ten (10) one-hour meetings attended by up to five 5 PB staff.
20.1.3.2 Meetings
with City Staff
The CONSULTANT shall attend up to ten (10)
coordination meetings with Issaquah staff, WSDOT and FHWA to review progress and
discuss upcoming actions. Up to two (2) CONSULTANT staff are assumed to attend
each meeting. The meetings shall be held at the CONSULTANT’S Seattle office or
other location agreed to by all parties. The CONSULTANT shall prepare meeting
notes and action items following each meeting.
20.1.3.3
Meetings/Coordination with Others
This task would provide for meetings and coordination with regulatory
agencies (outside of the Section 404 Merger activities described in Task 20.4)
to provide information or discuss project issues. Up to five 3-hour meetings,
attended by up to three (3) CONSULTANT staff is assumed for this task.
The CONSULTANT shall prepare meeting minutes to summarize issues discussed
with participating agencies.
PRODUCTS
Meeting notes documenting topics discussed and future action items will be
prepared and distributed as appropriate.
20.2 QUALITY
CONTROL
20.2.1 Quality
Assurance
Project deliverables shall be reviewed by CONSULTANT team staff with
expertise in the appropriate discipline areas. This task also includes
CONSULTANT team effort to review work products prepared by SUBCONSULTANTS. This
shall be an ongoing activity during the duration of the project.
20.3
SUPPLEMENTAL EIS
20.3.1
Transportation Study
Traffic Conditions and Analysis
Phase 2 work performed by the CONSULTANT shall include
those tasks necessary to analyze both the proposed Build alternative (based off
of the year 2030 analysis as described in Phase 1) for the opening year 2005 for
both the AM and PM peak hours. Additionally, the year 2005 No Action and
existing year 2000 conditions shall be analyzed. Updated traffic modeling data,
traffic analysis based on new modeling data, and analysis of the proposed Build
and No-Action alternatives shall be included.
Methodology
This section presents the methodology and assumptions used to guide the
transportation analysis. The methodology and assumptions used in this analysis
are consistent with those applied in the SR 900 Widening Project.
20.3.1.1 Traffic
Model Refinement
The traffic model used in the SE Issaquah Draft EIS (June 2000) shall be
replaced with the traffic model described below. The TMODEL software shall be
used in developing the traffic model.
Year 2000 Existing Conditions
The 2000 existing conditions SE Bypass model will be based off of the CITY’s
Travel Model used for Concurrency Testing. The CITY’s Travel Model assumes a
1999 land use and year 2000 traffic data. The CITY’s Travel Model will be
utilized as the Year 2000 SE Bypass Model.
Opening Year 2005
A future year 2005 traffic model, which will include a highway network of all
freeways, freeway interchanges, arterials and other streets in the study area
will be developed for use in subsequent tasks for the SE Bypass SEIS. The 2005
SE Bypass model will be developed using the CITY’s Year 2000 Travel Model (used
for Concurrency Testing) along with the 2005 SR 900 Widening Model’s land use
assumptions. The SR 900 Widening land use assumptions may be adjusted; the
CONSULTANT shall notify the CITY if adjustments are applied to the 2005 SE
Bypass Model. The King County or PSRC Models may also be referenced and used if
applicable.
20.3.1.2 Land Use
Assumptions For Transportation Modeling
Existing Conditions Year 2000
The CONSULTANT shall summarize the land use assumptions based on the CITY's
Year 2000 Travel Model used for concurrency testing.
Opening Year 2005
Future year land use assumptions will be based off of the Year 2005 SR 900
Widening Model and may be modified if necessary. The CONSULTANT shall summarize
(and update if necessary) the land use assumptions for the Year 2005 SE Bypass
Model.
The land use assumptions may differ from those used for the Draft EIS, since
those used in the 2005 SE Bypass model will be based on the more current
information.
20.3.1.3 Model
Network
Existing Conditions Year 2000
For year 2000, one Model run (one model run shall include both AM & PM
traffic forecasts) shall be performed. The PM peak hour generated trip tables
from the 2000 SE Bypass model shall be transposed and if necessary scaled to
represent AM peak hour demand. Additionally, the hourly volumes shall be
balanced for the SE Bypass corridor.
The Model run shall include:
· 2000 Model Run 1 - Year 2000 Existing Conditions: Year
1999 assumptions for land use will be incorporated.
Opening Year 2005
The transportation networks for model year 2005 shall be developed from
planned and programmed improvements to be implemented by WSDOT, King County, and
the City of Issaquah.
The CONSULTANT shall review and revise the 2005 SE Bypass model network to
provide continued consistency with adopted Plans.
For year 2005, up to two Model runs (one model run shall include both AM & PM
traffic forecasts) shall be performed. The PM peak hour generated trip tables
from the 2005 SE Bypass model shall be transposed and if necessary scaled to
represent AM peak hour demand. Additionally, the hourly volumes shall be
balanced for the SE Bypass corridor. Each model run shall contain different
assumptions regarding programmed and planned roadway projects.
The Model runs include:
2005 Model Run 1 - Year 2005 No Action: Included shall be the
following projects: North SPAR, South SPAR, Sunset Interchange
modification, and SR 900 widening. Baseline 2005 assumptions for land
use shall be incorporated.
2005 Model Run 2 - Year 2005 Full Build. Included shall be the
following projects: NSPAR, SSPAR, Sunset, SR 900, and SE Bypass (with no
widening of SR 18)
20.3.1.4 Prepare
Future Alternative Alignment Travel Demand Forecasts
Based on future land use assumptions supplied by the CITY and on the definition
of the roadway alignment alternatives, year 2005 travel demand forecasts shall
be prepared using the traffic model. For the 2005 build scenario, the proposed
build alternative alignment (based on the work completed through Phase 1) shall
be considered.
Available output from TMODEL includes specific roadway volumes, intersection
volumes and select link data for the PM Peak hour. The trip tables generated for
the PM peak hour shall then be transposed and possibly scaled in order to
generate the AM Peak hour volumes. For the 2005 build scenario, the traffic
information extracted from the 2005 build model shall be applied to the
recommended proposed design alignment alternative (as determined in Phase 1).
PRODUCTS
The CONSULTANT shall provide the CITY a copy of the TMODEL electronic files
with a brief annotation for model year runs 2030, 2005, and 2000.
20.3.1.5 Modal Share
Sensitivity
As part of development of
the 2005 SE Bypass Model (No-Action and Build Scenarios), the CONSULTANT shall
prepare a summary of the various travel demand management assumptions
incorporated into the 2005 SE Bypass Model. Most travel demand management
assumptions shall be based primarily off of the assumptions made in the SR 900
Widening model along with the CITY's Travel Model used for concurrency testing,
and possibly the PSRC model. The travel demand management assumptions shall be
presented in the SEIS.
20.3.1.6
Intersection/Roadway Operations
The CONSULTANT shall conduct intersection/roadway operational analysis of key
intersections/roadways (as determined by the CONSULTANT and CITY). The Synchro
software shall be utilized in performing the traffic operational analyses. The
operational analyses shall be conducted for the AM and PM peak hours and
intersection LOS along with intersection delay (sec/veh) shall be recorded.
Year 2000 Existing
Conditions and Year 2005 No Action
The CONSULTANT shall perform intersection analysis for up to twenty-five (25)
intersections as determined by the CITY and CONSULTANT. The AM and PM peak hours
shall be analyzed for each intersection; the LOS and intersection delay shall be
recorded. The intersections that shall be analyzed are (as per agreement with
the CITY):
SR 900 & NW Sammamish
SR 900 & I-90 WB Ramps
SR 900 & EB Ramps
SR 900 & Gilman
SR 900 & Maple
E Sammamish & 56th
Issaquah-Fall City & E. Lk. Sammamish
Front St. & WB Ramps
Front St. & EB Ramps
Front St & Gilman
Front St & Sunset
Issaquah-Fall City & Black Nugget Rd
Issaquah-Fall City & Issaquah Pine
Sunset & WB I-90 Ramps
Sunset & ED I-90 Ramps
E Sammamish & 43rd
Front Street & Clark
Front St & Dogwood - South
Front St & Dogwood - North
Sunset & Second
Front St & Second
SR 900 & Newport
Lake Sammamish & Black Nugget
Second Avenue SE & Bush Street
Issaquah-Hobart Rd & May Valley Rd
Year 2005 Build
The proposed Build alternative as determined in Phase 1 shall be analyzed for
the year 2005. The proposed roadway combination is defined as inclusion of one
north alignment alternative and the south alignment alternative. In terms of
traffic operations, all three North Alignments shall operate similarly;
therefore, one roadway combination (a north alignment and the south alignment)
shall be analyzed. Up to four (4) versions (or iterations) shall be conducted. A
roadway combination version (or iteration) may include:
Modifications to the number of lanes assigned at a particular
intersection or corridor
Modifications to design lengths (this can be either storage lengths
or distance between intersections)
The Synchro software shall be utilized in determining corridor and
intersection operations for the year 2005 build roadway combination as well as
the twenty-five (25) intersections as listed in the "Year 2000 Existing
Conditions and Year 2005 No Action" section (above). Additionally, the year 2000
Existing Conditions and the year 2005 No Action intersections as described above
shall also be analyzed using the Synchro software.
The CONSULTANT is assuming that the preferred alternative may be constructed
in two stages where Stage 1 involves construction of a two-lane roadway and
Stage 2 involves widening the initial two-lane facility to four lanes. For the
Build Scenario, the CONSULTANT shall determine the projected year in which
traffic volumes indicate that a four-lane roadway would be necessary in order to
adequately accommodate traffic demand on the SE Issaquah Bypass.
20.3.1.7 Mitigating Measures
Qualitative analyses shall be performed by the
CONSULTANT to identify and discuss the potential effectiveness of measures
designed to mitigate any significant adverse impacts of each of the
alternatives.
20.3.1.8. Draft
Transportation Study
The CONSULTANT shall prepare a Draft Transportation Study to document the
results of the new traffic modeling and analysis. The Draft Transportation Study
shall build on the analysis started under the Phase 1 Transportation Study. Ten
(10) copies of the Draft Study shall be provided for review and comments.
PRODUCTS
Draft Transportation Study for review by the City and other agencies (10
copies)
20.3.1.9. Final Transportation Study
The CONSULTANT shall revise the March 2003 Draft Transportation Study
following review by the CITY, WSDOT, FHWA, Signatory Agency Committee (SAC)
representatives and other resource agencies. Fifteen (15) copies of the Final
Transportation Study shall be provided. Additional traffic modeling required to
address comments on the Draft or Final Transportation Study shall be considered
Extra Work.
PRODUCTS
Final Transportation Study (15 copies)
20.3.2. Biological Assessment
The CONSULTANT shall revise the Draft Biological Assessment prepared in March
2003 to address comments received by WSDOT technical reviewers. The CONSULTANT
shall submit five (5) revised copies of the BA to WSDOT for distribution to FHWA,
NMFS and USFWS. The CONSULTANT shall revise the document in response to agency
comments and submit five (5) final copies of the BA for distribution to WSDOT,
FHWA, NMFS and USFWS.
PRODUCTS
Revised Draft BA (5 copies)
Revised Draft BA (5 copies)
20.3.3. Photo Imaging of Alternatives
The CONSULTANT shall provide up to four (4) computer generated oblique view
photographic images depicting proposed build alternatives for inclusion in the
Supplemental Draft and Final EIS. The images shall also be used to create
mounted display boards for use at public meetings, project exhibits, and other
public outreach events. In addition, three (3) ground level photo simulations
(Figures 4-20, 4-22, and 424) from the June 2000 Draft EIS, shall be revised to
show a four-lane roadway design. Figures 4-25 and 4-26 shall be replaced with
one (1) new ground-level view photo simulation to represent the new southern
alignment.
PRODUCTS
Computer generated oblique view photographic images (two sets of four
images mounted on foam core boards for public display)
Computer generated ground-level photographic images (four revised images
for report figures)
20.3.4. Supplemental Draft EIS
The CONSULTANT shall prepare a Supplemental Draft EIS to present new
information on proposed project alternatives and traffic analysis based on the
outcome of the Phase I work plan. The Supplemental Draft EIS shall follow a
format consistent with guidance in the revised WSDOT Environmental Procedures
Manual (July 2001), guidance in the "Interagency Working Agreement to
Integrate Special Aquatic Resources (404) Permit Requirements into the NEPA and
SEPA processes in the State of Washington," (NEPA/SEPA/404 Merger
Agreement), and FHWA Technical Advisory T6640.8A. The CITY will provide
close coordination with WSDOT and FHWA throughout the process. The Supplemental
Draft EIS is anticipated to include the following sections and appendices
(however, the final organization and format may change in response to the CITY’s
needs):
20.3.4.1. Introductory Material
The following sections of the June 2000 Draft EIS shall be revised, as
appropriate:
Cover Sheet
Title Sheet
Fact Sheet
Table of Contents
List of Tables
List of Figures
20.3.4.2. Summary
The Summary section from the June 2000 Draft EIS shall be revised to include
a brief description of the proposed action, other governmental agency's actions
in the geographic area, a summary of alternatives and options considered,
summary of major environmental impacts (in table format with proposed mitigation
measures), areas of concern or controversy, unresolved issues, list of required
permits, and a list of other actions required for the proposed project.
20.3.4.3. Chapter 1: Purpose and Need for the
Action
This chapter shall be revised to identify and describe the proposed action
and the transportation problems or other needs which it is intended to address.
This discussion shall clearly demonstrate that a need exists for the project.
20.3.4.4. Chapter 2: Alternatives
This chapter shall be revised to describe the process used to identify
various - alternatives, the range of alternatives considered, and the
alternatives that were eliminated from further consideration. Chapter 2 shall
include the NEPA 404 Alternatives Analysis and Aquatic Resource Avoidance
Analysis consistent with the requirements of the NEPA/SEPA/404 Merger Agreement.
The analysis shall describe alternatives considered but rejected (and reason
why) including efforts to minimize or avoid impacts to aquatic resources, and
shall identify a preferred alternative, if known. A table shall be included
comparing the various impacts of each alternative.
Alternatives to be analyzed in the Supplemental Draft EIS include: • No
Action (no-build) Alternative
Alternative 1 (North A with a new south alignment)
Alternative 2 (North B with a new south alignment)
Alternative 3 (North C with a new south alignment)
A detailed description of the alternatives selected for analysis in the
Supplemental Draft EIS shall be provided, together with updated information on
estimated project costs and construction timing. The description of the
alternative design concepts shall be in sufficient detail to allow
identification of the specific characteristics of each design concept to be
evaluated. These characteristics include roadway layout, intersection
configurations, structural features, and other roadway related facilities. Maps,
alignment drawings, road sections, cost estimates, a proposed construction
schedule with milestones, and other exhibits shall be used to describe and allow
a comparison between the alternatives.
20.3.4.5 Chapter 3: Affected Environment
This chapter shall be revised to update the description of the existing
social and environmental setting for the area affected by the alternatives
presented in the Supplemental Draft EIS. The following elements of the
environment shall be reviewed and updated as necessary: study area, local
geography, geology and soils, hydrologic systems and floodplains, wetlands, fish
and wildlife habitat, land use, regional and community growth, historic and
archaeological elements, hazardous waste, and visual quality. It shall also
discuss the adopted land use and transportation plans as they relate to the
proposed project, including the City's Traffic Concurrency Ordinance. These
discussions shall be limited to data, information, issues, and values that will
have a bearing on possible impacts, mitigation measures, and on the selection of
an alternative.
20.3.4.6 Chapter 4: Environmental
Consequences
This chapter shall be revised to document the direct project impacts, future
operational impacts, secondary and cumulative impacts, construction activity
impacts and mitigation measures associated with each of the three new build
alternatives and the no-action alternative.
Direct project impacts are those impacts associated with the footprint or
right-of-way of each alternative.
Future operational impacts are those impacts resulting from ongoing
operation of the project that are anticipated to occur between the year of
opening (2005) and the design year (2030).
Secondary impacts are those that are "caused by an action and are later
in time or farther removed in distance but are still reasonably foreseeable" (40
CFR 1508.8). These impacts, which usually result from the initial action,
include changes in land use, water quality, economic vitality, and population
density.
Cumulative impacts are those that "result from the incremental
consequences of an action when added to other past and reasonable foreseeable
future actions" (40 CFR 1508.7). The cumulative effects of an action may be
undetectable when viewed in the individual context of direct and even secondary
impacts but can nonetheless add to other disturbances and eventually lead to a
measurable environmental change.
Construction activity impacts are limited to construction process impacts
that are temporary in nature and typically limited to the immediate project area
(e.g., construction noise, dust, traffic controls, etc.). The CONSULTANT is
assuming that the preferred alternative will be constructed in two stages: Stage
1 will involve construction of a twolane roadway; Stage 2 will involve widening
the initial two-lane facility to four lanes.
The environmental elements listed below shall be reanalyzed for each of fie
alternatives addressed in the Supplemental Draft EIS:
Air Quality
Noise
Energy
Geology and Soils
Hydrological Systems
Floodplains
Water Quality
Wetlands
Vegetation and Wildlife
Fisheries
Threatened and Endangered Species
Land Use
Social Elements
Economic Elements
Displacement and Relocation
Historic and Cultural Resources
Hazardous Waste
Visual Quality
The CONSULTANT shall prepare draft and final technical reports for Air
Quality and Noise only. Draft technical reports shall be submitted to the ClW
and the STATE for review and comment. No additional revisions to previously
prepared discipline reports are included. Any other discipline report changes
would be considered "extra work."
The CONSULTANT shall not perform additional floodplain modeling work (HEC-RAS)
as part of this work plan. Floodplain impact analysis and conceptual design for
the SETS alternatives performed by the CONSULTANT shall be based on the recently
updated floodplain information (Montgomery Water Group, 2001) provided to the
CONSULTANT by the CITY. Any additional HEC-RAS analysis would be considered
extra work.
PRODUCTS
Draft and Final Air Quality Reports (10 copies each of Draft and Final)
Draft and Final Noise Reports (15 copies each of Draft and Final)
20.3.4.7 Chapter 5: Comments and Coordination
The CONSULTANT shall update this chapter to summarize the results of
additional coordination with federal, state, and local agencies, their level of
involvement, and any unresolved issues or areas of conflict. This section shall
also summarize additional public involvement activities conducted as part of the
Supplemental Draft EIS.
20.3.4.8 Chapter 6: Section 4(f) Evaluation
The CONSULTANT shall update and revise the Section 4(f) evaluation to reflect
the impacts (both during construction and operation) associated with the new
build alternatives. The CONSULTANT shall identify and evaluate location and
design alternatives which would avoid each and all Section 4(f) properties;
explain whether any avoidance alternatives which were eliminated from further
study are "feasible and prudent" and if not, explain why; discuss all possible
measures which are available to minimize impacts on Section 4(f) properties,
including commitments made and monitoring procedures to minimize harm.
20.3.4.9 Response to Comments on Draft EIS
The CONSULTANT shall review and prepare responses to over 1,000 comments
received on the Draft EIS in letters and recorded testimony at the Draft EIS
public hearing. It is assumed that many of the comments received are similar
incontent and a response to one will be appropriate for many others. It is also
assumed that many of the comments will no longer be relevant because several of
the alternatives presented in the Draft EIS are no longer being considered.
Copies of the comment letters and recorded public testimony, along with the
responses to those comments, shall be presented in an appendix to the
Supplemental Draft EIS. During this task the CONSULTANT shall also review one
(1) "constituent proposal" and provide a written response to be included in an
appendix to the Supplemental Draft EIS.
20.3.4.10 Closing Sections/Appendices
The CONSULTANT shall prepare closing documentation for the SEIS, including
the following information:
Principal Contributors
Studies Performed
Supplemental Draft EIS Distribution List
Transportation Studies
Supplemental Alternatives Analysis
Historic Site Documentation
20.3.4.11 Preliminary Supplemental Draft EIS
The CONSULTANT shall revise the March 2003 Preliminary Supplemental Draft EIS
(Interoffice Working Version #1) and supporting discipline reports to respond to
cursory review comments received from WSDOT and FHWA in April 2003, and
technical review comments received from WSDOT at the end of May 2003. The
CONSULTANT shall take the lead on resolving outstanding issues with the
following agencies:
Interagency for Outdoor Recreation (IAC) to address issues related to
impacts on the Sportsmen’s Club
WSDOT and FHWA to address needed revisions to the Section 4(f)
Evaluation
WSDOT and SHPO to address impacts to the Sportsmen’s Club and other
Section 4(f) resources.
Twenty-five (25) copies of the revised Preliminary Supplemental Draft EIS
(Interoffice Working Version #1) shall be submitted to WSDOT and CITY for review
and comment. The CONSULTANT shall revise the documents and submit two (2) copies
to WSDOT for distribution to FHWA. The CONSULTANT shall revise the documents in
response to FHWA comments and submit twenty-five (25) copies of the revised
Preliminary Supplemental Draft EIS to WSDOT for distribution to FHWA, Signatory
Agency Committee (SAC) representatives, and technical reviewers at USACE, USFWS,
EPA, NMFS, Ecology and WDFW.
PRODUCTS
Revised Preliminary Supplemental
Draft EIS for CITY and WSDOT review (25 copies)
Revised Preliminary Supplemental
Draft EIS for FHWA review (2 copies)
Revised Preliminary Supplemental
Draft EIS for distribution to FHWA, SAC agencies and federal and state
agency technical reviewers (25 copies)
Revised Preliminary Supplemental
Draft EIS for distribution to WSDOT and the CITY (5 copies)
20.3.4.12 Camera-Ready Supplemental Draft EIS
The CONSULTANT shall meet with the CITY, WSDOT and FHWA to review comments
received on the Preliminary Supplemental Draft EIS and to develop a strategy for
proceeding with final revisions. This work plan assumes the CONSULTANT will need
to respond to a limited number of comments that can be addressed with
approximately 120 hours of total labor. If additional hours are required, that
effort would be considered Extra Work. The CONSULTANT shall prepare a
camera-ready version of the Supplemental Draft EIS for review by the CITY, WSDOT
and FHWA.
PRODUCTS
Camera-ready copy of the Supplemental Draft EIS (3 copies)
20.3.4.13 Reproduction and Distribution
Upon approval of the camera-ready Supplemental Draft EIS by FHWA, the
CONSULTANT shall reproduce 200 copies of the Supplemental Draft EIS for
distribution. The CITY will develop the distribution list and be responsible for
distributing the document to the agencies and the public.
PRODUCTS
200 copies of the Supplemental Draft EIS for submittal to the CITY for
distribution.
20.3.5 Public Hearing
A joint public hearing on the Supplemental Draft EIS and the Section 404
permit application will be conducted within 30-days following publication of the
Supplemental
Draft EIS. The CONSULTANT shall prepare materials for the hearing and provide
originals to the CITY for reproduction and distribution. Relevant CONSULTANT
activities shall include:
Assist the CITY in preparing the public hearing packet
Assist the CITY in preparing exhibits and handouts
Prepare a Synchro display showing traffic operations
Provide technical staff to attend the Public Hearing
It is assumed that up to four (4) CONSULTANT team staff shall attend the
public hearing. It is also assumed that the CITY will be responsible for
arranging the meeting place, arranging for a court reporter, preparing the
public notice for the joint Supplemental Draft EIS/Section 404 Public Hearing
Notice, and all other activities related to meeting organization and/or
preparation.
20.3.6 Final EIS
20.3.6.1 Respond to Comments on the
Supplemental Draft EIS
The CITY will provide the CONSULTANT with copies of the letters received with
comments on the Supplemental Draft EIS. The CITY will also provide the
CONSULTANT with a copy of the transcript recording public testimony received at
the public hearing. Revisions to the Supplemental Draft EIS shall be based on
the comment letters, public hearing testimony and agency comments received
during the review period.
The CONSULTANT shall compile a summary of comments received on the
Supplemental Draft EIS, provide responses to comments, and make recommendations,
if necessary, on the need for additional studies, additional mitigation or
changes to the design. For budgeting purposes, it is assumed that there will be
a maximum of 100 comment letters with 10 comments each for a total of 1,000
comments. If there are more than 100 comment letters or 1,000 comments, the
extra level of effort to address comments shall be considered "extra work."
20.3.6.2 Revise Environmental Analysis
The CONSULTANT shall revise the discussion of elements of the environment in
EIS to reflect changes in the project design, impacts, and proposed or required
mitigation that have occurred since publication of the Supplemental Draft EIS,
or in response to review comments on the Supplemental Draft EIS. Any proposed
additional studies, detailed analyses, or changes in design shall be considered
"extra work."
20.3.6.3 Preliminary Final EIS Document
The CONSULTANT shall produce a preliminary Final EIS and submit twenty-five
(25) copies to WSDOT and the CITY for review and comment. The CONSULTANT shall
revise the documents and submit two (2) copies to WSDOT for distribution to FHWA.
The CONSULTANT shall revise the document in response to FHWA comments and
provide twenty-five (25) copies of the preliminary Final EIS to WSDOT for
distribution to FHWA, SAC representatives, and technical reviewers at USACE,
USFWS, EPA, NMFS, Ecology and WDFW.
PRODUCTS
Preliminary Final EIS for CITY and
WSDOT review (25 copies)
Preliminary Final EIS for FHWA
review (2 copies)
Preliminary Final EIS for
distribution to FHWA, SAC agencies and federal and state agency technical
reviewers (25 copies)
Preliminary Final EIS for
distribution to WSDOT and the CITY (5 copies)
20.3.6.4 Camera-Ready Final EIS
The CONSULTANT shall revise the preliminary Final EIS in response to the
comments received from the CITY, WSDOT, FHWA and reviewing agencies. The
CONSULTANT shall prepare a camera-ready Final EIS and the CITY will coordinate
with WSDOT and FHWA on a second review to check and approve the changes and
authorize reproduction and issuance of the Final EIS.
PRODUCTS
Camera-ready copy of the Final EIS (3 copies)
20.3.6.5 Reproduction and Distribution
The CONSULTANT shall make the second round of minor revisions based on the
review and approval of the camera-ready Final EIS and reproduce 200 copies of
the Final EIS for distribution. The CITY will provide the distribution list and
be responsible for distributing the document to agencies and the public.
PRODUCTS
200 copies of the Final EIS for submittal to the CITY for distribution.
20.3.7 Record of Decision
The CONSULTANT shall assist the CITY in preparing the draft NEPA Record of
Decision (ROD) and shall address any Final EIS comments received from FHWA.
PRODUCTS
Draft Record of Decision (1 copy)
Final Record of Decision (1 copy)
20.3.8 Respond to Miscellaneous Public
Comments
If directed by the CITY, the CONSULTANT shall prepare responses to public
comments on deliverables prepared under this work plan. It is assumed that the
CONSULTANT shall spend four (4) hours responding to up to ten (10) public
comments. Additional effort by the CONSULTANT to respond to more than ten (10)
comments shall be considered "extra work".
20.4 NEPA/SEPA/404
MERGER ACTIVITIES
The CONSULTANT shall provide project coordination to comply with the
"Interagency Working Agreement to Integrate Special Aquatic Resources (404)
Permit Requirements into the NEPA and SEPA processes in the State of Washington,
"(NEPA/SEPA/404 Merger Agreement).
20.4.1 NEPA/SEPA/404 Merger Concurrence
Up to two (2) CONSULTANT team members shall attend a SAC briefing before or
during the agency review period for the Preliminary Supplemental DEIS.
20.4.2 Initial Mitigation Plan
Upon issuance of the Agency Concurrence Letter regarding alternatives to be
evaluated in the Supplemental Draft EIS and identification of the preferred
alternative, the CONSULTANT shall conduct a preliminary investigation of
candidate mitigation sites to determine if there are suitable sites to support
the required mitigation. Upon identification of candidate sites, the CONSULTANT
shall prepare a draft Initial Mitigation Plan for the preferred alternative, as
described in Appendix F of the NEPA/SEPA/404 Merger Agreement. The Draft Plan
shall identify unavoidable impacts to aquatic resources; establish the goals and
objectives of the mitigation; the timing of the mitigation; a general
description of the candidate sites; and proposed monitoring of the mitigation.
The Draft Plan shall be submitted to the CITY for review and comment.
The Draft Initial Mitigation Plan shall be revised to address the CITY's
comments. The revised Plan shall be submitted to the CITY for distribution to
other merger agencies for review and comment. The CITY will provide consolidated
comments on the Plan to the CONSULTANT. The CONSULTANT shall conduct a site
visit with the USACE to review candidate sites. The CONSULTANT shall prepare a
final Initial Mitigation Plan for inclusion in the Draft SEIS.
PRODUCTS
Draft Initial Wetlands Mitigation Plan for CITY review (10 copies)
Draft Initial Wetlands Mitigation Plan for agency review (15 copies)
Final Initial Wetlands Mitigation Plan for inclusion in the
Supplemental Draft EIS (one camera ready copy)
20.4.3 Section 404 Permit Application
Prior to submittal of the Preliminary Supplemental Draft EIS, the CONSULTANT
shall attend one pre-application meeting with the USACE to identify issues of
concern and confirm Section 404 permitting requirements and scheduling. The
CONSULTANT shall then prepare draft Section 404 permit application materials for
submittal to the CITY. The CITY will submit the permit application to the USACE.
Prior to publication of the Final EIS, the CONSULTANT shall prepare a final
Section 404 permit application for submittal to the USACE. The final application
shall include a Detailed Mitigation Plan and Report.
PRODUCTS
Draft Section 404 Wetland Permit Application
Final Section 404 Wetland Permit Application
20.4.4 Detailed Mitigation Plan and Report
Prior to publication of the Final EIS, the CONSULTANT shall prepare a draft
Detailed Mitigation Plan and Report for the preferred alternative, as described
in Appendix F of the NEPA/SEPA/404 Merger Agreement. The Draft Detailed
Mitigation Plan shall include a summary of wetland impacts, description of
proposed mitigation and mitigation site(s), mitigation design (hydrology source,
grading plan, soil preparation, planting plan, and schedule), standards of
success, and monitoring and contingency plans. The Draft Plan shall be submitted
to the CITY for review and comment. The Draft Plan shall be revised to address
the CITY's comments. The revised Plan shall be submitted to the CITY for
distribution to the merger agencies with the preliminary Final EIS.
Upon issuance of concurrence on the preliminary Final EIS by the reviewing
agencies, the CONSULTANT shall prepare a Final Detailed Mitigation Plan for
inclusion in the Final EIS. A Final Mitigation Plan as required by the NEPA/SEPA/404
Merger Agreement is not included in this Work Plan and shall be considered
"extra work".
PRODUCTS
Preliminary Draft Detailed Wetland Mitigation Plan and Report (10
copies) Draft Detailed Wetland Mitigation Plan and Report (15 copies)
Final Detailed Wetland Mitigation Plan and Report (one camera ready
copy)
20.5
CONCEPTUAL DESIGN
20.5.1 Supplemental Survey and Mapping
The CONSULTANT shall collect additional field survey with to update the
existing mapping that will enable development of the conceptual design to the
level necessary to provide a clear idea of the environmental impacts. Except for
critical culverts, underground utilities shall not be surveyed or mapped. The
CONSULTANT shall update the existing base map with the additional supplemental
survey data. This supplemental survey data shall be developed in metric units.
The survey work shall conform to NAD 83/91 and to the vertical datum used by the
CITY for this project.
PRODUCTS
Updated Aerial Base Mapping
20.5.2 Geotechnical Feasibility Study
The CONSULTANT shall conduct geotechnical investigations to support the
conceptual design task. These investigations include the following:
Conduct a detailed site reconnaissance along the new southern
alignment to evaluate existing conditions. Also conduct a reconnaissance
along the preferred north alignment to observe current site conditions.
Drill a total of eight (8) borings: Six (6) along the centerline
alignment of the new southern alternative and two (2) at the northerly
edge of the proposed roadway along the new southern alternative. The
borings shall be drilled to depths ranging from 15 to 40 feet using a
track-mounted drill rig. Soil samples shall be collected from the
borings at five-foot depth intervals. The CONSULTANT shall obtain
"Right-of-Entry" to complete the eight (8) soil borings.
Install a piezometer casing in the borings for ground water
monitoring. Monitor ground water levels on a monthly basis for six (6)
months following installation. The borings/piezometers shall be
backfilled in accordance with Washington State Department of Ecology
requirements.
Conduct limited laboratory testing on the soil samples obtained from
the borings. The testing shall include moisture content.
Evaluate the subsurface information obtained from the soil borings as
a basis for describing the existing conditions, impacts and mitigation
of identified environmental issues.
The CONSULTANT shall prepare a Geotechnical Feasibility Report that documents
the additional geotechnical activities described above, as well as the
geotechnical investigations conducted in support of the June 2000 Draft EIS. The
report shall identify preliminarily recommended slope support options including
but not limited to MSE walls, soldier pile walls, reinforced concrete walls, and
rockeries.
PRODUCTS
Draft Geotechnical Feasibility Report (3 copies)
Final Geotechnical Feasibility Report (3 copies)
20.5.3 Design Memorandum
A Design Memorandum summarizing the relevant geometric design criteria
applicable to CITY designated design or posted speed limits shall be prepared
based on applicable design standards and in accordance with the CITY'S Design
Standards and the WSDOT Local Agency Guidelines Manual, as well as the AASHTO
Green Book (See Attachment A). Particular emphasis shall be placed on
identifying those elements that may be subject to interpretation, engineering
judgment or modification due to adverse field conditions. The CONSULTANT shall
review the design elements with and seek approval by the CITY.
The Design Memorandum shall include documentation on design decisions, design
deviations, geotechnical and structural evaluations, stormwater management
issues and considerations, and a staged construction proposal.
PRODUCTS
Draft Design Memorandum (3 copies)
Final Design Memorandum (3 copies)
20.5.4 Refine Phase 1 Conceptual Design
The CONSULTANT shall complete conceptual design work for the three (3) build
alternatives begun during Phase 1 (Task 19.3.2). The three build alternatives
are comprised of one new southern alignment and three refined northern
alignments from the original Draft EIS (June 2000). The three northern
alignments can be matched with the one new southern alignment (at a common match
point) to yield three different alternatives providing a new north south
connection between I-90 and Front Street.
During this task the CONSULTANT shall refine the channelization features for
each of the alternatives to reflect the traffic needs for the year 2030 as
described in the Phase 1 Transportation Study (Task 19.3.1).
The CONSULTANT shall refine the roadway template, including retaining walls
and stormwater facilities, develop new cross sections, and refine slope lines to
allow determination of potential impacts to wetlands, streams, floodplains,
trails, existing homes, school district property and other elements of the
environment. Space for roadside landscaping shall be included along the western
edge of the proposed roadway. The CONSULTANT shall develop up to two (2) Typical
Sections to depict the roadway prism in the northern segment of each alternative
and one (1) Typical Section illustrative of all alternatives for the roadway
section in the southern segment.
Based on the results of this effort and the corresponding impacts, the
CONSULTANT shall revise the horizontal and vertical alignments up to two
additional times for each alternative, once in response to the CITY'S review
comments and once in response to comments received on the Supplemental Draft EIS,
to mitigate unfavorable impacts to existing natural resources, properties and
structures. With each vertical alignment revision, the CONSULTANT shall rerun
cross sections throughout the length of the vertical alignment revision and
revise slope lines to further determine their impact on the environment.
The CONSULTANT shall prepare a design that accommodates existing and proposed
pedestrian and bicycle facilities within the corridor, as well as appropriate
connections and extensions of existing trails. Type 11 bicycle lanes and
contiguous sidewalks are to be assumed.
The CONSULTANT shall coordinate with Issaquah School District officials to
identify appropriate and reasonable vertical alignments for each alternative
(including possible noise berm) to address school district concerns over
potential noise impacts to Issaquah High School. One (1) meeting with three (3)
people is assumed for budgetary purposes.
The CONSULTANT shall review and modify the size, type and location of
proposed stormwater management facilities to reflect the refined roadway design
and new floodplain elevation information (Montgomery Water Group, 2001) provided
to the CONSULTANT by the CITY.
If a revision in the horizontal and vertical alignment of the planned East
Sunset Way connection to the SE Issaquah Bypass is required because of
refinements to the SE Bypass design geometrics, that effort shall be considered
"extra work" and will be covered by a future change order.
PRODUCTS
Plans, profiles and typical sections for up to three (3) alternatives
identifying the proposed project design for the northern and southern
alignments shall be provided. Three (3) sets of drawings shall be provided for
up to three (3) submittals.
20.5.5 Stage 1 Conceptual Design
It is anticipated that the construction sequencing of the preferred
alternative will be shown to occur in two separate stages. The CONSULTANT shall
prepare Stage 1 plans that depict a two-lane roadway with bike lanes in each
direction and a sidewalk on the southbound side only. Retaining walls would be
located to accommodate an ultimate build out of a four-lane roadway section.
Three Typical Sections shall be prepared depicting the two-lane roadway in Stage
1. The Stage 1 plans shall also reflect the rightof-way acquisition needs to
accommodate the ultimate build out. Roadway profile changes are assumed not to
be required.
The CONSULTANT shall develop a stormwater management facilities design to
accommodate a two-lane roadway. Roadside ditches are assumed for the Stage 1
stormwater conveyance system. The CONSULTANT shall also design reduced-size
stormwater detention ponds appropriate for the Stage 1 construction.
PRODUCTS
Stage 1 plans and typical sections for one (1) submittal (3 sets).
20.5.6 Cost Estimates
The CONSULTANT shall prepare a conceptual cost estimate for each of the SETS
build alternatives. A refined cost estimate shall be prepared for the preferred
alternative reflecting a two-stage construction sequence. Costs shall be based
on standard bid item tables published by WSDOT and the CITY. The CITY will
provide estimated right-of-way costs based upon right-of-way requirements
identified by the CONSULTANT. Earthwork volumes shall be prepared for both Stage
1 and Stage 2 construction.
PRODUCT
Conceptual cost estimates for SEIS Build Alternatives (3 sets)
Conceptual cost estimate for preferred alternative with two-stage
construction (3 sets)
20.6 6TH
AVENUE SE ALIGNMENT
The CONSULTANT shall conduct additional transportation and environmental
analysis and preliminary design activities to include an additional southern
alignment in the Supplemental EIS. The additional southern alignment is assumed
to approximately follow the existing alignment of 6th Avenue SE.
20.6.1 Transportation Study
The CONSULTANT shall conduct additional transportation analysis to study an
additional southern alignment that approximately follows the alignment of 6th
Avenue SE and intersects with Issaquah-Hobart Road at approximately SE 96th
Street. The additional analysis shall include rerunning the TMODEL travel demand
forecasts for the 2030 build scenario to include the additional southern
alignment.
The CONSULTANT shall also conduct additional Synchro intersection/roadway
operational analysis for up to three (3) alignment combinations (i.e. the 6thAvenue
SE southern alignment with each of the three northern alignments). In addition,
the transportation analysis described in Task 20.3.1 of this work plan shall be
expanded to include analysis of the additional alternative for the opening year
of 2005.
20.6.2 Supplemental Draft EIS
The CONSULTANT shall expand the discussion and analysis in the Supplemental
Draft EIS to include an additional southern alignment that approximately follows
the alignment of 6th Avenue SE. The following sections of the EIS
document shall be revised to discuss the additional alternative:
Summary
Chapter 1 Purpose and Need for the Action
Chapter 2 Alternatives
Chapter 3 Affected Environment
Chapter 4 Environmental Consequences
Chapter 5 Comments and Coordination
Chapter 6 Section 4(f) Evaluation
The impact analysis in the Supplemental Draft EIS addressing the
environmental elements listed below shall be expanded to include analysis of the
additional southern alignment that approximately follows 6th Avenue
SE:
Air Quality
Noise
Energy
Geology and Soils
Hydrological Systems
Floodplains
Water Quality
Wetlands
Vegetation and Wildlife
Fisheries
Threatened and Endangered Species
Land Use
Social Elements
Economic Elements
Displacement and Relocation
Historic and Cultural Resources
Hazardous Waste
Visual Quality
The Air Quality and Noise modeling efforts and related technical reports
shall be expanded to include the additional southern alignment.
20.6.3 Final EIS
The CONSULTANT shall address public and agency comments received on the
Supplemental Draft EIS related to the additional southern alternative. For
budgeting purposes it is assumed that the addition of the 6thAvenue
southern alignment will add approximately 25% to the level of effort assumed for
this task in 20.3.6.1. The CONSULTANT shall revise the discussion of elements of
the environment in the EIS to reflect any changes in the project design, impacts
and proposed or required mitigation as they relate to the additional
alternative.
20.6.4 NEPA/SEPA/404 Merger Activities
The CONSULTANT shall coordinate with regulatory agencies to review and
comment on the additional southern alignment along 6th Avenue SE.
Additional studies required to obtain concurrence from the regulatory agencies,
or development and analysis of additional alternatives, shall be considered
"extra work."
Up to two (2) CONSULTANT staff shall attend up to three (3) additional
meetings with regulatory agencies to gain concurrence on the preliminary Final
EIS regarding the apparent final mitigation plan and the preferred
alternative/least environmentally damaging alternative, as specified in the NEPA/SEPA/404
Merger Agreement. Additional meetings, studies or revisions to alternatives that
may be needed to obtain concurrence shall be considered "extra work."
20.6.5 Conceptual Design
The CONSULTANT shall supplement the conceptual design work described in Task
20.5 of this work plan to include conceptual design of an additional 6thAvenue
SE alignment. The 6th Avenue SE alignment shall be designed to match
with any one of the three northern alignments (at a common match point) to yield
three different alternatives providing a new connection between I-90 and
Issaquah-Hobart Road.
During this task the CONSULTANT shall develop conceptual plan, profile, and
typical section for an alignment that reflects the traffic channelization needs
for the year 2030 as determined in the Task 20.1.6, above.
The CONSULTANT shall prepare a roadway template, including retaining walls
and stormwater facilities, develop new cross sections, and refine slope lines to
allow determination of potential impacts to wetlands, streams, floodplains,
trails, existing homes, school district property and other elements of the
environment. Space for roadside landscaping shall be provided along the western
side of the proposed roadway. The CONSULTANT shall develop one (1) Typical
Section to further clarify the roadway prism at a selected location along the
alignment.
Based on the results of this effort and the corresponding impacts, the
CONSULTANT shall revise the horizontal and vertical alignments up to two
additional times, once in response to the CITY'S review comments and once in
response to comments received on the Supplemental Draft EIS, to mitigate
unfavorable impacts existing natural resources, properties, and structures. With
each vertical alignment revision, the CONSULTANT shall rerun cross sections
throughout the length of the vertical alignment revision and revise slope lines
to further determine their impact on the environment.
The CONSULTANT shall accommodate existing and proposed pedestrian and bicycle
facilities within the corridor, as well as appropriate connections and
extensions of existing trails. Type II bicycle lanes and contiguous sidewalks
are anticipated.
The CONSULTANT shall review and modify the size, type and location of
proposed stormwater management facilities to reflect the new southern roadway
alignment.
PRODUCTS
Plan, profile and typical section identifying the proposed project design
for the additional southern alignment shall be provided. Three (3) sets of
drawings shall be provided for up to three (3) submittals.
20.6.6 6th Avenue SE Stage 1 Conceptual
Design
- The CONSULTANT shall prepare Stage 1 plans that depict a two-lane roadway
with bike lanes in each direction and a sidewalk on the southbound side only.
Retaining walls, if any, would be located to accommodate the ultimate build-out
of a four-lane roadway section. One (1) Typical Section shall be prepared
depicting the two-lane roadway in Stage 1. The Stage 1 plans shall also reflect
the right-of-way acquisition needs to accommodate the ultimate build out.
Roadway profile changes are assumed not to be required.
- The CONSULTANT shall develop a Stage 1 stormwater management facility design
to accommodate a two-lane roadway. Roadside ditches are assumed for the Stage 1
stormwater conveyance system. The CONSULTANT shall also design reduced-size
stormwater detention ponds appropriate for the Stage 1 construction.
- PRODUCTS
- Stage 1 plan and typical section for one (1) submittal (3 sets).
20.6.7 Cost Estimates
The CONSULTANT shall revise the conceptual cost estimates described in Task
20.5.5 to include the additional 6th Avenue alignment. Costs shall be based on
standard bid item tables published by WSDOT and the CITY. The CITY will provide
estimated right-of-way costs based upon right-of-way requirements identified by
the CONSULTANT.
20.6 ATTACHMENT A - DESIGN GUIDELINES
The CITY will designate the basic premises and criteria for the design.
Reports and plans, to the extent feasible, shall be developed in accordance with
the latest edition and amendments to the following:
City of Issaquah Publications
Issaquah Design Standards
Critical Areas Ordinance
King County Publications
Road Standards 1994
General Special Provisions 1991
Surface Water Design Manual
Community Plan
Basin Studies
Sensitive Areas Ordinance
Washington State Publications
Standard Specifications for Road, Bridge, and Municipal Construction
(M41-10)
Standard Plans for Road, Bridge, and Municipal Construction
(M21-01)
Amendments and General Special Provisions • Standard Item Table
Highway Design Manual
Bridge Design Manual
Construction Manual
Local Agency Guidelines
DOE Stormwater Management Manual forthe Puget Sound Basin
Hydraulics Manual
American Association of State Highway and Transportation Officials
Publications
A Policy on Geometric Design of Highways and Streets
(2000)
A Policy on Geometric Design of Highways and Streets
(1994)
(Green Book)
Standard Specifications for Highways Bridges,
Twelfth Edition
(1977)
A Guide for Highway Landscape and Environmental Design
(1970)
Highway Design and Operational Practices Related to Highway Safety
(1974) (Yellow Book)
Any American Association of STATE Highway Officials policy applicable
where said policy is not in conflict with CITY standards
U.S. Department of Transportation Publications
Manual on Uniform Traffic Control Devices for Streets and Highways
Other Publications
National Electrical Code
Transportation Research Board Highway Capacity Manual (1994)
20.7 BIOLOGICAL ASSESSMENT
The CONSULTANT shall review and revise the Biological Assessment (BA)
prepared for the June 2000 Draft EIS. The BA will be revised to describe the
impacts of the new alternatives on federally listed, proposed, and candidate
species and designated and proposed critical habitat present in the project
vicinity. The CONSULTANT will submit 10 copies of the Revised Draft BA to the
CITY for review and comment. The CONSULTANT will revise the document and provide
10 copies of the Revised Draft BA for distribution with the Preliminary SDEIS to
the USACOE, USFWS, EPA, NMFS, Ecology and WDFW. Special effort will be made
during this task to follow the guidance in the July 2001 WSDOT Environmental
Procedures Manual.
PRODUCTS
Revised Draft BA for CITY review (10 copies)
Revised Draft BA for review by cooperating agencies (10 copies)
20.8 Final
Environmental Impact Statement
20.8.1 Respond to
Comments on the Supplemental DEIS
The CITY will provide the CONSULTANT with copies of the letters received with
comments on the SDEIS. The CITY will also provide the CONSULTANT with a copy of
the transcript recording public testimony received at the public hearing.
Revisions to the Supplemental DEIS will be based on the comment letters, public
hearing testimony and agency comments received during the review period.
The CONSULTANT shall compile a summary of comments received on the SDEIS,
provide responses to comments, and make recommendations, if necessary, on the
need for additional studies, additional mitigation or changes to the design. For
budgeting purposes, it is assumed that there will be a maximum of 100 comment
letters with 10 comments each for a total of 1,000 comments. If there are more
than 100 comment letters or 1,000 comments, this extra level of effort will be
considered "extra work."
20.8.2 Revise Environmental Analysis
The CONSULTANTS shall revise the discussion of any elements of the EIS
necessary to reflect changes in the project design, impacts, and proposed or
required mitigation that have occurred since publication of the SDEIS, or in
response to review comments on the SDEIS. Any proposed additional studies,
detailed analyses, or changes in design would be considered "extra work."
20.3.8 Prepare Preliminary Final EIS Document
The CONSULTANT shall prepare a preliminary Final EIS and submit 10 copies to
the CITY for review and comment. The CONSULTANT will revise the document and
provide copies of the preliminary Final EIS (including the final alternatives
analysis, identification of the preferred alternative and apparent least
environmentally damaging practicable alternative, and apparent final wetland
mitigation plan) to the USACOE, USFWS, EPA, NMFS, Ecology and WDFW. The Final
EIS will incorporate changes that reflect changes in the PROJECT scope, impacts,
technical analysis and mitigation analysis that have occurred since the SDEIS.
The Final EIS will include comments received on the SDEIS, a summary of the
comments, responses to comments, and an updated fact sheet.
PRODUCTS
Preliminary Final EIS for CITY
review (10 copies)
Preliminary Final EIS for review by
cooperating agencies (10 copies)
20.8.4 Final EIS Production
The CITY will provide consolidated comments on the
preliminary Final EIS to the CONSULTANT. It is assumed that cooperating agencies
will submit comments separately. The CONSULTANT shall revise the preliminary
Final EIS in response to the comments received from the CITY and cooperating
agencies and prepare a final detailed wetland mitigation plan. The CONSULTANT
will prepare a camera ready Final EIS and the CITY will conduct a second review
to check and approve the changes and authorize reproduction and issuance of the
Final EIS.
The CONSULTANT shall make the second, minor revisions based on the review and
reproduce 200 copies of the Final EIS for distribution. The CITY will provide
the distribution list for the FEIS and will be responsible for distributing the
document to the public and agencies.
PRODUCTS
Camera Ready Final EIS (1 camera
ready copy)
Final EIS (200 copies)
20.8.5 Record of Decision
The CONSULTANT shall assist the CITY in preparing the draft NEPA Record of
Decision (ROD) and shall address any Final EIS comments received.
PRODUCTS
Draft Record of Decision
Final Record of Decision
20.9 NEPA/SEPA/404 MERGER ACTIVITIES
The CONSULTANT shall provide project coordination to comply with the
"Interagency Working Agreement to Integrate Special Aquatic Resources (404)
Permit Requirements into the NEPA and SEPA processes in the State of
Washington," (NEPA/SEPA/404 Merger Agreement).
20.9.1 NEPA/SEPA/404 Merger Concurrence
The CONSULTANT shall coordinate with regulatory agencies to gain concurrence
on the preliminary SDEIS regarding project alternatives to be evaluated in the
SDEIS, preliminary preferred alternative, and initial and detailed wetland
mitigation plans. Additional studies required to obtain concurrence, or
development and analysis of additional alternatives, will be considered "extra
work." Preparation of the final version of the SDEIS cannot proceed without
issuance of a letter of concurrence from the cooperating agencies.
The CONSULTANT shall coordinate and meet with regulatory agencies to gain
concurrence on the preliminary Final EIS regarding the apparent final mitigation
plan and the preferred alternative/least environmentally damaging alternative,
as specified in the NEPA/SEPA/404 Merger Agreement. Additional studies or
revisions to alternatives that may be needed to obtain concurrence will be
considered "extra work." Publication of the Final EIS cannot occur without
issuance of a letter of concurrence from the cooperating agencies.
20.9.2 Initial Mitigation Plan for Preferred
Alternative
Upon issuance of the Agency Concurrence Letter regarding alternatives to be
evaluated in the SDEIS and identification of the preferred alternative, the
CONSULTANT shall conduct a preliminary investigation of candidate mitigation
sites to determine if there are suitable sites to support the required
mitigation. Upon identification of candidate sites, the CONSULTANT shall prepare
a draft Initial Mitigation Plan for the preferred alternative, as described in
Appendix F of the NEPA/SEPA/404 Merger Agreement. The draft Plan will identify
unavoidable impacts to aquatic resources; establish the goals and objectives of
the mitigation; the timing of the mitigation; a general description of the
candidate sites; and proposed monitoring of the mitigation. No drawings will be
included in the Plan. The draft Plan will be submitted to the CITY for review
and comment.
The draft Initial Mitigation Plan will be revised to address the CITY’s
comments. The revised Plan will be submitted to the CITY for distribution to
other merger agencies for review and comment. The CITY will provide consolidated
comments on the Plan to the CONSULTANT. The CONSULTANT shall conduct a site
visit with the USACOE to review candidate sites. The CONSULTANT shall prepare a
final Initial Mitigation Plan for inclusion in the Draft SEIS.
PRODUCTS
Draft Initial Wetlands Mitigation Plan and Report for CITY review (10
copies)
Draft Initial Wetlands Mitigation Plan and Report for cooperating agency
review (10 copies)
Final Initial Wetlands Mitigation Plan and Report for inclusion in the
SDEIS (one camera ready copy)
20.9.3 Section 404 Permit Application
Preparation
Prior to submittal of the Preliminary SDEIS, the CONSULTANT shall attend one
pre-application meeting with the USACOE to identify issues of concern and
confirm Section 404 permitting requirements and scheduling. The CONSULTANT shall
then prepare draft Section 404 permit application materials for submittal to the
CITY. The CITY will process the permit to the USACOE. Prior to publication of
the Final EIS, the CONSULTANT shall prepare a final Section 404 permit
application for submittal to the permitting agencies. The final application will
include a detailed Mitigation Plan and Report.
PRODUCTS
Draft Section 404 Wetland Permit Application
Final Section 404 Wetland Permit Application
20.9.4 Detailed Mitigation Plan and Report
Prior to publication of the Final EIS, the CONSULTANT shall prepare a draft
Detailed Mitigation Plan and Report for the preferred alternative, as described
in Appendix F of the NEPA/SEPA/404 Merger Agreement. The draft Plan will include
a summary of wetland impacts, description of proposed mitigation and mitigation
site(s), mitigation design (hydrology source, grading plan, soil preparation,
planting plan, and schedule), standards of success, and monitoring and
contingency plans. The draft Plan will be submitted to the CITY for review and
comment. The draft Plan will be revised to address the CITY’s comments. The
revised Plan will be submitted to the CITY for distribution to the merger
agencies with the preliminary Final EIS.
Upon issuance of concurrence on the preliminary Final EIS by the cooperating
agencies, the CONSULTANT shall prepare a final Detailed Mitigation Plan for
inclusion in the Final EIS. A Final Mitigation Plan as required by the NEPA/SEPA/404
Merger Agreement is not included in this Work Plan and will be considered "extra
work".
PRODUCTS
Draft Detailed Wetland Mitigation Plan and Report for CITY review (10
copies)
Draft Detailed Wetland Mitigation Plan for cooperating agency review (10
copies)
Final Detailed Wetland Mitigation Plan for inclusion in the SDEIS (one
camera ready copy)
Change Order #3

Change Order #4

Change Order #5
Scope
of Services for Additional Alternatives
Analysis for the SE Issaquah Bypass Project
The CONSULTANT
will
provide
research and analysis to expand on the SE Issaquah
Bypass Final Alternatives Analysis (May 1997). This effort will build on, and
provide additional support for, the previous screening of potential
alternatives that may be considered in environmental review for the SE
Issaquah Bypass project.
Task
1: Project Management
1.2 Monthly Billings
and Progress Reports
The CONSULTANT will prepare monthly progress reports
describing the status of the PROJECT. These reports will:
• Highlight significant accomplishments
• Target potential problem areas needing special attention or
coordination
• Compare actual work
progress with contractual obligations on a design task basis
The
progress reports will be presented in a task oriented format and will include
updated scheduling reports, indicating all progress to date and resources
expended. This update will include any changes in schedule, sequence, or
resource loading. If any schedule slippage has occurred, a plan for bringing
the work back on schedule and budget will be included.
Progress
reports and billings will be prepared by the CONSULTANT and submitted on a
monthly basis. These items will be supported by detailed record keeping
sufficient to closely track the PROJECT budget and expenditures and support
the billings.
PRODUCTS
Monthly Progress Reports (approximately 2 additional progress
reports), incorporating Project Schedule revisions as appropriate, and Monthly
Billings (approximately 2 additional billings).
1.3 Direction,
Meetings, and Coordination
This task
includes the following project management items:
• Technical direction to project staff
• Coordination meetings with the CITY on a bi-monthly basis
• Meetings with third parties such as CITY, State, and Federal officials,
and other consultants, as necessary up to 4 meetings
• Coordination with subconsultants
Technical
review
Task
7.11 Historic, Archaeological, and
Cultural
Resources
Completion of Section 106
coordination for the proposed SE Bypass alignments by Northwest Archaeological
Associates (NWAA) as indicated in the attached scope and budget dated July 5,
1999. NWAA will review the assessment of effects on the White Swan Inn and the
Issaquah Sportsman's Clubhouse, and complete consultation with the Office of
Archaeology and Historic Preservation and interested parties. This will
include a site visit to the Issaquah Sportsman's Clubhouse, preparation of the
Section 4(f) evaluation, and the Memorandum of Agreement if necessary.
Task 10: NEPA/SEPA/404 Merger
Process
10.
1 Concurrence Point 1
Review and research related to project purpose and need
including documentation of background on purpose and need development.
Analysis of purpose and need definitions in the Transportation Technical
Report and Final Alternatives Analysis report, and approach to defining SE
Bypass purpose and need for meeting with resource agencies on March 31. Review
of SE Bypass purpose and need, NEPA and FHWA guidelines on purpose and need,
and preparation of revised SE Bypass purpose and need statement for April 27
meeting with resource agencies.
10.3
Concurrence Point 2
Review and research related to alternative alignments
including evaluation of the previous SE Bypass Final Alternatives Analysis.
Documentation of previous consideration of alternative alignments in 1-90
Access, Sunset Interchange, East Sammamish Alternatives Feasibility, and
Issaquah High Capacity Transit studies. Review of fatal flaws for May Valley
Road and Newport Way Alternatives; land use project assumptions used in
Issaquah traffic modeling; existing conditions modeling for Issaquah traffic;
evaluation of approaches to defining the No Action alternative; background on
TDM/CTR programs in Issaquah; strategies for making greater use of existing
infrastructure in Issaquah; future plans for transit service and additional
transit funds; Issaquah's commitment to access control for the SE Bypass;
environmental impacts resulting from the proposed wetland bridging
alternative; and fish usage in the North Tributary stream in the project for
the March 31 meeting with resource agencies.
Background on
independent utility for the SE Bypass project; additional analysis of traffic
impacts of the May Valley Road and Newport Way alternatives including
interchange and arterial volumes, and level of service associated with these
approaches; qualitative assessment of potential environmental impacts
associated with May Valley Road and Newport Way alternatives; and additional
information on shading impacts and fish usage associated with the SE bypass
alternatives for the April 27 meeting to discuss concurrence issues. This
task also includes engineering design of the proposed bridging alternative
for South A and B alignments.
10. 9 Meetings and
Coordination
CONSULTANT attendance at March 31 and April 27 meetings with
resource agencies. Preparation and distribution of revised concurrence forms.
Meetings with King County (May 10), Corps of Engineers (May 26), Mike Birdsall
from EarthTech (June 23), and communication and coordination with resource
agencies regarding revisions in purpose and need, and agency issues related to
alternative alignments.
10.9.1 Attend Meetings and Coordinate with Agencies and
Subconsultants
The
CONSULTANT will coordinate with the City of Issaquah, King County, resource
agencies and subconsultants as required to complete additional alternatives
analysis and Merger Process concurrence. Up to 10 meetings will be attended.
10.9.2 Present Findings to Resource Agencies
The CONSULTANT will prepare
for, and attend, one meeting with the Merger Resource agencies to present
results of the additional alternatives analysis completed in Tasks 13-16
below. This task will include preparation of any display boards or other
presentation materials needed for this meeting.
Task 13: Research Congestion
Pricing
Alternative
13.1
Research and Analyze Transportation Impacts
The CONSULTANT will provide research and analysis of an
alternative involving the use of congestion pricing in Issaquah to encourage the use of alternative
routes, alternative modes of transportation, or a shift in driving to off-peak
periods. Tasks included in this research include the following: research
impacts of congestion pricing in other areas; describe assumptions included in
the congestion pricing scenario; review assumptions with City of Issaquah and
revise; develop two scenarios for inclusion in the network model; develop
ranges for the potential cost for each scenario; for each scenario analyze
model results for potential changes in vehicle trips for the year 2015; for
each scenario analyze model results for potential changes in VMT for year
2015; evaluate the potential queue area required for 3 toll booths; for each
scenario evaluate impacts to operations at twelve signalized intersections for
year 2015 (see section 15.1 for a list of intersections); prepare
presentation; incorporate comments and feedback; and prepare final results in
tech memo or presentation. The development of a congestion pricing scenario
will include an overview of opportunities for coordinated expansion of transit
service to support this alternative (see Transit Service Alternative below).
This alternative will be evaluated individually, and also in combination with
the proposed SE Bypass project. This analysis will provide information for a
combined approach to be included
in the alternatives matrix (Task 16.2 below) as SE Bypass with Congestion
Pricing alternative.
13.2
Environmental Impacts
of Congestion Pricing
The CONSULTANT will provide a
qualitative description of potential impacts to the elements of the natural
and social environment that may result from this alternative. A general
discussion of toll booths and other facilities (such as parking) that would be
needed to support this alternative will be provided. The CONSULTANT will
identify the effectiveness of this alternative in meeting the purpose and need
to be addressed by this project. The environmental analysis also will include
the combined SE Bypass with Congestion Pricing alternative identified above.
Task
14: Research Transit Service
Alternative
14.1
Research and Analysis
The CONSULTANT will provide research and analysis of transit
service improvements that could be implemented as a separate alternative to
constructing the SE Bypass roadway. Tasks included in this research include
the following: The CONSULTANT will describe potential use of an expanded
shuttle/transit service in the city. Potential use of an expanded
shuttle/transit service in the city will be based on discussions with King
County Metro transit service planners, and an analysis of previously collected
data. Activities included in this subtask include the following: develop
assumptions included in preliminary transit alternative; prepare overview of
alternative for King County and City of Issaquah; develop two transit
alternative scenarios for inclusion in network model; for each scenario,
analyze model results; for each scenario, develop range for costs; evaluate
impacts to twelve signalized intersections for each scenario; analyze
potential change in vehicle trips; analyze potential change in VMT; prepare
presentation materials; incorporate comments and feedback from presentation;
and prepare final results in a tech memo or presentation. This alternative
will be evaluated individually, and also in combination with the proposed SE
Bypass project. This analysis will provide information for a combined approach
to be included in the alternatives matrix (Task 16.2 below) as SE Bypass with
Transit alternative.
14.2
Environmental
Impacts of Transit
Service
The
CONSULTANT will provide a qualitative description of potential impacts to the
elements of the natural and social environment that may result from this
alternative. The CONSULTANT will identify the effectiveness of this
alternative in meeting the purpose and need to be addressed by this project.
The environmental analysis also will include the combined SE Bypass with
Transit alternative identified above.
TASK
15: ALTERNATIVES ALIGNMENT REVIEW
The CONSULTANT will review
only the Newport Way, May Valley, and Front Street to I-90 alternative
corridors previously studied in the Alternatives Alignment Study completed in
May 1997 for this project.
15.1
Transportation
Analysis
The CONSULTANT will review existing transportation conditions
for both the Newport Way and May Valley alternatives. New network modeling
will be required for this task. Year 2015
volumes will be used to determine intersection Level Of Service along each of
the proposed alternatives and along Front Street. This information will be
used to evaluate the alternatives for the "Decreases Traffic Congestion"
criterion in the Alternatives Alignment Study. Based on the purpose and need,
the determining factor will be whether the alternative significantly decreases
congestion in the future along the Front Street corridor. Intersections
evaluated using Transyt-7F or HCS/NCAP are the following: SR 900 and WB Ramps;
SR 900 and EB Ramps; SR 900 and Gilman; SR 900 and Maple; Front St. WB Ramps;
Front St. EB Ramps; Front and Gilman; Front and Sunset; SR 900 and Newport,
May Valley Road and Hobart; May Valley Road and 128`h; and May
Valley Road and SR 900.
Tasks involved include data
collection and coordination with the network modeling subconsultant; an
initial set-up for each intersection for the Transyt-7F/HCS analysis,
Transyt-7F and HCS analysis for each scenario for each intersection for the AM
and PM peak periods; and summarizing of results.
15.2
Alternative
Definition
Both the Newport Way and May Valley build alternatives will
be further defined. This will include number of additional lanes required,
approximate lengths of widening, and any structural elements needed to
accomplish the widening. The above transportation analysis will aid in
defining the need for additional lanes.
Geometric feasibility with respect to deviations from
standards will be reviewed. A rough cost estimate will be computed for each of
the two alternatives to provide a relative comparison to the Bypass.
15.3
Environmental
Review
The
CONSULTANT will review the Newport Way and May Valley build alternatives to
determine environmental impacts consistent with the Alternatives Alignment
Study. The number of residential and commercial displacements will be counted.
The approximate area of recreational space affected and approximate
right-of-way requirements will be determined. Sensitive areas impacted by the
proposed alternative such as streams, vegetation, wetlands, and slopes, will
be determined. This task may include a field visit to review sensitive areas
along these routes.
TASK
16: ADDENDUM TO ALTERNATIVES
ALIGNMENT
STUDY
16.1
Report Addendum
The CONSULTANT will use the information obtained in tasks 13
through 15 to prepare an addendum to the Alternatives Alignment Study
completed in May of 1997. This addendum will be written for the Newport Way,
May Valley, Congestion Pricing, Transit, Front Street to 1-90, Front Street to
1-90 in combination with Congestion Pricing, and Front Street to 1-90 in
combination with Transit alternatives
only. The addendum
will include descriptions of the alternatives, as well as discussion on each
of these alternative's merits and shortfalls as related to Project Goals,
Social/Economic Impacts, Natural Environment Impacts, Transportation
Improvements, and Cost. Part of this effort will include revising the criteria
for the study and providing more detailed descriptions of all criteria.
Products
Draft Addendum to the Alternatives Alignment Study (6 copies)
Final Addendum to the Alternatives Alignment Study (12 copies)
16.2
Matrix Addendum
An update to the existing Southeast Issaquah Bypass Corridor
Alternative Fatal Flaw Matrix will be provided by the CONSULTANT with ratings
on the Newport Way, May Valley, Congestion Pricing, Transit, Front Street to
1-90, and Combination alternatives only. These ratings will be on a one to
three basis rather than a pass/fail basis. The matrix completed in this task,
together with the addendum prepared in the above task, will be the basis for
the decision to cant' forward any of these seven alternatives into the DEIS.
Products
Draft
Addendum to the Fatal Flaw Matrix (6 copies) Final Addendum to the Fatal Flaw
Matrix (12 copies)
Task
17: Incorporate Results of
Additional
Alternatives
Analysis in SE Bypass DEIS
17.1 Expand Draft
EIS Alternatives Discussion
The
CONSULTANT will be responsible for incorporating the results of the additional
alternatives analysis provided for in the tasks above, within the SE Bypass
Draft EIS. This would involve supplementing the discussion of 'Alternatives
Considered but Rejected for Further Analysis,' and may include adding new
alternatives for analysis throughout the DEIS. The cost estimate provided here
is for supplementing the 'Alternatives Considered but Rejected' discussion only.
If the additional alternatives analysis results in a determination that new
alternatives are to be analyzed throughout the Draft EIS, a separate contract
amendment to the Draft EIS contract, based on the additional alternative(s) to
be analyzed, would be prepared and submitted by the CONSULTANT.
Change Order #6

Change Order #7





Change Order #8
Phase I Work Plan
Southeast Issaquah Bypass
Supplemental Environmental Impact Statement
and Preliminary Engineering Design
Supplement No. ___
Contract No. ___
October 2001
10/24/06
6:35 AM
Introduction AND ASSUMPTIONS
The work plan presented here
for the Southeast Issaquah Bypass project is for the preparation of a
Supplemental Environmental Impact Statement (SEIS) to the Draft Environmental
Impact Statement (June 2000) for a new bypass arterial connecting I-90 to the
Issaquah-Hobart Road. The SEIS is being prepared to analyze a new southern
alignment in combination with three possible northern alignments as presented in
the Draft EIS. The No Action Alternative will also be included. This work plan
represents a new supplement to Parsons Brinckerhoff’s existing contract for the
SE Issaquah Bypass project.
The SEIS will be prepared consistent with the requirements
of the National Environmental Policy Act (NEPA). It will meet the requirements
of the National Environmental Policy Act (NEPA) with respect to possible actions
by the Federal Highway Administration (FHWA ) and possible permit actions by the
U.S. Army Corps of Engineers (USACOE). The SEIS will also meet the requirements
of the Washington State (STATE) Environmental Policy Act (SEPA) with respect to
possible actions by the Washington State Department of Transportation (WSDOT)
and the City of Issaquah (CITY). When similar activities are called for under
both NEPA and SEPA, such as circulation times or length of comment periods, the
longer of the two time periods will govern.
The EIS will be prepared in accordance with the procedures
set forth in the
WSDOT Local Agency Guidelines, the
WSDOT Environmental Procedures Manual, and applicable guidance from
the FHWA. The SEIS will also comply with the “Interagency Working
Agreement to Integrate Special Aquatic Resources (404) Permit Requirements into
the NEPA and SEPA processes in the State of Washington,” referred to herein as
the NEPA/SEPA/404 Merger Agreement. The SEIS will be prepared using metric
measurements with English measurements shown in parentheses behind the metric
measurements. The environmental documentation will be prepared following the
format guidelines from the SE Issaquah Bypass Draft EIS.
Alternatives to be considered in the SEIS will include:
·
No Action (no-build) Alternative
·
One new south alignment and three refined north alignments from
the Draft EIS. The north and south alignments meet at a common point, either
north alignment can be matched with the newly designed southern alignment, to
yield three build alternatives: 1) Southern alignment with North S, and 2)
Southern alignment with North B, and 3) Southern alignment with North A.
The work plan for preparing the SEIS is divided into two
phases. Phase I will involve the following tasks:
·
Updating the traffic model to reflect 2030 design year
·
Refining the preliminary design for one new south alignment and
three north alignments from the Draft EIS
·
Conducting additional wetlands and stream studies to the degree
necessary to support preliminary design refinements
·
Updating the conceptual drainage plan to accommodate changes in
the preliminary design
·
Resolving questions regarding Section 4(f) resources and how they
might affect preliminary design and the selection of a preferred alternative
·
Additional coordination with agencies under the 404 Merger Process
Assumptions
Phase 2 to be completed under a future supplement will
involve preparing a draft and final Supplemental EIS document, participating in
a required public hearing and additional agency meetings, and assisting the City
in obtaining a Record of Decision.
This study assumes that the Park Pointe intersection identified in the northern
alignments will remain
as designed.
It is also assumed that the design will include a lowering of the vertical
profile
of the southern
alignment
to mitigate potential
noise
impacts
on the high school.
Task 19.1
Project Management
19.1
Project Management Plan
The CONSULTANT
shall update the project management plan for the Supplemental EIS through
the Final Environmental Impact Statement (FEIS) and Design Report. The plan will
include new information related to preparation of the SEIS, and a new project
schedule will be prepared.
19.2
Monthly Billings and Progress Reports
The CONSULTANT
shall prepare monthly progress reports describing the status of the
PROJECT. These reports will:
·
Highlight significant accomplishments
·
Target potential problem areas needing special attention or
coordination
·
Compare actual work progress with contractual obligations on a
design task basis
The progress reports will be presented in a task oriented
format and will include updated scheduling reports, indicating all progress to
date and resources expended. This update will include any changes in schedule,
sequence, or resource loading. If any schedule slippage has occurred, a plan
for bringing the work back on schedule and budget will be included.
Progress reports and billings will be prepared by the
CONSULTANT and submitted on a monthly basis. These items will be supported by
detailed record keeping sufficient to closely track the PROJECT budget and
expenditures and support the billings.
PRODUCTS
·
Monthly Progress Reports, incorporating Project Schedule
revisions as appropriate, and Monthly Billings. Approximately 4 progress
reports and billings will be provided.
19.3
Direction, Meetings, and Coordination
This task includes the following project management items:
1.3.119.3.1
Team Coordination/General Direction
This task includes internal
staff meetings and discussions to direct efforts and facilitate completion of
project tasks.
1.3.219.3.2 Meetings with
City Staff
Regularly scheduled meetings
(two per month) with Issaquah staff to review progress and discuss upcoming
actions will be held. This task would also include additional meetings with City
staff members as needed to obtain information or resolve project issues. The
CONSULTANT shall prepare meeting minutes to summarize issues discussed.
1.3.419.3.3Meetings/Coordination
with Others
This task would provide for
meetings and coordination with outside agencies to provide information or
discuss project issues. The CONSULTANT shall prepare meeting minutes to
summarize issues discussed with participating agencies.
PRODUCTS
·
Meeting notes documenting topics discussed and future action
items will be prepared and distributed as appropriate.
TASK 19.2
QUALITY CONTROL
19.2.1 Quality Assurance
The work
products will be reviewed by consultant team staff with expertise in the
appropriate discipline areas. This will be an ongoing activity during the
duration of the project with emphasis on major deliverable work products.
TASK 19. 3
Supplemental
EIS
19.3.1 Transportation Study
Phase 1 will include those
tasks necessary to define alternatives to be evaluated in the Supplemental EIS
based on a design year 2030 traffic model. Included will be updated traffic
modeling data, new analyses of traffic operations based on new model data, a
review of potential refinements to the north alignments, as well as the study of
one new possible south alignments.
19.3.1.1 Traffic Model Refinement
A future year 2030 traffic model (TMODEL Software), which
will include a highway network of all freeways, freeway interchanges, arterials
and other streets in the study area will be developed for use in subsequent
tasks for the SE Bypass SEIS. This model will replace the traffic model used
for preparation of the SE Bypass Draft EIS (June, 2000). The 2030 SE Bypass
model will be developed using the
SR 900 Widening project
model as a base, and will focus primarily on the Issaquah area (both
incorporated and unincorporated Issaquah). The SR 900 model incorporated a
design year of 2020. For the 2030 SE Bypass model the SR 900 model
the
CITY’s Concurrency model and will be updated to incorporate
2030 land use and demographic data, based on the
updated concurrency plan
from the CITY along with the 2030 PSRC model. Input data like
model growth rates at external stations will also be updated for the 2030 SE
Bypass model.
19.3.1.2 Land Use Assumptions For
Transportation Modeling
Future year land use assumptions will be developed for the
year 2030. The land use data for 2030 will be provided by the PSRC and the City
of Issaquah (concurrency model). The data is based on regional forecasts of
economic activity and local land use plans, including the East Sammamish
Community Plan and the Issaquah Comprehensive Plan. The CONSULTANT shall
summarize
and update
the land use assumptions based on the 2030 PSRC model along with the CITY’s
updated Concurrency model. The land use assumptions may differ from those used
for the Draft EIS, since those used in the 2030
SE Bypass model will be based on the most current information
available.
19.3.1.3 Model Network
The transportation networks for model year 2030 will be
developed from planned and the programmed improvements to be implemented by
WSDOT, King County, and the City of Issaquah. The CONSULTANT shall review and
revise the 2030
SE Bypass model network as necessary to ensure continued
consistency with adopted Plans.
For year 2030, up to
four
three Model runs (one model run shall include both AM & PM traffic
forecasts) will be performed. Each model run may require further
post-processing of the AM and PM Peak hour forecasts. If necessary,
post-processing will include converting the model traffic forecasts into hourly
volumes for the AM and PM peak hours that can be utilized for corridor and
intersection analysis.
The PM peak hour generated trip
talbestables
from the 2030 SE Bypass model will be transposed and if necessary scaled to represent
AM peak hour demand. Additionally, these hourly volumes will be
balanced for the SE Bypass corridor.
Each model run will contain differing assumptions regarding
programmed and planned roadway projects. One model run may include alternative
land use assumptions as determined by the CITY.
The Model runs include:
·
2030 Model Run 1 - Year 2030 No Action: Included will be
the following projects: North SPAR, South SPAR, Sunset Interchange modification,
and SR 900 widening. with baseline 2030 assumptions for land use
·
2030 Model Run 2 - Year 2030 No-Action w/SR 18: Included
will be the following projects: North SPAR, South SPAR, Sunset Interchange, SR
900 widening, and SR 18 widening (this will require using the King County or
PSRC model rather than the SE Bypass Model)
·
2030 Model Run 3 - Year 2030 Full Build: Included will be
the following projects: NSPAR, SSPAR, Sunset, SR 900, and SE Bypass (with no
widening of SR 18)
19.3.1.4 Prepare Future Alternative
Alignment Travel Demand Forecasts
Based on future land use assumptions supplied by the CITY
and on the definition of the roadway alignment alternatives, year 2030 travel
demand forecasts will be prepared using the traffic model. For the 2030 build
model, the three north alignments (North A, North B, North S) and the new south
alignment alternatives for the SE Bypass may be refined. Additionally, the
southern alignment may be evaluated for channelization and alignment design.
The 2030 SE Bypass model will be created using the TMODEL
software. Available output from TMODEL includes specific roadway volumes,
intersection volumes and select link data for the AM and PM Peak hours. This
information will be extracted from the model for the various 2030 model runs.
For the 2030 build scenario, the traffic information extracted from the 2030
build model will be applied to the various proposed design alignment
alternatives.
19.3.1.5 Modal Share Sensitivity
As part of development of the 2030 SE Bypass Model, the
CONSULTANT shall prepare a summary of the varying travel demand assumptions
(such as ridesharing
and transit mode shares in the peak hour) incorporated into the
2030 SE Bypass Model. Most travel demand assumptions will be based primarily
off of the assumptions made in the CITY’s concurrency model along with the
PSRC’s 2030 model.
Ridesharing and transit
mode share assumptions will be presented in the SEISThe
travel demand assumptions will be presented in the SEIS.
19.3.1.6 Evaluation of Alternatives for
Transportation Element
The alignment alternatives (North and South alignments)
will be evaluated based on transportation criteria related to the following
areas:
·
Arterial operations including service to CITY planned land uses
·
Interchange operations
·
Non-motorized transportation (including trails)
·
Safety
·
Recommendations from the Draft EIS
Results of the transportation evaluation will be documented
in the SEIS.
19.3.1.7 Intersection/Roadway Operations
Intersection/Roadway operational analysis of key
intersections/roadways (as determined by the CONSULTANT and CITY) will be
conducted by the CONSULTANT.
2030 No Action
The CONSULTANT shall perform intersection analysis for up
to twenty-six
four (2624)
intersections as determined by the CITY and CONSULTANT. The AM and PM peak
hours will be analyzed for each intersection; the LOS and intersection delay
will be recorded. The intersections that will be analyzed are:
·
SR 900 & NW Sammamish
·
SR 900 & I-90 WB Ramps
·
SR 900 & EB Ramps
·
SR 900 & Gilman
·
SR 900 & Maple
·
E Sammamish & 56th
·
Issaquah-Fall City & E. Lk Sammamish
·
Front St. & WB Ramps
·
Front St. & EB Ramps
·
Front St & Gilman
·
Front St & Sunset
·
Issaquah-Fall City & Black Nugget Rd
·
Issaquah-Fall City & Issaquah Pine
·NSPAR
& Black Nugget
·
Sunset & WB I-90 Ramps
·
Sunset & EB I-90 Ramps
·Issaquah-Pine
& Klahanie
·
E Sammamish & 43rd
·Issaquah-Fall
City & Klahanie
·
Front Street & Clark
·
Front St & Dogwood – South
·
Front St & Dogwood – North
·
Sunset & Second
·
Front St & Second
·
SR 900 & Newport
·228th
SE & Issaquah Pine Lake Road
·
E. Lake Sammamish & Black Nugget
·
Second Avenue SE & Bush Street
2030 Build-Intersection Analysis
For the 2030 Build scenario, a preliminary operational
analysis will be conducted based on SE Bypass configuration assumptions provided
by the CITY. Based on the results of this preliminary operational analyses,
additional operational analyses will be performed as needed to evaluate
alternative SE Bypass configurations (e.g., shorter or longer turning pockets,
more or fewer lanes, etc.), in order to determine the preferred SE Bypass design
alternative.
The Synchro software will be utilized in determining
corridor and intersection operations for the various roadway combinations. The
operational analyses will be conducted for the AM and PM peak hours and
intersection LOS along with intersection delay (sec/veh) will be recorded.
A roadway combination will be defined as inclusion of one
north alignment alternative and one south alignment alternative. Up to three
(3) road combinations will be considered (this is contingent upon the assumption
that all three north alignments and the new south alignment are not fatally
flawed at this point). Up to four (4) versions (or iterations) will be
conducted per roadway combination as directed by the CITY. A version (or
iteration) may include:
·
Modifications to the number of lanes assigned at a particular
intersection or corridor
·
Modifications to design lengths (this can be either storage
lengths or distance between intersections)
Once the
preferred design alternative is determined, other local intersection analysis
will be conducted. Please refer to the 2030 No Action section (above)
for a list of the twenty-six
four intersections to be analyzed.
19.3.1.8 Mitigating Measures
Qualitative
analyses will be performed by the CONSULTANT to identify and discuss the
potential effectiveness of measures designed to mitigate any significant adverse
impacts of each of the alternatives.
19.3.1.9 Draft Transportation Study
The CONSULTANT shall prepare a Draft Transportation Study to document the
results of the new traffic modeling and analysis. Up to 20
copies
of the draft study will be provided for review and
comments.
19.3.1.10 Final Transportation Study
Following review of the draft Transportation Study, the CONSULTANT shall revise
the draft
Transportation
Study to incorporate review comments. Up to 10 copies of the Final Transportation
Study will be provided.
PRODUCTS
·
Approximately 20 copies of the Draft Transportation Study will
be provided for review by the City and other agencies.
·
Following review, approximately 10 copies of the Final
Transportation Study will be provided.
19.3.2 Preliminary Design
The
CONSULTANT shall provide analysis and design drawings for a new alternative to
be analyzed in the SEIS. This alternative will include a new design of the
southern alignment and potential modifications to northern alignments evaluated
in the Draft EIS.
The CONSULTANT shall revise the chanellization plan
features of the current north and south alignments to reflect the traffic needs
as required by the Transportation Study for the year 2030. The CONSULTANT will
then use this revised roadway template, including stormwater facilities, to
develop new cross sections and revised slope lines to further determine their
impact with respect to wetlands, streams, existing property boundaries and
structures. The CONSULTANT shall develop up to three (3) Typical Sections to
further clarify the roadway prism at selected locations throughout the project
length.
Based on the results of this effort and the corresponding
impacts, the CONSULTANT shall revise the horizontal and vertical alignments in
an effort to mitigate unfavorable impacts to wetlands, streams, existing
properties and structures. With each horizontal revision, the CONSULTANT shall
revise the channelization plan features throughout the length of the horizontal
shift. With each vertical alignment revision, the CONSULTANT shall rerun cross
sections throughout the length of the vertical alignment revision and revise
slope lines to further determine their impact with respect to wetlands, streams,
existing properties and structures. The CONSULTANT shall make any revisions to
the Typical Sections that may result from the shifts in horizontal and vertical
alignments.
Consideration will be given to a diverging, separated pedestrian trail, along
the south roadway alignment, that would better serve the adjacent high school.
If this is determined desirable, one (1) separate horizontal alignment and
vertical profile will be developed for the pedestrian trail. The separated
trail alignment will be modeled to determine cut and fill limits and their
location with respect to wetlands, streams, existing properties and
structures.
The CONSULTANT
shall develop up to two (2) new alternative designs for the south alignment that
shall reflect a roadway footprint (conceptual channelization) that will be based
on the Traffic Study for the year 2030. Each alternative design shall consist
of a horizontal alignment and a vertical profile. A roadway template will be
developed to determine cut and fill limits and their location with respect to
wetlands, streams and existing property boundaries and structures. Up to three
(3) typical sections per alternative shall be developed to further evaluate the
impacts on the adjacent topography. Consideration will be given to a diverging,
separated pedestrian trail, at the south roadway alignment, that would better
serve the adjacent high school. If this is determined desirable, one (1)
separate horizontal alignment and vertical profile will be developed for the
pedestrian trail. The separated trail alignment will be modeled to determine
cut and fill limits and their location with respect to adjacent wetlands.
PRODUCTS
·
Up to three (3) alignment drawings identifying the proposed
project design for the northern and southern alignments will be provided.
·
Up to (2) two vertical profiles of the proposed project design
will be provided.
19.3.3 Section 4(f) Issues
The CONSULTANT shall
investigate Section 4(f) resource issues and how they might affect decisions
regarding the project’s northern alignments. The necessity of identifying the
Issaquah High School facilities as Section 4(f) resources will be explored. The
Department of Natural Resources will be contacted regarding potential impacts on
Tiger Mountain NRCA property. Further coordination with the Office of
Archaeology and Historic Preservation will be pursued regarding the need to
confirm determinations of effect on the Sportsman Clubhouse. Potential
balancing of impacts on historic properties with impacts on school facilities
under Section 4(f) [if it is agreed to consider high school property under
Section 4(f)] will be evaluated.
19.3.4 Additional Wetlands and Streams Study
The
CONSULTANT shall provide additional study of wetlands and streams in the project
area to determine impacts on these resources from the new alignment design
resulting from the updated 2030 traffic model. This work will involve
additional wetland and stream reconnaissance of the North Tributary stream in
the vicinity of Front Street, south of 2nd Avenue. It will also involve review
of potential impacts to Wetland HS and Wetland GW (identified in the Draft EIS)
associated with the new alternative.
The
results of this task will be documented in a Wetlands Technical Memorandum. A
draft technical memorandum will be submitted for review and comment. A final
technical memorandum will be prepared incorporating comments on the draft.
PRODUCTS
·
Approximately 20 copies of the Wetlands technical memorandum will be provided
for review and comments.
·
Approximately 10 copies of the Final Wetlands Technical Memorandum will be
provided.
19.3.5 Drainage Design Review
The
CONSULTANT shall review the conceptual drainage design of the new southern
alignment in relation to the new 2030 model results to assure that adequate
consideration of drainage requirements is provided. A review of the conceptual
drainage design for the three northern alignments will be done to confirm that
the current changes have not altered the previous design. Preliminary
calculations of runoff volumes and flow rates to support preliminary sizing of
the stormwater control ponds needed to serve the updated roadway design will be
prepared. These calculations will be prepared for each of the northern
alignment alternatives as well as the new southern alignment alternative. The
CONSULTANT will also evaluate the approximate sizes and locations of runoff
conveyance systems that would be needed to deliver roadway runoff to the
stormwater ponds. Hard copy markups of preliminary conveyance system alignments
to will be prepared for transfer onto the project base maps.
The
results of this task will be documented in a Drainage Design Technical
Memorandum. A draft technical memorandum will be submitted for review and
comment. A final technical memorandum will be prepared incorporating comments
on the draft.
PRODUCTS
·
Approximately 20 copies of the Drainage Technical Memorandum will be provided
for review and comments.
·
Approximately 10 copies of the Final Drainage Technical Memorandum will be
provided.
19.3.6 Merger Process Coordination
The CONSULTANT shall coordinate with regulatory agencies to
gain concurrence on the alternatives to be evaluated in the Supplemental EIS.
Additional studies to gain concurrence, or development and analysis of
additional alternatives will be considered “extra work.” Preparation of the
preliminary draft SEIS cannot proceed without issuance of a letter of
concurrence from the cooperating agencies.
Change Order #9
Preliminary
Phase 2 Work Plan
Southeast Issaquah Bypass
Supplemental Environmental
Impact Statement
and Preliminary
Engineering Design
Change Order No. 9
October 22, 2001
INTRODUCTION
AND ASSUMPTIONS
This work plan describes
Phase 2 activities for the Southeast Issaquah Bypass project. Phase 2
activities described continue and build on the work completed during Phase 1
(Change Order No. 8). Phase 2 will involve the following tasks:
·
Analyzing the preferred recommended alternative for the opening
year 2005. Additionally, the year 2005 No Action and existing year 2000
conditions will also be analyzed. Included will be updated traffic modeling
data, new analyses of traffic operations based on new model data, and analysis
of the recommended preferred alternative.
·
Preparation of a Supplemental Draft and Final Environmental Impact
Statement including revisions to the Section 4(f) Evaluation, Biological
Assessment, and Section 106 documentation prepared for the June 2000 Draft EIS
·
Preparation of Initial and Detailed Wetland Mitigation Plans
including draft and final Section 404 Permit Applications
·
Additional coordination with agencies under the 404 Merger Process
·
Participation in a public hearing on the Supplemental Draft EIS,
and
·
Assisting the City in obtaining a Record of Decision.
20.1.1.
Project Management Plan
The
CONSULTANT shall update the
project management plan to incorporate any staffing changes, changes in
deliverables of other updates required by the Phase 2 work plan. A new project
schedule will also be prepared.
20.1.2.
Monthly Billings and Progress Reports
The
CONSULTANT shall prepare monthly
progress reports describing the status of the PROJECT. These reports will:
·
Highlight
significant accomplishments
·
Target
potential problem areas needing special attention or coordination
·
Compare actual
work progress with contractual obligations on a design task basis
The
progress reports will be presented in a task oriented format and will include
updated scheduling reports, indicating all progress to date and resources
expended. This update will include any changes in schedule, sequence, or
resource loading. If any schedule slippage has occurred, a plan for bringing
the work back on schedule and budget will be included.
Progress reports and billings will be prepared by the CONSULTANT and submitted
on a monthly basis. These items will be supported by detailed record keeping
sufficient to closely track the PROJECT budget and expenditures and support the
billings.
PRODUCTS
-
Monthly Progress
Reports, incorporating Project Schedule revisions as appropriate, and
Monthly Billings. Approximately 12 progress reports and billings will be
provided.
20.1.3.
Direction, Meetings, and Coordination
This task includes the
following project management items:
1.3.120.1.3.1.
Team Coordination/General Direction
This
task includes internal staff meetings and discussions to direct efforts and
facilitate completion of project tasks.
1.3.220.1.3.2.
Meetings with City Staff
Regularly scheduled meetings (two per month) will be held with Issaquah staff to
review progress and discuss upcoming actions. This task would also include
additional meetings with City staff members as needed to obtain information or
resolve project issues. The CONSULTANT shall prepare meeting minutes to
summarize issues discussed.
1.3.420.1.3.3.
Meetings/Coordination with Others
This
task would provide for meetings and coordination with outside agencies to
provide information or discuss project issues. The CONSULTANT shall prepare
meeting minutes to summarize issues discussed with participating agencies.
PRODUCTS
Meeting notes documenting
topics discussed and future action items will be prepared and distributed as
appropriate.
20.2.
QUALITY
CONTROL
20.2.1.
Quality Assurance
The work products will be
reviewed by consultant team staff with expertise in the appropriate discipline
areas. This will be an ongoing activity during the duration of the project with
emphasis on major deliverable work products.
20.3.
Transportation and alternatives review
20.3.1.
Transportation Study
Traffic Conditions and Analysis
Phase 2 will include those
tasks necessary to analyze the recommended alternative (based off of the year
2030 analysis as described in Phase 1) for the opening year 2005. Additionally,
the year 2005 No Action and existing year 2000 conditions will be analyzed.
Included will be updated traffic modeling data, new analyses of traffic
operations based on new model data, and analysis of the recommended alternative.
Methodology
This section presents the
methodology and assumptions used to guide the transportation analysis. The
methodology and assumptions used in this analysis are consistent with those
applied in the SR 900 Widening Project. Additionally, the TMODEL software will
be used.
20.3.1.1.
Traffic Model Refinement
The
traffic model used in the SE Issaquah Draft EIS (June 2000) shall be replaced
with the traffic model described below.
Year 2000 Existing Conditions
The 2000 existing
conditions SE Bypass model will be based off of the CITY’s Travel Model used for
Concurrency Testing. The CITY’s Travel Model assumes a 1999 land use and year
2000 traffic data. The CITY’s Travel Model will be utilized as the Year 2000 SE
Bypass Model.
Opening Year 2005
A future year 2005 traffic
model, which will include a highway network of all freeways, freeway
interchanges, arterials and other streets in the study area will be developed
for use in subsequent tasks for the SE Bypass SEIS. The 2005 SE Bypass model
will be developed using the CITY’s Year 2000 Travel Model (used for Concurrency
Testing) along with the 2005 SR 900 Widening Model’s land use assumptions. The
SR 900 Widening land use assumptions may be adjusted; the CONSULTANT shall
notify the CITY if adjustments are applied to the 2005 SE Bypass Model. The
King County or PSRC Models may also be referenced and used if applicable.
20.3.1.2.
Land Use Assumptions For Transportation Modeling
Existing Conditions Year 2000
The CONSULTANT will
summarize the land use assumptions based on the CITY’s Year 2000 Travel Model
used for concurrency testing.
Opening Year 2005
Future year land use
assumptions will be based off of the Year 2005 SR 900 Widening Model and may be
modified if necessary. The CONSULTANT will summarize (and update if necessary)
the land use assumptions for the Year 2005 SE Bypass Model. The land use
assumptions may differ from those used for the Draft EIS, since those used in
the 2005 SE Bypass model will be based on the more current information.
20.3.1.3.
Model Network
Existing Conditions Year 2000
For
year 2000, one Model run (one model run shall include both AM & PM traffic
forecasts) will be performed. The PM peak hour generated trip tables from the
2000 SE Bypass model will be transposed and if necessary scaled to represent AM
peak hour demand. Additionally,
these
the hourly volumes will be balanced for the SE Bypass corridor.
The
Model run shall include:
-
2000 Model Run 1 - Year 2000 Existing Conditions:
Year
20001999
assumptions for land use will be incorporated.
Opening Year 2005
The
transportation networks for model year 2005 will be developed from planned and
programmed improvements to be implemented by WSDOT, King County, and the City of
Issaquah.
The
CONSULTANT will review and revise the 2005 SE Bypass model network as necessary
to ensure continued consistency with adopted Plans.
For year 2005, up to two
Model runs (one model run shall include both AM & PM traffic forecasts) will be
performed.
The
PM peak hour generated trip tables from the 2005 SE Bypass model will be
transposed and if necessary scaled to represent AM peak hour demand.
Additionally, these
hourly volumes will be balanced for the SE Bypass corridor.
Each
model run will contain differing assumptions regarding programmed and planned
roadway projects.
The
Model runs include:
-
2005 Model Run 1 - Year 2005 No Action:
Included will be the following projects: North SPAR, South SPAR, Sunset
Interchange modification, and SR 900 widening. Baseline 2005 assumptions for
land use will be incorporated.
-
2005 Model Run 2 - Year 2005 Full Build:
Included will be the following projects: NSPAR, SSPAR, Sunset, SR 900, and SE
Bypass (with no widening of SR 18)
20.3.1.4.
Prepare Future Alternative Alignment Travel Demand Forecasts
Based
on future land use assumptions supplied by the CITY and on the definition of the
roadway alignment alternatives, year 2005 travel demand forecasts will be
prepared using the traffic model. For the 2005 build scenario, the recommended
proposed design alignment (based on the work completed through Phase 1) will be
considered.
Available output from
TMODEL includes specific roadway volumes, intersection volumes and select link
data for the PM Peak hour. The trip tables generated for the PM peak hour will
then be transposed and possibly scaled in order to generate the AM Peak hour
volumes. For the 2005 build scenario, the traffic information extracted from
the 2005 build model will be applied to the recommended proposed design
alignment alternative (as determined in Phase 1).
20.3.1.5.
Modal Share Sensitivity
As part of development of
the 2005 SE Bypass Model (No-Action and Build Scenarios), the CONSULTANT shall
prepare a summary of the various travel demand management assumptions
incorporated into the 2005 SE Bypass Model. Most travel demand management
assumptions will be based primarily off of the assumptions made in the SR 900
Widening model along with the CITY’s Travel Model used for concurrency testing,
and possibly the PSRC model. The travel demand management assumptions will be
presented in the SEIS.
20.3.1.6.
Intersection/Roadway Operations
Intersection/Roadway
operational analysis of key intersections/roadways (as determined by the
CONSULTANT and CITY) will be conducted by the CONSULTANT. The Synchro software
will be utilized in performing the traffic operational analyses. The
operational analyses will be conducted for the AM and PM peak hours and
intersection LOS along with intersection delay (sec/veh) will be recorded.
Year 2000 Existing Conditions and Year 2005 No Action
The
CONSULTANT shall perform intersection analysis for up to twenty-six
four (2624)
intersections as determined by the CITY and CONSULTANT. The AM and PM peak
hours will be analyzed for each intersection; the LOS and intersection delay
will be recorded. The intersections that will be analyzed are (as per agreement
with the CITY
- SR
900 & NW Sammamish
- SR
900 & I-90 WB Ramps
- SR
900 & EB Ramps
- SR
900 & Gilman
- SR
900 & Maple
- E
Sammamish & 56th
-
Issaquah-Fall City & E. Lk Sammamish
-
Front St. & WB Ramps
-
Front St. & EB Ramps
-
Front St & Gilman
-
Front St & Sunset
-
Issaquah-Fall City & Black Nugget Rd
-
Issaquah-Fall City & Issaquah Pine
-
NSPAR & Black Nugget
-
Sunset & WB I-90 Ramps
-
Sunset & EB I-90 Ramps
-
Issaquah-Pine & Klahanie
- E
Sammamish & 43rd
-
Issaquah-Fall City & Klahanie
-
Front Street & Clark
-
Front St & Dogwood – South
-
Front St & Dogwood – North
-
Sunset & Second
-
Front St & Second
-
SR 900 & Newport
-
228th
SE & Issaquah Pine Lake Road
-
E. Lake Sammamish & Black Nugget
-
Second Avenue SE & Bush Street
Year 2005 Build
The recommended proposed
design alternative as determined in Phase 1 will be analyzed for the year 2005.
The recommended proposed roadway combination is defined as inclusion of
recommended north alignment alternative and the recommended south alignment
alternative. Therefore, one roadway combination (the recommended proposed
design alternative) shall be analyzed. Up to four (4) versions (or iterations)
will be conducted in order to determine the recommended roadway combination as
directed by the CITY. A roadway combination version (or iteration) may include:
-
Modifications to the number of lanes assigned at a particular intersection or
corridor
-
Modifications to design lengths (this can be either storage lengths or
distance between intersections)
The
Synchro software will be utilized in determining corridor and intersection
operations for the year 2005 build roadway combination as well as the twenty-six
four (2624)
intersections as listed in the “Year 2000 Existing Conditions and Year
2005 No Action” section (above). Additionally, the year 2000 Existing
Conditions and the year 2005 No Action intersections as described above will
also be analyzed using the Synchro software.
20.3.1.7.
Mitigating Measures
Qualitative analyses will
be performed by the CONSULTANT to identify and discuss the potential
effectiveness of measures designed to mitigate any significant adverse impacts
of each of the alternatives.
20.4.
SUPPLEMENTAL DRAFT EIS
The
CONSULTANT shall prepare a Supplemental Draft EIS (SDEIS) to present new
information on proposed project alternatives and traffic analysis based on the
outcome of the Phase I work plan. The SDEIS will follow a format consistent
with guidance in the revised WSDOT Environmental Procedures Manual (July
2001), guidance in the “Interagency Working Agreement to Integrate Special
Aquatic Resources (404) Permit Requirements into the NEPA and SEPA processes in
the State of Washington,” (NEPA/SEPA/404 Merger Agreement), and FHWA
Technical Advisory T6640.8A. The CITY will provide close coordination with
WSDOT and FHWA throughout the process. The document will be in compliance with
NEPA and SEPA.
The
SDEIS is anticipated to include the following sections and appendices (however,
the final EIS format may change in response to the CITY’s needs):
20.4.1.
Introductory Material
The following sections of
the June 2000 Draft EIS will be revised, as appropriate:
-
Cover Sheet
-
Title Sheet
-
Fact Sheet
-
Table of
Contents
-
List of Tables
-
List of
Figures
20.4.2.
Summary
The Summary section from the
June 2000 Draft EIS will be revised to include a brief description of the
proposed action, other governmental agency’s actions in the geographic area, a
summary of alternatives and options considered, summary of major environmental
impacts (in table format with proposed mitigation measures), areas of concern or
controversy, unresolved issues, list of required permits, and a list of other
actions required for the proposed PROJECT.
20.4.3.
Chapter 1: Purpose of and Need for the Action
This chapter will be revised
to identify and describe the proposed action and the transportation problems or
other needs which it is intended to address. This discussion will clearly
demonstrate that a need exists for the PROJECT and describe the problems which
it is to correct.
20.4.4.
Chapter 2: Alternatives
This chapter will be revised
to describe the process used to identify various alternatives, the range of
alternatives considered, and the alternatives that were eliminated from further
consideration. Chapter 2 will include the NEPA 404 Alternatives Analysis and
Aquatic Resource Avoidance Analysis consistent with the requirements of the NEPA/SEPA/404
Merger Agreement. The analysis will describe alternatives considered but
rejected (and reason why) including efforts to minimize or avoid impacts to
aquatic resources, and will identify a preferred alternative, if known. A table
will be included comparing the various impacts of each alternative.
Alternatives to be
considered in the SDEIS include:
- No
Action (no-build) Alternative
·
Alternative 1: North A with a new south alignment
·
Alternative 2: North B with a new south alignment
·
Alternative 3: North S with a new south alignment
A detailed description of
the alternatives selected for analysis in the Supplemental Draft EIS will be
provided, together with updated information on estimated project costs and
construction timing. The description of the alternative design concepts will be
in sufficient detail to allow identification of the specific characteristics of
each design concept to be evaluated. These characteristics include roadway
layout, intersection configurations, structural features, and other roadway
related facilities. Maps, alignment drawings, road sections, cost estimates, a
proposed construction schedule with milestones, and other exhibits will be used
to describe and allow a comparison between the alternatives.
20.4.5.
Chapter 3: Affected Environment
This chapter will be revised
to update the description of the existing social and environmental setting for
the area affected by the alternatives presented in the SDEIS. The following
elements of the environment will be reviewed and updated as necessary: study
area, local geography, geology and soils, hydrologic systems and floodplains,
wetlands, fish and wildlife habitat, land use, regional and community growth,
historic and archaeological elements, hazardous waste, and visual quality. It
will also discuss the adopted land use and transportation plans as they relate
to the proposed PROJECT, including the City’s Traffic Concurrency Ordinance.
These discussions will be limited to data, information, issues, and values that
will have a bearing on possible impacts, mitigation measures, and on the
selection of an alternative.
3.2.320.4.6.
Chapter 4: Environmental Consequences
This chapter will be revised
to document the direct project impacts, future operational impacts, secondary
and cumulative impacts, construction activity impacts and mitigation measures
associated with each of the three new build alternatives and the no-action
alternative. The text will include a description of any major assumptions made
and supporting information on the validity of the environmental assessment
methodology used. If details beyond those included in the Affected
Environment chapter are necessary to clarify the impacts, they will be
addressed in this chapter. For each element of the environment each alternative
will be analyzed separately.
Direct project impacts
are those impacts associated with the footprint or right-of-way of each
alternative.
Future operational impacts
are those impacts resulting from ongoing operation of the project that are
anticipated to occur between the year of opening (2005) and the design year
(2030).
Secondary impacts
are those that are “caused by an action and are later in time or farther removed
in distance but are still reasonably foreseeable” (40 CFR 1508.8). These
impacts, which usually result from the initial action, include changes in land
use, water quality, economic vitality, and population density.
Cumulative impacts
are those that “result from the incremental consequences of an action when added
to other past and reasonable foreseeable future actions” (40 CFR 1508.7). The
cumulative effects of an action may be undetectable when viewed in the
individual context of direct and even secondary impacts but can nonetheless add
to other disturbances and eventually lead to a measurable environmental change.
Construction activity impacts
are limited to construction process impacts that are temporary in nature and
typically limited to the immediate project area (e.g., construction noise, dust,
traffic controls, etc.).
20.4.7.
Chapter 5: Comments and Coordination
The CONSULTANT
shall update this chapter to summarize the results of additional coordination
with federal, state, and local agencies, their level of involvement, and any
unresolved issues or areas of conflict. This section will also summarize
additional public involvement for the SDEIS.
20.4.8.
Chapter 6: Section 4(f) Evaluation
The CONSULTANT shall update
and revise the Section 4(f) evaluation to reflect the impacts (both during
construction and operation) associated with the new build alternatives. The
CONSULTANT shall identify and evaluate location and design alternatives which
would avoid each and all Section 4(f) properties; explain whether any avoidance
alternatives which were eliminated from further study are “feasible and prudent”
and if not, explain why; discuss all possible measures which are available to
minimize impacts on Section 4(f) properties, including commitments made and
monitoring procedures to minimize harm.
20.4.9.
Response to Comments on Draft EIS
The CONSULTANT shall review
and prepare responses to over 1000 comments received on the Draft EIS in letters
and recorded testimony at the DEIS public hearing. It is assumed that many of
the comments received are similar in content and a response to one will be
appropriate for many others. It is also assumed that many of the comments will
no longer be relevant because several of the alternatives presented in the Draft
EIS are no longer being considered. Copies of the comment letters and recorded
public testimony, along with the responses to those comments, will be presented
in an appendix to the SDEIS.
20.4.10.
Closing Sections/Appendices
The CONSULTANT shall prepare
closing documentation for the SEIS, including the following information:
·
Principal
Contributors
·
Studies
Performed
·
SDEIS
Distribution List
·
Transportation
Studies
·
Supplemental
Alternatives Analysis
·
Historic Site
Documentation
20.4.11.
Prepare Preliminary Supplemental Draft EIS
The CONSULTANT shall
produce a preliminary SDEIS and submit 10 copies to the CITY for review and
comment. The CONSULTANT will revise the document and provide 10 copies of the
preliminary SDEIS (including the revised Wetland and Streams Technical
Memorandum and Biological Assessment) to the CITY for distribution to the USACOE,
USFWS, EPA, NMFS, Ecology and WDFW.
PRODUCTS
-
Preliminary SDEIS for
CITY review (10 copies)
·
Preliminary
SDEIS for review by cooperating agencies (10 copies)
20.4.12.
Revise Supplemental Draft EIS
The CITY will provide one
set of consolidated comments on the Preliminary SDEIS to the CONSULTANT. It is
assumed that cooperating agencies will submit comments separately. The
CONSULTANT shall make requested revisions and prepare a camera-ready SDEIS for
review by the CITY. The SDEIS will include an initial wetland mitigation plan
if a preferred alternative is known, otherwise a conceptual mitigation plan will
be included in the SDEIS.
PRODUCTS
One camera-ready copy of the SDEIS for final CITY approval
20.4.13.
Publish Supplemental Draft EIS
Upon approval of the
camera-ready SDEIS by the CITY, the CONSULTANT shall reproduce 200 copies of the
final SDEIS for distribution. The CITY will provide the distribution list and
be responsible for distributing the document to the agencies and the public.
PRODUCTS
200 copies of the SDEIS for distribution
20.5.
SUPPLEMENTAL DRAFT EIS/SECTION 404 PUBLIC HEARING
A public hearing will be
conducted following publication of the SDEIS. The CONSULTANT shall prepare
materials for the hearing and provide originals to the CITY for reproduction and
distribution. Relevant activities will include:
·
Preparing
hearing packet
·
Preparing
exhibits and handouts
·
Coordinating/attending the Public Hearing
It is
assumed that up to four (4) CONSULTANT staff will attend the public hearing. It
is also assumed that the CITY will be responsible for preparing the public
notice for the joint SDEIS/404 Public Hearing Notice.
20.6.
SECTION 106 PROCESS
If the Section
106 process is triggered, aThe
Section 106 documentation prepared for the June 2000 Draft EIS will be
prepared
revised
to describe the impacts of the new alternatives on historic and
cultural resources identified within the project area. The CONSULTANT, in
consultation with the Office of Archaeology and Historic Preservation (OAHP)
shall review, and revise if necessary, the Determination of Effect documentation
included in Appendix F of the DEIS. If there is an adverse effect, or if the
Advisory Council on Historic Preservation objects to a determination of no
adverse effect, the CONSULTANT and the CITY will confer with WSDOT, FHWA, OAHP,
and the Council to find ways to reduce/minimize adverse effects. Consultation
will result in a Memorandum of Agreement (MOA) that outlines measures the CITY
can take to reduce, avoid or mitigate the adverse effect. This task will be
closely coordinated with the Section 4(f) evaluation described previously.
The CONSULTANT
shall prepare the Section 106 report following agency guidelines and will assist
in coordinating review and approval by historic preservation agencies.
PRODUCTS
·
Draft Revised Cultural Resources Technical Memorandum
·
Final Revised Cultural Resources Technical Memorandum
·
Draft Memorandum of Agreement
·
Final Memorandum of Agreement
20.7.
BIOLOGICAL ASSESSMENT
The CONSULTANT shall review
and revise the Biological Assessment (BA) prepared for the June 2000 Draft EIS.
The BA will be revised
prepared
to describe the impacts of the new alternatives on federally
listed, proposed, and candidate species and designated and proposed critical
habitat present in the project vicinity. The CONSULTANT will submit 10 copies
of the Revised Draft BA to the CITY for review and comment. The CONSULTANT will
revise the document and provide 10 copies of the Revised Draft BA for
distribution with the Preliminary SDEIS to the USACOE, USFWS, EPA, NMFS, Ecology
and WDFW. Special effort will be made during this task to follow the guidance
in the July 2001 WSDOT Environmental Procedures Manual.
PRODUCTS
·
Revised Draft BA for CITY review (10 copies)
·
Revised
Draft BA for review by cooperating agencies (10 copies)
20.8.
Final Environmental Impact Statement
20.8.1.
Respond to Comments on the Supplemental DEIS
The
CITY will provide the CONSULTANT with copies of the letters received with
comments on the SDEIS. The CITY will also provide the CONSULTANT with a copy of
the transcript recording public testimony received at the public hearing.
Revisions to the Supplemental DEIS will be based on the comment letters, public
hearing testimony and agency comments received during the review period.
The CONSULTANT shall
compile a summary of comments received on the SDEIS, provide responses to
comments, and make recommendations, if necessary, on the need for additional
studies, additional mitigation or changes to the design. For budgeting
purposes, it is assumed that there will be a maximum of 100 comment letters with
10 comments each for a total of 1,000 comments. If there are more than 100
comment letters or 1,000 comments, this extra level of effort will be considered
“extra work.”
20.8.2.
Revise
Environmental Analysis
of Discipline
Issues
The
consultants
CONSULTANTS shall revise the discussion of
the
variousany
elements
of the EIS,
if necessary
,
to reflect changes in the project design, impacts, and proposed or required
mitigation that have occurred since publication of the SDEIS,
or in response to review comments on the SDEIS.
Any proposed additional studies, detailed analyses, or changes in design would
be considered “extra work.”
20.8.3.
Prepare Preliminary Final EIS Document
The CONSULTANT shall
prepare a preliminary Final EIS and submit 10 copies to the CITY for review and
comment. The CONSULTANT will revise the document and provide copies of the
preliminary Final EIS (including the final alternatives analysis, identification
of the preferred alternative and apparent least environmentally damaging
practicable alternative, and apparent final wetland mitigation plan) to the
USACOE, USFWS, EPA, NMFS, Ecology and WDFW. The Final EIS will incorporate
changes that reflect changes in the PROJECT scope, impacts, technical analysis
and mitigation analysis that have occurred since the SDEIS. The Final EIS will
include comments received on the SDEIS, a summary of the comments, responses to
comments, and an updated fact sheet.
PRODUCTS
-
Preliminary Final EIS
for CITY review (10 copies)
·
Preliminary
Final EIS for review by cooperating agencies (10 copies)
20.8.4.
Final EIS Production
The
CITY will provide consolidated comments on the preliminary Final EIS to the
CONSULTANT. It is assumed that cooperating agencies will submit comments
separately. The CONSULTANT shall revise the preliminary Final EIS in response
to the comments received from the CITY and cooperating agencies and prepare a
final detailed wetland mitigation plan. The CONSULTANT will prepare a camera
ready Final EIS and the CITY will conduct a second review to check and approve
the changes and authorize reproduction and issuance of the Final EIS.
The CONSULTANT shall make
the second, minor revisions based on the review and reproduce 200 copies of the
Final EIS for distribution. The CITY will provide the distribution list for the
FEIS and will be responsible for distributing the document to the public and
agencies.
PRODUCTS
·
Camera Ready Final EIS (1 camera ready copy)
·
Final EIS (200 copies)
20.8.5.
Record of Decision
The CONSULTANT shall assist
the CITY in preparing the draft NEPA Record of Decision (ROD) and shall address
any Final EIS comments received.
PRODUCTS
-
Draft Record of Decision
-
Final Record of Decision
20.9.
NEPA/SEPA/404 MERGER ACTIVITIES
The CONSULTANT shall
provide project coordination to comply with the “Interagency Working Agreement
to Integrate Special Aquatic Resources (404) Permit Requirements into the NEPA
and SEPA processes in the State of Washington,” (NEPA/SEPA/404 Merger
Agreement).
20.9.1.
NEPA/SEPA/404 Merger Concurrence
The CONSULTANT shall
coordinate with regulatory agencies to gain concurrence on the preliminary SDEIS
regarding project alternatives to be evaluated in the SDEIS, preliminary
preferred alternative, and initial and detailed wetland mitigation plans.
Additional studies required to obtain concurrence, or development and analysis
of additional alternatives, will be considered “extra work.” Preparation of the
final version of the SDEIS cannot proceed without issuance of a letter of
concurrence from the cooperating agencies.
The CONSULTANT shall
coordinate and meet with regulatory agencies to gain concurrence on the
preliminary Final EIS regarding the apparent final mitigation plan and the
preferred alternative/least environmentally damaging alternative, as specified
in the NEPA/SEPA/404 Merger Agreement. Additional studies or revisions to
alternatives that may be needed to obtain concurrence will be considered “extra
work.” Publication of the Final EIS
(Task 9.4)
cannot occur without issuance of a letter of concurrence from the
cooperating agencies.
20.9.2.
Initial Mitigation Plan for Preferred Alternative
Upon issuance of the Agency
Concurrence Letter regarding alternatives to be evaluated in the SDEIS and
identification of the preferred alternative, the CONSULTANT shall conduct a
preliminary investigation of candidate mitigation sites to determine if there
are suitable sites to support the required mitigation. Upon identification of
candidate sites, the CONSULTANT shall prepare a draft Initial Mitigation Plan
for the preferred alternative, as described in Appendix F of the NEPA/SEPA/404
Merger Agreement. The draft Plan will identify unavoidable impacts to aquatic
resources; establish the goals and objectives of the mitigation; the timing of
the mitigation; a general description of the candidate sites; and proposed
monitoring of the mitigation. No drawings will be included in the Plan. The
draft Plan will be submitted to the CITY for review and comment.
The draft Initial
Mitigation Plan will be revised to address the CITY’s comments. The revised
Plan will be submitted to the CITY for distribution to other merger agencies for
review and comment. The CITY will provide consolidated comments on the Plan to
the CONSULTANT. The CONSULTANT shall conduct a site visit with the USACOE to
review candidate sites. The CONSULTANT shall prepare a final Initial Mitigation
Plan for inclusion in the Draft SEIS.
PRODUCTS
·
Draft
Initial Wetlands Mitigation Plan and Report for CITY review (10 copies)
·
Draft
Initial Wetlands Mitigation Plan and Report for cooperating agency review (10
copies)
·
Final Initial Wetlands Mitigation Plan and Report for inclusion
in the SDEIS (one camera ready copy)
20.9.3.
Section 404 Permit Application Preparation
Prior to submittal of the
Preliminary SDEIS, the CONSULTANT shall attend one pre-application meeting with
the USACOE to identify issues of concern and confirm Section 404 permitting
requirements and scheduling. The CONSULTANT shall then prepare draft Section
404 permit application materials for submittal to the CITY. The CITY will
process the permit to the USACOE. Prior to publication of the Final EIS, the
CONSULTANT shall prepare a final Section 404 permit application for submittal to
the permitting agencies. The final application will include a detailed
Mitigation Plan and Report
(Section 10.7 of this Scope of Work).
PRODUCTS
·
Draft Section 404 Wetland Permit Application
·
Final Section 404 Wetland Permit Application
20.9.4.
Detailed Mitigation Plan and Report
Prior
to publication of the Final EIS, the CONSULTANT shall prepare a draft Detailed
Mitigation Plan and Report for the preferred alternative, as described in
Appendix F of the NEPA/SEPA/404 Merger Agreement. The draft Plan will include a
summary of wetland impacts, description of proposed mitigation and mitigation
site(s), mitigation design (hydrology source, grading plan, soil preparation,
planting plan, and schedule), standards of success, and monitoring and
contingency plans. The draft Plan will be submitted to the CITY for review and
comment. The draft Plan will be revised to address the CITY’s comments. The
revised Plan will be submitted to the CITY for distribution to the merger
agencies with the preliminary Final EIS.
Upon issuance of
concurrence on the preliminary Final EIS by the cooperating agencies, the
CONSULTANT shall prepare a final Detailed Mitigation Plan for inclusion in the
Final EIS. A Final Mitigation Plan as required by the NEPA/SEPA/404 Merger
Agreement is not included in this Work Plan and will be considered “extra work”.
PRODUCTS
·
Draft
Detailed Wetland Mitigation Plan and Report for CITY review (10 copies)
·
Draft
Detailed Wetland Mitigation Plan for cooperating agency review (10 copies)
·
Final Detailed Wetland Mitigation Plan for inclusion in the
SDEIS (one camera ready copy)
Change Order #10
Phase 2 Work Plan
Southeast Issaquah Bypass
Supplemental Environmental Impact Statement
and Conceptual Engineering Design
Change Order No. 10
April 19, 2002
INTRODUCTION AND ASSUMPTIONS
This work plan describes Phase 2
activities for the Southeast Issaquah Bypass project. Phase 2 activities
described herein build on and continue the work initiated during Phase 1 (Change
Orders No. 8 and 9). During Phase 2, the following tasks shall be performed:
• Conduct
traffic analysis for the opening year 2005 AM and PM peak hours. Opening year
analysis shall include the proposed Build alternative as well as the No Action
alternative. Existing year 2000 conditions for AM and PM Peak hours shall also
be analyzed. Included shall be updated traffic modeling data for both opening
year 2005 and existing year 2000.
• Prepare
additional ground level and oblique view photo images of the proposed build
alternatives.
• Prepare a
Supplemental Draft and Final Environmental Impact Statement; including revisions
to the Section 4(f) Evaluation, Biological Assessment, and Section 106
documentation prepared for the June 2000 Draft EIS.
• Respond to
approximately 1,000 public and agency comments received on the June 2000 Draft
EIS.
• Prepare
Initial and Detailed Wetland Mitigation Plans (including draft and final USACE
Section 404 permit applications).
• Coordinate
with the USACE, EPA, USFWS, NMFS, WDFW and Ecology as part of the Section 404
Merger Process.
• Participate
in a Public Hearing on the Supplemental Draft EIS.
• Assist the
City of Issaquah in obtaining a Record of Decision from FHWA.
• Collect
additional field survey with sufficient detail to update the existing mapping to
conceptual design level accuracy within the study alignment corridor.
• Conduct
geotechnical investigations to support the conceptual design task.
• Complete
Phase 1 conceptual design
• Prepare
construction sequencing plans
• Prepare
conceptual cost estimates
Items to be provided to the
CONSULTANT by the CITY
The CITY will furnish to the
CONSULTANT copies of documents that are available to the CITY that will
facilitate the preparation of the plans and studies within the limits of the
project. These include:
• Aerial
mapping in hard copy and digital (AutoCAD) format
• A list of
utilities and other agencies having jurisdiction in the project area
• Rights of
Entry to affected properties as requested by the CONSULTANT (except as otherwise
noted in this workplan)
• "As Built"
plans, as available
• Assessor's
maps (in digital and hard copy format)
• Timely
review of all CONSULTANT submittals and collation of all review comments into a
single document for submission to the CONSULTANT at one time
• Existing
right-of-way and parcel information in AutoCAD format
• Updated
floodplain mapping and background data for Issaquah Creek (Montgomery, 2001).
20.1.
PROJECT MANAGEMENT
20.1.1. Project
Management Plan
The CONSULTANT shall update the project management plan to incorporate any
staffing changes, changes in deliverables or other updates required by the Phase
2 work plan. The project schedule shall be updated on an as needed basis.
20.1.2. Monthly Billings
and Progress Reports
The CONSULTANT shall prepare monthly progress reports describing the status of
the project. These reports shall:
• Highlight significant accomplishments
• Target potential problem areas needing
special attention or coordination
• Compare actual work progress with
contractual obligations on a task by task basis
Progress reports and billings shall be prepared by the CONSULTANT and submitted
on a monthly basis. These items shall be supported by detailed record keeping
sufficient to closely track the project budget and expenditures and support the
billings.
PRODUCTS
Monthly Progress Reports, incorporating Project Schedule revisions as
appropriate, and Monthly Billings. Approximately 16 progress reports and
billings shall be provided.
20.1.3. Direction,
Meetings, and Coordination
This task includes the following project management items:
20.1.3.1. Team
Coordination/General Direction
This task assumes regularly scheduled internal staff meetings (two per month) to
direct team efforts and facilitate completion of project tasks identified in the
Phase 2 work plan. This task also includes project administrator coordination
with subconsultants and one team coordination meeting with subconsultant staff.
20.1.3.2.
Meetings with City Staff
Regularly scheduled meetings (two per month) shall be held with Issaquah staff
to review progress and discuss upcoming actions. The CONSULTANT shall update the
project schedule (one time each month) prior to one of the regularly scheduled
meeting with CITY staff. Additional meetings with CITY staff assumed under this
task includes: one (1) working session with the Public Works Director and the
Mayor's team; one (1) working session with the City Council; and one (1)
additional meeting with the Public
Works Director to review work plan
and schedule. The CONSULTANT shall prepare meeting minutes to summarize issues
discussed.
PRODUCTS
Meeting notes
documenting topics discussed and future action items shall be prepared and
distributed.
20.1.3.3. Meetings/Coordination with
Others
This task would provide for
meetings and coordination with regulatory agencies (outside of the Section 404
Merger activities described in Task 20.4) to provide information or discuss
project issues. Up to five 3-hour meetings, attended by up to three (3)
CONSULTANT staff is assumed for this task. The CONSULTANT shall prepare meeting
minutes to summarize issues discussed.
PRODUCTS
Meeting notes
documenting topics discussed and future action items shall be prepared and
distributed.
20.1.3.4. Coordination with Public
Involvement Consultant
This task provides for support on
public involvement efforts led by others and includes assistance in preparing
public display boards, newsletter information, and graphics for public
presentations or public outreach activities.
20.1.3.5. Phase 2 Work Plan Development
This task provides for team
coordination to assess the results of Phase 1 activities and to develop a
detailed Phase 2 work plan for CITY approval. Substantial coordination between
CONSULTANT and SUBCONSULTANT team members is anticipated.
PRODUCTS
•
Draft Phase 2 Work Plan and Budget
•
Final Phase 2 Work Plan and Budget
20.2.
QUALITY CONTROL
20.2.1. Quality
Assurance
Project deliverables shall be
reviewed by CONSULTANT team staff with expertise in the appropriate discipline
areas. This task includes CONSULTANT team effort to review work products
prepared by SUBCONSULTANTS. This shall be an ongoing activity during the
duration of the project.
20.3.
SUPPLEMENTAL EIS
20.3.1. Transportation
Study
Traffic Conditions and Analysis
Phase 2 work performed
by the CONSULTANT shall include those tasks necessary to analyze both the
proposed Build alternative (based off of the year 2030 analysis as described in
Phase 1) for the opening year 2005 for both the AM and PM peak hours.
Additionally, the year 2005 No Action and existing year 2000 conditions shall be
analyzed. Updated traffic modeling data, traffic analysis based on new modeling
data, and analysis of the proposed Build and No-Action alternatives shall be
included.
Methodology
This section presents
the methodology and assumptions used to guide the transportation analysis. The
methodology and assumptions used in this analysis are consistent with those
applied in the SR 900 Widening Project.
20.3.1.1.
Traffic Model Refinement
The traffic model used in the SE Issaquah
Draft BS (June 2000) shall be replaced with the traffic model described below.
The TMODEL software shall be used in developing the traffic model.
Year 2000 Existing Conditions
The 2000 existing
conditions SE Bypass model shall be based off of the CITY's Travel Model used
for Concurrency Testing. The CITY's Travel Model assumes a 1999 land use and
year 2000 traffic data. The CITY's Travel Model shall be utilized as the Year
2000 SE Bypass Model.
Opening Year 2005
A future year 2005
traffic model, which will include a highway network of all freeways, freeway
interchanges, arterials and other streets in the study area shall be developed
for use in subsequent tasks for the SE Bypass SEIS. The 2005 SE Bypass model
shall be developed using the CITY's Year 2000 Travel Model (used for Concurrency
Testing) along with the 2005 SR 900 Widening Model's land use assumptions. The
SR 900 Widening land use assumptions may be adjusted; the CONSULTANT shall
notify the CITY if adjustments are applied to the 2005 SE Bypass Model. The King
County or PSRC Models may also be referenced and used if applicable.
20.3.1.2.
Land Use Assumptions For Transportation Modeling
Existing Conditions Year 2000
The CONSULTANT shall
summarize the land use assumptions based on the CITY's Year 2000 Travel Model
used for concurrency testing.
Opening Year 2005
Future year land use
assumptions shall be based off of the Year 2005 SR 900 Widening Model and may be
modified if necessary. The CONSULTANT shall summarize (and update if necessary)
the land use assumptions for the Year 2005 SE Bypass Model.
The land use assumptions may differ from those used for the
Draft EIS, since those used in the 2005 SE Bypass model shall be based on the
more current information.
20.3.1.3. Model Network
Existing Conditions Year 2000
For year 2000, one Model run (one model run shall include
both AM & PM traffic forecasts) shall be performed. The PM peak hour generated
trip tables from the 2000 SE Bypass model shall be transposed and if necessary
scaled to represent AM peak hour demand. Additionally, the hourly volumes shall
be balanced for the SE Bypass corridor.
The Model run shall include:
• 2000 Model
Run 1 - Year 2000 Existing Conditions: Year 1999 assumptions for land use shall
be incorporated.
Opening Year 2005
The transportation networks for model year 2005 shall be
developed from planned and programmed improvements to be implemented by WSDOT,
King County, and the City of Issaquah.
The CONSULTANT shall review and
revise the 2005 SE Bypass model network to provide continued consistency with
adopted Plans.
For year 2005, up to two Model
runs (one model run shall include both AM & PM traffic forecasts) shall be
performed. The PM peak hour generated trip tables from the 2005 SE Bypass model
shall be transposed and if necessary scaled to represent AM peak hour demand.
Additionally, the hourly volumes shall be balanced for the SE Bypass corridor.
Each model run shall contain different assumptions regarding programmed and
planned roadway projects.
The Model runs include:
• 2005 Model
Run 1 - Year 2005 No Action: Included shall be the following projects: North
SPAR, South SPAR, Sunset Interchange modification, and SR 900 widening. Baseline
2005 assumptions for land use shall be incorporated.
• 2005 Model
Run 2 - Year 2005 Full Build. Included shall be the following projects: NSPAR,
SSPAR, Sunset, SR 900, and SE Bypass (with no widening of SR 18)
20.3.1.4. Future Alternative Alignment
Travel Demand Forecasts
Based on future land use
assumptions supplied by the CITY and on the definition of the roadway alignment
alternatives, year 2005 travel demand forecasts shall be prepared using the
traffic model. For the 2005 build scenario, the proposed build alternative
alignment (based on the work completed through Phase 1) shall be considered.
Available output from TMODEL includes specific roadway
volumes, intersection volumes and select link data for the PM Peak hour. The
trip tables generated for the PM peak hour shall then be transposed and possibly
scaled in order to generate the AM Peak hour volumes. For the 2005 build
scenario, the traffic information extracted from the 2005 build model shall be
applied to the recommended proposed design alignment alternative (as determined
in Phase 1).
PRODUCTS
The CONSULTANT
shall provide the CITY a copy of the TMODEL electronic files with a brief
annotation for model year runs 2030, 2005, and 2000.
20.3.1.5. Modal Share Sensitivity
As part of development of the
2005 SE Bypass Model (No-Action and Build Scenarios), the CONSULTANT shall
prepare a summary of the various travel demand management assumptions
incorporated into the 2005 SE Bypass Model. Most travel demand management
assumptions shall be based primarily off of the assumptions made in the SR 900
Widening model along with the CITY's Travel Model used for concurrency testing,
and possibly the PSRC model. The travel demand management assumptions shall be
presented in the SEIS.
20.3.1.6. Intersection/Roadway
Operations
The CONSULTANT shall conduct
intersection/roadway operational analysis of key intersections/roadways (as
determined by the CONSULTANT and CITY). The Synchro software shall be utilized
in performing the traffic operational analyses. The operational analyses shall
be conducted for the AM and PM peak hours and intersection LOS along with
intersection delay (sec/veh) shall be recorded.
Year 2000 Existing
Conditions and Year 2005 No Action
The CONSULTANT shall perform intersection analysis for up
to twenty-five (25) intersections as determined by the CITY and CONSULTANT. The
AM and PM peak hours shall be analyzed for each intersection; the LOS and
intersection delay shall be recorded. The intersections that shall be analyzed
are (as per agreement with the CITY):
• SR 900
& NW Sammamish
• SR
900 & I-90 WB Ramps
• SR
900 & EB Ramps
• SR
900 & Gilman
• SR
900 & Maple
• E
Sammamish & 56th
•
Issaquah-Fall City & E. Lk. Sammamish
• Front
St. & WB Ramps
• Front
St. & EB Ramps
• Front
St & Gilman
• Front
St & Sunset
•
Issaquah-Fall City & Black Nugget Rd
•
Issaquah-Fall City & Issaquah Pine
•
Sunset & WB I-90 Ramps
•
Sunset & ED I-90 Ramps
• E
Sammamish & 43rd
• Front
Street & Clark
• Front
St & Dogwood - South
• Front
St & Dogwood - North
•
Sunset & Second
• Front
St & Second
• SR
900 & Newport
• E.
Lake Sammamish & Black Nugget
•
Second Avenue SE & Bush Street
•
Issaquah-Hobart Rd & May Valley Rd
Year 2005 Build
The proposed Build alternative as determined in Phase 1
shall be analyzed for the year 2005. The proposed roadway combination is defined
as inclusion of one north alignment alternative and the south alignment
alternative. In terms of traffic operations, all three North Alignments shall
operate similarly; therefore, one roadway combination (a north alignment and the
south alignment) shall be analyzed. Up to four (4) versions (or iterations)
shall be conducted. A roadway combination version (or iteration) may include:
•
Modifications to the number of lanes assigned at a particular intersection or
corridor
•
Modifications to design lengths (this can be either storage lengths or distance
between intersections)
The Synchro software shall be
utilized in determining corridor and intersection operations for the year 2005
build roadway combination as well as the twenty-five (25) intersections as
listed in the "Year 2000 Existing Conditions and Year 2005 No Action" section
(above). Additionally, the year 2000 Existing Conditions and the year 2005 No
Action intersections as described above shall also be analyzed using the Synchro
software.
The CONSULTANT is assuming that
the preferred alternative may be constructed in two stages where Stage 1
involves construction of a two-lane roadway and Stage 2 involves widening the
initial two-lane facility to four lanes. For the Build Scenario, the CONSULTANT
shall determine the projected year in which traffic volumes indicate that a
four-lane roadway would be necessary in order to adequately accommodate traffic
demand on the SE Issaquah Bypass.
20.3.1.7. Mitigation Measures
Qualitative analyses shall be
performed by the CONSULTANT to identify and discuss the potential effectiveness
of measures designed to mitigate any significant adverse impacts of each of the
alternatives.
20.3.1.8. Draft
Transportation Study
The CONSULTANT shall prepare a Draft
Transportation Study to document the results of the new traffic modeling and
analysis. The Draft Transportation Study shall build on the analysis started
under the Phase 1 Transportation Study. Ten (10) copies of the Draft Study shall
be provided for review and comments.
PRODUCTS
Draft Transportation Study for review by the City and other agencies (10
copies)
20.3.1.9. Final
Transportation Study
Following review of the Draft Transportation
Study, the CONSULTANT shall revise the Draft Transportation Study to incorporate
review comments. Fifteen (15) copies of the Final Transportation Study shall be
provided.
PRODUCTS
Final Transportation Study (15 copies)
20.3.2. Biological
Assessment
The CONSULTANT shall review and revise the
Biological Assessment (BA) prepared for the June 2000 Draft EIS. The BA shall be
revised to describe the impacts of the new alternatives on federally listed,
proposed, and candidate species and designated and proposed critical habitat
present in the project vicinity. The CONSULTANT shall submit 10 copies of the
Preliminary Revised Draft BA to the CITY for review and comment. The CONSULTANT
shall revise the document and provide ten (10) copies of the Revised Draft BA
for distribution with the Preliminary Supplemental Draft EIS to the USACE, USFWS,
EPA, NIVIFS, Ecology and WDFW.
PRODUCTS
• Preliminary Revised Draft BA (10 copies)
• Revised Draft BA (10 copies)
20.3.3. Photo Imaging of
Alternatives
The CONSULTANT shall provide up to four (4)
computer generated oblique view photographic images depicting proposed build
alternatives for inclusion in the Supplemental Draft and Final EIS. The images
shall also be used to create mounted display boards for use at public meetings,
project exhibits, and other public outreach events. In addition, three (3)
ground level photo simulations (Figures 4-20, 4-22, and 424) from the June 2000
Draft EIS, shall be revised to show a four-lane roadway design. Figures 4-25 and
4-26 shall be replaced with one (1) new ground-level view photo simulation to
represent the new southern alignment.
PRODUCTS
•
Computer generated oblique view photographic images (two sets of four images
mounted on foam core boards for public display)
•
Computer generated ground-level photographic images (four revised images for
report figures)
20.3.4.
Supplemental Draft EIS
The CONSULTANT shall prepare a
Supplemental Draft EIS to present new information on proposed project
alternatives and traffic analysis based on the outcome of the Phase I work plan.
The Supplemental Draft EIS shall follow a format consistent with guidance in the
revised WSDOT Environmental Procedures Manual (July 2001), guidance in the
"Interagency Working Agreement to Integrate Special Aquatic Resources (404)
Permit Requirements into the NEPA and SEPA processes in the State of
Washington," (NEPA/SEPA/404 Merger Agreement), and FHWA Technical Advisory
T6640.8A. The CITY will provide close coordination with WSDOT and FHWA
throughout the process. The document shall be in compliance with NEPA and SEPA.
The Supplemental Draft EIS is
anticipated to include the following sections and appendices (however, the final
organization and format may change in response to the CITY's needs):
20.3.4.1. Introductory Material
The following sections of the
June 2000 Draft EIS shall be revised, as appropriate:
• Cover
Sheet
• Title
Sheet
• Fact
Sheet
• Table
of Contents
• List
of Tables
• List
of Figures
20.3.4.2. Summary
The Summary section from the June
2000 Draft EIS shall be revised to include a brief description of the proposed
action, other governmental agency's actions in the geographic area, a summary of
alternatives and options considered, summary of major environmental impacts (in
table format with proposed mitigation measures), areas of concern or
controversy, unresolved issues, list of required permits, and a list of other
actions required for the proposed project.
20.3.4.3. Chapter 1: Purpose and Need
for the Action
This chapter shall be revised to
identify and describe the proposed action and the transportation problems or
other needs which it is intended to address. This discussion shall clearly
demonstrate that a need exists for the project.
20.3.4.4. Chapter 2: Alternatives
This chapter shall be revised to
describe the process used to identify various - alternatives, the range of
alternatives considered, and the alternatives that were eliminated from further
consideration. Chapter 2 shall include the NEPA 404 Alternatives Analysis and
Aquatic Resource Avoidance Analysis consistent with the requirements of the NEPA/SEPA/404
Merger Agreement. The analysis shall describe alternatives considered but
rejected (and reason why) including efforts to minimize or avoid impacts to
aquatic resources, and shall identify a preferred alternative, if known. A table
shall be included comparing the various impacts of each alternative.
Alternatives to be analyzed in
the Supplemental Draft EIS include:
•
No Action (no-build) Alternative
•
Alternative 1 (North A with a new south alignment)
•
Alternative 2 (North B with a new south alignment)
•
Alternative 3 (North C with a new south alignment)
A detailed description of the
alternatives selected for analysis in the Supplemental Draft EIS shall be
provided, together with updated information on estimated project costs and
construction timing. The description of the alternative design concepts shall be
in sufficient detail to allow identification of the specific characteristics of
each design concept to be evaluated. These characteristics include roadway
layout, intersection configurations, structural features, and other roadway
related facilities. Maps, alignment drawings, road sections, cost estimates, a
proposed construction schedule with milestones, and other exhibits shall be used
to describe and allow a comparison between the alternatives.
20.3.4.5. Chapter 3: Affected
Environment
This chapter shall be revised to
update the description of the existing social and environmental setting for the
area affected by the alternatives presented inthe Supplemental Draft EIS. The
following elements of the environment shall be reviewed and updated as
necessary: study area, local geography, geology and soils, hydrologic systems
and floodplains, wetlands, fish and wildlife habitat, land use, regional and
community growth, historic and archaeological elements, hazardous waste, and
visual quality. It shall also discuss the adopted land use and transportation
plans as they relate to the proposed project, including the City's Traffic
Concurrency Ordinance. These discussions shall be limited to data, information,
issues, and values that will have a bearing on possible impacts, mitigation
measures, and on the selection of an alternative.
20.3.4.6. Chapter 4: Environmental
Consequences
This chapter shall be revised to
document the direct project impacts, future operational impacts, secondary and
cumulative impacts, construction activity impacts and mitigation measures
associated with each of the three new build alternatives and the no-action
alternative.
Direct project impacts are
those impacts associated with the footprint or right-of-way of each alternative.
Future operational impacts
are those impacts resulting from ongoing operation of the project that are
anticipated to occur between the year of opening (2005) and the design year
(2030).
Secondary impacts are
those that are "caused by an action and are later in time or farther removed in
distance but are still reasonably foreseeable" (40 CFR 1508.8). These impacts,
which usually result from the initial action, include changes in land use, water
quality, economic vitality, and population density.
Cumulative impacts are
those that "result from the incremental consequences of an action when added to
other past and reasonable foreseeable future actions" (40 CFR 1508.7). The
cumulative effects of an action may be undetectable when viewed in the
individual context of direct and even secondary impacts but can nonetheless add
to other disturbances and eventually lead to a measurable environmental change.
Construction activity impacts
are limited to construction process impacts that are temporary in nature and
typically limited to the immediate project area (e.g., construction noise, dust,
traffic controls, etc.). The CONSULTANT is assuming that the preferred
alternative will be constructed in two stages: Stage 1 will involve construction
of a twolane roadway; Stage 2 will involve widening the initial two-lane
facility to four lanes.
The environmental elements listed
below shall be reanalyzed for each of fie alternatives addressed in the
Supplemental Draft EIS:
• Air
Quality
• Noise
•
Energy
•
Geology and Soils
•
Hydrological Systems
•
Floodplains
• Water
Quality
•
Wetlands
•
Vegetation and Wildlife
•
Fisheries
•
Threatened and Endangered Species
• Land
Use
•
Social Elements
•
Economic Elements
•
Displacement and Relocation
•
Historic and Cultural Resources
•
Hazardous Waste
•
Visual Quality
The CONSULTANT shall prepare
draft and final technical reports for Air Quality and Noise only. Draft
technical reports shall be submitted to the ClW and the STATE for review and
comment. No additional revisions to previously prepared discipline reports are
included. Any other discipline report changes would be considered "extra work."
The CONSULTANT shall not perform additional
floodplain modeling work (HEC-RAS) as part of this work plan. Floodplain impact
analysis and conceptual design for the SETS alternatives performed by the
CONSULTANT shall be based on the recently updated floodplain information
(Montgomery Water Group, 2001) provided to the CONSULTANT by the CITY. Any
additional HEC-RAS analysis would be considered extra work.
PRODUCTS
• Draft and Final Air Quality Reports (10 copies each of
Draft and Final)
• Draft and Final Noise Reports (15 copies each of Draft and
Final)
20.3.4.7.
Chapter 5: Comments and Coordination
The CONSULTANT shall update this chapter to
summarize the results of additional coordination with federal, state, and local
agencies, their level of involvement, and any unresolved issues or areas of
conflict. This section shall also summarize additional public involvement
activities conducted as part of the Supplemental Draft EIS. 20.3.4.8.
Chapter 6: Section 4(f) Evaluation
The CONSULTANT shall update and revise the
Section 4(f) evaluation to reflect the impacts (both during construction and
operation) associated with the new build alternatives. The CONSULTANT shall
identify and evaluate location and design alternatives which would avoid each
and all Section 4(f) properties; explain whether any avoidance alternatives
which were eliminated from further study are "feasible and prudent" and if not,
explain why; discuss all possible measures which are available to minimize
impacts on Section 4(f) properties, including commitments made and monitoring
procedures to minimize harm.
20.3.4.9.
Response to Comments on Draft EIS
The CONSULTANT shall review and prepare
responses to over 1,000 comments received on the Draft EIS in letters and
recorded testimony at the Draft EIS public hearing. It is assumed that many of
the comments received are similar incontent and a response to one will be
appropriate for many others. It is also assumed that many of the comments will
no longer be relevant because several of the alternatives presented in the Draft
EIS are no longer being considered. Copies of the comment letters and recorded
public testimony, along with the responses to those comments, shall be presented
in an appendix to the Supplemental Draft EIS. During this task the CONSULTANT
shall also review one (1) "constituent proposal" and provide a written response
to be included in an appendix to the Supplemental Draft EIS.
20.3.4.10. Closing
Sections/Appendices
The CONSULTANT shall prepare closing
documentation for the SEIS, including the following information:
• Principal Contributors
• Studies Performed
•
Supplemental Draft EIS Distribution List
•
Transportation Studies
•
Supplemental Alternatives Analysis
•
Historic Site Documentation
20.3.4.11. Preliminary Supplemental Draft
EIS
The CONSULTANT shall produce a
preliminary Supplemental Draft EIS and submit ten (10) copies to the CITY for
review and comment. The CONSULTANT shall revise the document and provide fifteen
(15) copies of the preliminary Supplemental Draft EIS (including the revised
Wetland and Streams Technical Memorandum and Biological Assessment) to the CITY
for distribution to the USACE, USFWS, EPA, NMFS, Ecology and WDFW.
PRODUCTS
•
Preliminary Supplemental Draft EIS for CITY review (10 copies)
•
Preliminary Supplemental Draft EIS for review by agencies (15 copies)
20.3.4.12. Camera-Ready Supplemental
Draft EIS
The CITY will provide one
consolidated set of comments on the Preliminary Supplemental Draft EIS to the
CONSULTANT. It is assumed that agencies will submit comments separately. The
CONSULTANT shall make requested revisions and prepare a camera-ready
Supplemental Draft EIS for review by the CITY. The Supplemental Draft EIS shall
include an initial wetland mitigation plan if a preferred alternative is known,
otherwise a conceptual mitigation plan shall be included in the Supplemental
Draft EIS.
PRODUCTS
Camera-ready
copy of the Supplemental Draft EIS for CITY approval (1 copy).
20.3.4.13. Reproduction and Distribution
Upon approval of the camera-ready
Supplemental Draft EIS by the CITY, the CONSULTANT shall reproduce 200 copies of
the final Supplemental Draft EIS for distribution. The CITY will provide the
distribution list. The CONSULTANT shall assist the CITY in distributing the
document to the agencies and the public.
PRODUCTS
200 copies of
the Supplemental Draft EIS for submittal to the CITY for distribution.
20.3.5. Public Hearing
A joint public hearing on the
Supplemental Draft EIS and the Section 404 permit application will be conducted
within 30-days following publication of the Supplemental Draft EIS. The CONSULTANT shall
prepare materials for the hearing and provide originals to the CITY for
reproduction and distribution. Relevant CONSULTANT activities shall include:
• Assist
the CITY in preparing the public hearing packet
•
Assist the CITY in preparing exhibits and handouts
•
Prepare a Synchro display showing traffic operations
•
Provide technical staff to attend the Public Hearing
It is assumed that up to four (4)
CONSULTANT team staff shall attend the public hearing. It is also assumed that
the CITY will be responsible for arranging the meeting place, arranging for a
court reporter, preparing the public notice for the joint Supplemental Draft EIS/Section
404 Public Hearing Notice, and all other activities related to meeting
organization and/or preparation.
20.3.6. Final EIS
20.3.6.1. Respond to Comments on the
Supplemental Draft EIS
The CITY will provide the
CONSULTANT with copies of the letters received with comments on the Supplemental
Draft EIS. The CITY will also provide the CONSULTANT with a copy of the
transcript recording public testimony received at the public hearing. Revisions
to the Supplemental Draft EIS shall be based on the comment letters, public
hearing testimony and agency comments received during the review period.
The CONSULTANT shall compile a
summary of comments received on the Supplemental Draft EIS, provide responses to
comments, and make recommendations, if necessary, on the need for additional
studies, additional mitigation or changes to the design. For budgeting purposes,
it is assumed that there will be a maximum of 100 comment letters with 10
comments each for a total of 1,000 comments. If there are more than 100 comment
letters or 1,000 comments, the extra level of effort to address comments shall
be considered "extra work."
20.3.6.2. Revise Environmental Analysis
The CONSULTANT shall revise the
discussion of elements of the environment in EIS to reflect changes in the
project design, impacts, and proposed or required mitigation that have occurred
since publication of the Supplemental Draft EIS, or in response to review
comments on the Supplemental Draft EIS. Any proposed additional studies,
detailed analyses, or changes in design shall be considered "extra work."
20.3.6.3. Preliminary Final EIS
Document
The CONSULTANT shall produce a
preliminary Final EIS and submit ten (10) copies to the CITY for review and
comment. The CONSULTANT shall revise the document and provide fifteen (15)
copies of the preliminary Final EIS (including the final alternatives analysis,
identification of the preferred alternative and apparent least environmentally
damaging practicable alternative, and apparent final wetland mitigation plan) to
the CITY for distribution to the USACE,
USFWS, EPA, NMFS, Ecology and WDFW. The Final EIS shall incorporate
changes that reflect changes in the project scope, impacts, technical analysis
and mitigation analysis that have occurred since the Supplemental Draft EIS. The
Final EIS shall include comments received on the Supplemental Draft EIS, a
summary of the comments, responses to comments, and an updated fact sheet.
PRODUCTS
•
Preliminary Final EIS for CITY review (10 copies)
•
Preliminary Final EIS for review by agencies (15 copies)
20.3.6.4. Camera-Ready Final EIS
The CITY will provide one
consolidated set of comments on the preliminary Final EIS to the CONSULTANT. It
is assumed that reviewing agencies will submit comments separately. The
CONSULTANT shall revise the preliminary Final EIS in response to the comments
received from the CITY and reviewing agencies. The CONSULTANT shall prepare a
camera-ready Final EIS and the CITY will conduct a second review to check and
approve the changes and authorize reproduction and issuance of the Final EIS.
PRODUCTS
Camera-ready
copy of the Final EIS for City approval (1 copy)
20.3.6.5. Reproduction and Distribution
The CONSULTANT shall make the
second, minor revisions based on the review and approval of the camera-ready
Final EIS and reproduce 200 copies of the Final EIS for distribution. The CITY
will provide the distribution list for the Final EIS. The CONSULTANT shall
assist the CITY in distributing the document to agencies and the public.
PRODUCTS
200 copies of
the Final EIS for submittal to the CITY for distribution.
20.3.7. Record of
Decision
The CONSULTANT shall assist the
CITY in preparing the draft NEPA Record of Decision (ROD) and shall address any
Final EIS comments received from FHWA.
PRODUCTS
•
Draft Record of Decision (1 copy)
•
Final Record of Decision (1 copy)
20.3.8. Respond to
Miscellaneous Public Comments
If directed by the CITY, the
CONSULTANT shall prepare responses to public comments on deliverables prepared
under this work plan. It is assumed that the CONSULTANT shall spend four (4)
hours responding to up to ten (10) public comments. Additional effort by the
CONSULTANT to respond to more than ten (10) comments shall be considered "extra
work".
20.4 NEPA/SEPA/404 MERGER ACTIVITIES
The CONSULTANT shall provide
project coordination to comply with the "Interagency Working Agreement to
Integrate Special Aquatic Resources (404) Permit Requirements into the NEPA and
SEPA processes in the State of Washington, "(NEPA/SEPA/404 Merger Agreement).
20.4.1. NEPA/SEPA/404 Merger Concurrence
The CONSULTANT shall coordinate
with regulatory agencies to gain concurrence on the preliminary Supplemental
Draft EIS regarding project alternatives to be evaluated in the Supplemental
Draft EIS, preliminary preferred alternative, and initial and detailed wetland
mitigation plans. Additional studies required to obtain concurrence, or
development and analysis of additional alternatives, shall be considered "extra
work." Preparation of the final version of the Supplemental Draft EIS cannot
proceed without issuance of a letter of concurrence from the reviewing agencies.
Up to two (2) CONSULTANT staff
shall attend up to three (3) meetings with regulatory agencies to gain
concurrence on the preliminary Final EIS regarding the apparent final mitigation
plan and the preferred alternative/least environmentally damaging alternative,
as specified in the NEPA/SEPA/404 Merger Agreement. Additional meetings, studies
or revisions to alternatives that may be needed to obtain concurrence shall be
considered "extra work." Publication of the Final EIS cannot occur without
issuance of a letter of concurrence from the 404 Merger agencies.
20.4.2. Initial Mitigation Plan
Upon issuance of the Agency
Concurrence Letter regarding alternatives to be evaluated in the Supplemental
Draft EIS and identification of the preferred alternative, the CONSULTANT shall
conduct a preliminary investigation of candidate mitigation sites to determine
if there are suitable sites to support the required mitigation. Upon
identification of candidate sites, the CONSULTANT shall prepare a draft Initial
Mitigation Plan for the preferred alternative, as described in Appendix F of the
NEPA/SEPA/404 Merger Agreement. The Draft Plan shall identify unavoidable
impacts to aquatic resources; establish the goals and objectives of the
mitigation; the timing of the mitigation; a general description of the candidate
sites; and proposed monitoring of the mitigation. The Draft Plan shall be
submitted to the CITY for review and comment.
The Draft Initial Mitigation Plan
shall be revised to address the CITY's comments. The revised Plan shall be
submitted to the CITY for distribution to other merger agencies for review and
comment. The CITY will provide consolidated comments on the Plan to the
CONSULTANT. The CONSULTANT shall conduct a site visit with the USACE to review
candidate sites. The CONSULTANT shall prepare a final Initial Mitigation Plan
for inclusion in the Draft SEIS.
• Draft Initial Wetlands Mitigation Plan for CITY review (10 copies)
• Draft Initial Wetlands Mitigation Plan for agency review (15 copies)
• Final Initial Wetlands Mitigation Plan for inclusion in the
Supplemental Draft EIS (one camera ready copy)
20.4.3. Section 404 Permit Application
Prior to submittal of the
Preliminary Supplemental Draft EIS, the CONSULTANT shall attend one
pre-application meeting with the USACE to identify issues of concern and confirm
Section 404 permitting requirements and scheduling. The CONSULTANT shall then
prepare draft Section 404 permit application materials for submittal to the
CITY. The CITY will submit the permit application to the USACE. Prior to
publication of the Final EIS, the CONSULTANT shall prepare a final Section 404
permit application for submittal to the USACE. The final application shall
include a Detailed Mitigation Plan and Report.
• Draft Section 404 Wetland Permit Application
• Final Section 404 Wetland Permit Application
20.4.4. Detailed Mitigation Plan and Report
Prior to publication of the Final
EIS, the CONSULTANT shall prepare a draft Detailed Mitigation Plan and Report
for the preferred alternative, as described in Appendix F of the NEPA/SEPA/404
Merger Agreement. The Draft Detailed Mitigation Plan shall include a summary of
wetland impacts, description of proposed mitigation and mitigation site(s),
mitigation design (hydrology source, grading plan, soil preparation, planting
plan, and schedule), standards of success, and monitoring and contingency plans.
The Draft Plan shall be submitted to the CITY for review and comment. The Draft
Plan shall be revised to address the CITY's comments. The revised Plan shall be
submitted to the CITY for distribution to the merger agencies with the
preliminary Final EIS.
Upon issuance of concurrence on
the preliminary Final EIS by the reviewing agencies, the CONSULTANT shall
prepare a Final Detailed Mitigation Plan for inclusion in the Final EIS.
A Final Mitigation Plan as required by the NEPA/SEPA/404 Merger Agreement is not
included in this Work Plan and shall be considered "extra work".
• Preliminary Draft Detailed Wetland Mitigation Plan and Report (10
copies) Draft Detailed Wetland Mitigation Plan and Report (15 copies)
• Final Detailed Wetland Mitigation Plan and Report (one camera ready
copy)
20.5.
CONCEPTUAL DESIGN
20.5.1 Supplemental
Survey and Mapping
The CONSULTANT shall collect
additional field survey with to update the existing mapping that will enable
development of the conceptual design to the level necessary to provide a clear
idea of the environmental impacts. Except for critical culverts, underground
utilities shall not be surveyed or mapped. The CONSULTANT shall update the
existing base map with the additional supplemental survey data. This
supplemental survey data shall be developed in metric units. The survey work
shall conform to NAD 83/91 and to the vertical datum used by the CITY for this
project.
PRODUCTS
Updated Aerial
Base Mapping
20.5.2 Geotechnical
Feasibility Study
The CONSULTANT shall conduct
geotechnical investigations to support the conceptual design task. These
investigations include the following:
• Conduct
a detailed site reconnaissance along the new southern alignment to evaluate
existing conditions. Also conduct a reconnaissance along the preferred north
alignment to observe current site conditions.
• Drill a
total of eight (8) borings: Six (6) along the centerline alignment of the new
southern alternative and two (2) at the northerly edge of the proposed roadway
along the new southern alternative. The borings shall be drilled to depths
ranging from
15 to 40 feet using a track-mounted drill rig. Soil samples shall be collected
from the borings at five-foot depth intervals. The CONSULTANT shall obtain
"Right-of-Entry" to complete the eight (8) soil borings.
• Install
a piezometer casing in the borings for ground water monitoring. Monitor ground
water levels on a monthly basis for six (6) months following installation. The
borings/piezometers shall be backfilled in accordance with Washington State
Department of Ecology requirements.
• Conduct
limited laboratory testing on the soil samples obtained from the borings. The
testing shall include moisture content.
•
Evaluate the subsurface information obtained from the soil borings as a basis
for describing the existing conditions, impacts and mitigation of identified
environmental issues.
The CONSULTANT shall prepare a
Geotechnical Feasibility Report that documents the additional geotechnical
activities described above, as well as the geotechnical investigations conducted
in support of the June 2000 Draft EIS. The report shall identify preliminarily
recommended slope support options including but not limited to MSE walls,
soldier pile walls, reinforced concrete walls, and rockeries.
PRODUCTS
•
Draft Geotechnical Feasibility Report (3 copies)
•
Final Geotechnical Feasibility Report (3 copies)
20.5.3 Design Memorandum
A Design Memorandum summarizing
the relevant geometric design criteria applicable to CITY designated design or
posted speed limits shall be prepared based on applicable design standards and
in accordance with the CITY'S Design Standards and the WSDOT Local Agency
Guidelines Manual, as well as the AASHTO Green Book (See Attachment A).
Particular emphasis shall be placed on identifying those elements that may be
subject to interpretation, engineering judgment or modification due to adverse
field conditions. The CONSULTANT shall review the design elements with and seek
approval by the CITY.
The Design Memorandum shall
include documentation on design decisions, design deviations, geotechnical and
structural evaluations, stormwater management issues and considerations, and a
staged construction proposal.
PRODUCTS
• Draft Design Memorandum (3 copies)
• Final Design Memorandum (3 copies)
20.5.4 Refine Phase 1
Conceptual Design
The CONSULTANT shall complete
conceptual design work for the three (3) build alternatives begun during Phase 1
(Task 19.3.2). The three build alternatives are comprised of one new southern
alignment and three refined northern alignments from the original Draft EIS
(June 2000). The three northern alignments can be matched with the one new
southern alignment (at a common match point) to yield three different
alternatives providing a new north south connection between I-90 and Front
Street.
During this task the CONSULTANT
shall refine the channelization features for each of the alternatives to reflect
the traffic needs for the year 2030 as described in the Phase 1 Transportation
Study (Task 19.3.1).
The CONSULTANT shall refine the
roadway template, including retaining walls and stormwater facilities, develop
new cross sections, and refine slope lines to allow determination of potential
impacts to wetlands, streams, floodplains, trails, existing homes, school
district property and other elements of the environment. Space for roadside
landscaping shall be included along the western edge of the proposed roadway.
The CONSULTANT shall develop up to two (2) Typical Sections to depict the
roadway prism in the northern segment of each alternative and one (1) Typical
Section illustrative of all alternatives for the roadway section in the southern
segment.
Based on the results of this
effort and the corresponding impacts, the CONSULTANT shall revise the horizontal
and vertical alignments up to two additional times for each alternative, once in response to
the CITY'S review comments and once in response to comments received on the
Supplemental Draft EIS, to mitigate unfavorable impacts to existing natural
resources, properties and structures. With each vertical alignment revision, the
CONSULTANT shall rerun cross sections
throughout the length of the vertical alignment revision and revise slope lines
to further determine their impact on the environment.
The
CONSULTANT shall prepare a design that accommodates existing and
proposed pedestrian and bicycle facilities within the corridor, as well as
appropriate connections and extensions of existing trails. Type 11 bicycle lanes
and contiguous sidewalks are to be assumed.
The
CONSULTANT shall coordinate with Issaquah School District officials
to identify appropriate and reasonable vertical alignments for each alternative
(including possible noise berm) to address school district concerns over
potential noise impacts to Issaquah High School. One (1) meeting with three (3)
people is assumed for budgetary purposes.
The
CONSULTANT shall review and modify the size, type and location of
proposed stormwater management facilities to reflect the refined roadway design
and new floodplain elevation information (Montgomery Water Group, 2001) provided
to the CONSULTANT by the CITY.
If a revision in the horizontal
and vertical alignment of the planned East Sunset Way connection to the SE
Issaquah Bypass is required because of refinements to the SE Bypass design
geometrics, that effort shall be considered "extra work" and will be covered by
a future change order.
PRODUCTS
• Plans, profiles and typical sections for up to three (3) alternatives
identifying the proposed project design for the northern and southern
alignments shall be provided. Three (3) sets of drawings shall be provided for
up to three (3) submittals.
20.5.5 Stage 1 Conceptual
Design
It is anticipated that the
construction sequencing of the preferred alternative will be shown to occur in
two separate stages. The CONSULTANT
shall prepare Stage 1 plans that depict a two-lane roadway with bike lanes in
each direction and a sidewalk on the southbound side only. Retaining walls would
be located to accommodate an ultimate build out of a four-lane roadway section.
Three Typical Sections shall be prepared depicting the two-lane roadway in Stage
1. The Stage 1 plans shall also reflect the rightof-way acquisition needs to
accommodate the ultimate build out. Roadway profile changes are assumed not to
be required.
The
CONSULTANT shall develop a stormwater management facilities design
to accommodate a two-lane roadway. Roadside ditches are assumed for the Stage 1
stormwater conveyance system. The CONSULTANT
shall also design reduced-size stormwater detention ponds appropriate for
the Stage 1 construction.
PRODUCTS
Stage 1 plans
and typical sections for one (1) submittal (3 sets).
20.5.6 Cost Estimates
The CONSULTANT shall prepare a
conceptual cost estimate for each of the SETS build alternatives. A refined cost
estimate shall be prepared for the preferred alternative reflecting a two-stage
construction sequence. Costs shall be based on standard bid item tables
published by WSDOT and the CITY. The CITY will provide estimated right-of-way
costs based upon right-of-way requirements identified by the CONSULTANT.
Earthwork volumes shall be prepared for both Stage 1 and Stage 2 construction.
PRODUCT
Conceptual cost
estimates for SEIS Build Alternatives (3 sets)
Conceptual cost
estimate for preferred alternative with two-stage construction (3 sets)
20.6.
6TH
AVENUE SE ALIGNMENT (OPTIONAL)
The CONSULTANT shall conduct
additional transportation and environmental analysis and conceptual design
activities to include an additional southern alignment in the Supplemental EIS.
The additional southern alignment is assumed to approximately follow the
existing alignment of 6thAvenue SE. This is an optional task included
in the work plan budget. The optional tasks are further defined below:
20.6.1. Transportation Study
The CONSULTANT shall conduct
additional transportation analysis to study an additional southern alignment
that approximately follows the alignment of 6th Avenue SE and intersects with
Issaquah-Hobart Road at approximately SE 96th Street. The additional
analysis shall include rerunning the TMODEL travel demand forecasts for the 2030
build scenario to include the additional southern alignment.
The CONSULTANT shall also conduct
additional Synchro intersection/roadway operational analysis for up to three (3)
alignment combinations (i.e. the 6thAvenue SE southern alignment with
each of the three northern alignments). In addition, the transportation analysis
described in Task 20.3.1 of this work plan shall be expanded to include analysis
of the additional alternative for the opening year of 2005.
20.6.2. Supplemental Draft EIS
The CONSULTANT shall expand the
discussion and analysis in the Supplemental Draft EIS to include an additional
southern alignment that approximately follows the alignment of 6th
Avenue SE. The following sections of the EIS document shall be revised to
discuss the additional alternative:
• Summary
•
Chapter 1 Purpose and Need for the Action
•
Chapter 2 Alternatives
•
Chapter 3 Affected Environment
•
Chapter 4 Environmental Consequences
•
Chapter 5 Comments and Coordination
•
Chapter 6 Section 4(f) Evaluation
The impact analysis in the
Supplemental Draft EIS addressing the environmental elements listed below shall
be expanded to include analysis of the additional southern alignment that
approximately follows 6th Avenue SE:
-
Air
Quality
-
Noise
-
Energy
-
Geology and Soils
-
Hydrological Systems
-
Floodplains
-
Water
Quality
-
Wetlands
-
Vegetation and Wildlife
-
Fisheries
-
Threatened and Endangered Species
-
Land Use
-
Social Elements
-
Economic Elements
-
Displacement and Relocation
-
Historic and Cultural Resources
-
Hazardous Waste
-
Visual Quality
The Air Quality and Noise modeling efforts and
related technical reports shall be expanded to include the additional southern
alignment.
20.6.3. Final EIS
The CONSULTANT shall address public and agency
comments received on the Supplemental Draft EIS related to the additional
southern alternative. For budgeting purposes it is assumed that the addition of
the 6thAvenue southern alignment will add approximately 25% to the
level of effort assumed for this task in 20.3.6.1. The CONSULTANT shall revise
the discussion of elements of the environment in the EIS to reflect any changes
in the project design, impacts and proposed or required mitigation as they
relate to the additional alternative.
20.6.4. NEPA/SEPA/404 Merger Activities
The CONSULTANT shall coordinate with
regulatory agencies to review and comment on the additional southern alignment
along 6th Avenue SE. Additional studies required to obtain
concurrence from the regulatory agencies, or development and analysis of
additional alternatives, shall be considered "extra work."
Up to two (2) CONSULTANT staff shall attend up
to three (3) additional meetings with regulatory agencies to gain concurrence on
the preliminary Final EIS regarding the apparent final mitigation plan and the
preferred alternative/least environmentally damaging alternative, as specified
in the NEPA/SEPA/404 Merger Agreement. Additional meetings, studies or revisions
to alternatives that may be needed to obtain concurrence shall be considered
"extra work."
20.6.5. Conceptual Design
The CONSULTANT shall supplement the conceptual
design work described in Task 20.5 of this work plan to include conceptual
design of an additional 6thAvenue SE alignment. The 6th
Avenue SE alignment shall be designed to match with any one of the three
northern alignments (at a common match point) to yield three different
alternatives providing a new connection between I-90 and Issaquah-Hobart Road.
During this task the CONSULTANT shall develop
conceptual plan, profile, and typical section for an alignment that reflects the
traffic channelization needs for the year 2030 as determined in the Task 20.1.6,
above.
The
CONSULTANT shall prepare a roadway template, including retaining
walls and stormwater facilities, develop new cross sections, and refine slope
lines to allow determination of potential impacts to wetlands, streams,
floodplains, trails, existing homes, school district property and other elements
of the environment. Space for roadside landscaping shall be provided along the
western side of the proposed roadway. The CONSULTANT shall develop one (1) Typical Section to further clarify
the roadway prism at a selected location along the alignment.
Based on the results of this
effort and the corresponding impacts, the
CONSULTANT shall revise the horizontal and vertical alignments up to two
additional times, once in response to the CITY'S review comments and once in
response to comments received on the Supplemental Draft EIS, to mitigate
unfavorable impacts existing natural resources, properties, and structures. With
each vertical alignment revision, the
CONSULTANT shall rerun cross sections throughout the length of the
vertical alignment revision and revise slope lines to further determine their
impact on the environment.
The
CONSULTANT shall accommodate existing and proposed pedestrian and
bicycle facilities within the corridor, as well as appropriate connections and
extensions of existing trails. Type II bicycle lanes and contiguous sidewalks
are anticipated.
The
CONSULTANT shall review and modify the size, type and location of
proposed stormwater management facilities to reflect the new southern roadway
alignment.
PRODUCTS
• Plan, profile and typical section identifying the proposed project
design for the additional southern alignment shall be provided. Three (3) sets
of drawings shall be provided for up to three (3) submittals.
20.6.6. 6th Avenue
SE Stage 1 Conceptual Design
The
CONSULTANT shall prepare Stage 1 plans that depict a two-lane
roadway with bike lanes in each direction and a sidewalk on the southbound side
only. Retaining walls, if any, would be located to accommodate the ultimate
build-out of a four-lane roadway section. One (1) Typical Section shall be
prepared depicting the two-lane roadway in Stage 1. The Stage 1 plans shall also
reflect the right-of-way acquisition needs to accommodate the ultimate build
out. Roadway profile changes are assumed not to be required.
The
CONSULTANT shall develop a Stage 1 stormwater management facility
design to accommodate a two-lane roadway. Roadside ditches are assumed for the
Stage 1 stormwater conveyance system. The
CONSULTANT shall also design reduced-size stormwater detention ponds
appropriate for the Stage 1 construction.
PRODUCTS
Stage 1 plan
and typical section for one (1) submittal (3 sets).
20.6.7. Cost Estimates
The CONSULTANT shall revise the
conceptual cost estimates described in Task 20.5.5 to include the
additional 6th Avenue alignment. Costs shall be based on
standard bid item tables published by WSDOT and the CITY. The CITY will provide
estimated rightof-way costs based upon right-of-way requirements identified by
the CONSULTANT.
ATTACHMENT A - DESIGN GUIDELINES
The CITY will designate the basic premises
and criteria for the design. Reports and plans, to the extent feasible, shall be
developed in accordance with the latest edition and amendments to the following:
City of Issaquah Publications
• Issaquah Design Standards
• Critical
Areas Ordinance
King County Publications
• Road Standards 1994
• General
Special Provisions 1991
• Surface
Water Design Manual
• Community
Plan
• Basin
Studies
• Sensitive
Areas Ordinance
Washington State Publications
• Standard Specifications for Road,
Bridge, and Municipal Construction
(M41-10)
• Standard
Plans for Road, Bridge, and Municipal Construction
(M21-01)
•
Amendments and General Special Provisions • Standard Item Table
• Highway
Design Manual
• Bridge
Design Manual
•
Construction Manual
• Local
Agency Guidelines
• DOE
Stormwater Management Manual forthe Puget Sound Basin
•
Hydraulics Manual
American Association of State Highway and
Transportation Officials Publications
• A Policy on Geometric Design of
Highways and Streets (2000)
• A Policy
on Geometric Design of Highways and Streets
(1994) (Green Book)
• Standard
Specifications for Highways Bridges,
Twelfth Edition (1977)
• A Guide
for Highway Landscape and Environmental Design
(1970)
• Highway Design and Operational Practices
Related to Highway Safety (1974)
(Yellow Book)
• Any
American Association of STATE Highway Officials policy applicable where said
policy is not in conflict with CITY standards
U.S. Department of Transportation
Publications
• Manual on Uniform Traffic Control
Devices for Streets and Highways
Other Publications
• National Electrical Code
• Transportation Research Board
Highway Capacity Manual (1994)
Change Order #10v2
Phase 2
Work Plan
Southeast Issaquah Bypass
Supplemental Environmental Impact Statement
and Preliminary Engineering Design
Change
Order No. 10
June 5,
2002
INTRODUCTION AND ASSUMPTIONS
This work plan describes Phase 2 activities for the
Southeast Issaquah Bypass project. Phase 2 activities described herein build
on and continue the work initiated during Phase 1 (Change Orders No. 8 and 9).
During Phase 2, the following tasks shall be performed:
·
Conduct traffic analysis for the
opening year 2005 AM and PM peak hours. Opening year analysis shall include
the proposed Build alternative as well as the No Action alternative. Existing
year 2000 conditions for AM and PM Peak hours shall also be analyzed. Included
shall be updated traffic modeling data for both opening year 2005 and existing
year 2000.
·
Prepare a Supplemental Draft and
Final Environmental Impact Statement; including revisions to the Section 4(f)
Evaluation, Biological Assessment, and Section 106 documentation prepared for
the June 2000 Draft EIS.
·
Respond to approximately 1,000
public and agency comments received on the June 2000 Draft EIS.
·
Prepare Initial and Detailed
Wetland Mitigation Plans (including draft and final USACE Section 404 permit
applications).
·
Coordinate with the USACE, EPA,
USFWS, NMFS, WDFW and Ecology as part of the Section 404 Merger Process.
·
Participate in a Public Hearing
on the Supplemental Draft EIS.
·
Assist the City of Issaquah in
obtaining a Record of Decision from FHWA.
·
Collect additional field survey
to update the existing mapping to preliminary design level accuracy within the
study alignment corridor.
·
Conduct geotechnical
investigations to support the preliminary design task. • Complete Phase 2
Preliminary Design
·
Describe project staging
·
Prepare preliminary cost
estimates
Items is be- provided-to-the CONSULTANT by the CITY
The CITY will furnish to
the CONSULTANT copies of documents that are available to the CITY that will
facilitate the preparation of the plans and studies within the limits of the
project. These include:
·
Aerial mapping in hard copy and
digital (AutoCAD) format
·
A list of utilities and other
agencies having jurisdiction in the project area
·
Rights of Entry to affected
properties as requested by the CONSULTANT (except as otherwise noted in this
workplan)
·
"As Built" plans, as available
·
Assessor's maps (in digital and
hard copy format)
·
Timely review of all CONSULTANT
submittals and collation of all review comments into a single document for
submission to the CONSULTANT at one time
• Existing right-of-way and parcel
information in AutoCAD format
·
Updated floodplain mapping and
background data for Issaquah Creek (Montgomery, 2001).
20.1. PROJECT MANAGEMENT
20.1.1. Project Management Plan
The CONSULTANT shall update the project management
plan to incorporate any staffing changes, changes in deliverables or other
updates required by the Phase 2 work plan.
20.1.2. Monthly Billings, Progress Reports and Schedule Updates
The CONSULTANT shall prepare monthly progress reports
describing the status of the project. These reports shall:
·
Highlight significant
accomplishments
·
Target potential problem areas
needing special attention or coordination
·
Compare actual work progress with
contractual obligations on a task by task basis
Progress reports and billings shall be prepared by the
CONSULTANT and submitted on a monthly basis. These items shall be supported by
detailed record keeping sufficient to closely track the project budget and
expenditures and support the billings. The CONSULTANT shall monitor project
progress and provide schedule updates, as appropriate, up to a maximum of
sixteen (16) total schedule updates.
PRODUCTS
Monthly Progress Reports, incorporating Project Schedule revisions as
appropriate, and Monthly Billings. Approximately 16 progress reports and
billings shall be provided.
20.1.3. Direction, Meetings, and Coordination
This task includes-the.
following project management_ items:
20.1.3.1. Team Coordination/General Direction
Regularly scheduled internal
staff meetings shall be held (two per month over fourteen months) to direct
team efforts and facilitate completion of project tasks identified in the
Phase 2 work plan. This task also includes project administrator coordination
with subconsultants and one team coordination meeting with subconsultant
staff.
20.1.3.2. Coordination Meetings with City Staff
Up to twenty (20)
coordination meetings shall be held with Issaquah staff to review progress and
discuss upcoming actions. The meetings shall be held at the CONSULTANT'S
Seattle office. Additional meetings with CITY staff under this task include:
one (1) working session with the Public Works Director and the Mayor's team;
one (1) working session with
the City Council; and one (1) additional meeting with the Public Works
Director to review work plan and schedule. The CONSULTANT shall prepare
meeting minutes to summarize issues discussed at each meeting.
PRODUCTS
Meeting notes documenting topics discussed and future action items shall
be prepared and distributed via e-mail.
20.1.3.3. Coordination with Public Involvement Consultant
The CONSULTANT shall provide
support to the City on public involvement efforts led by others, including
review of up to three (3) draft newsletters and the preparation of up to three
(3) electronic graphics/figures for inclusion in the newsletters.
20.2. QUALITY CONTROL
20.2.1. Quality Assurance
Project deliverables
shall be reviewed by CONSULTANT team staff with expertise in the appropriate
discipline areas. This task also includes CONSULTANT team effort to review
work products prepared by SUBCONSULTANTS. This shall be an ongoing activity
during the duration of the project.
20.3. SUPPLEMENTAL EIS
20.3.1. Transportation Study
Traffic Conditions and
Analysis
Phase 2 work performed by the CONSULTANT shall include those tasks necessary
to analyze both the proposed Build alternative (based on the year 2030
analysis as described in Phase 1) for the opening year 2005 for both the AM
and PM peak hours. Additionally, the year 2005 No Action and existing year
2000 conditions shall be analyzed. Updated traffic modeling data, traffic
analysis based on new modeling data, and analysis of the proposed Build and
No-Action alternatives shall be included.
Methodology
This section-presents the
methodology-and-assumptions used to guide the transportation analysis. The
methodology and assumptions used in this analysis are consistent with those
applied in the SR 900 Widening Project.
20.3.1.1. Traffic Model Refinement
The traffic model used in
the SE Issaquah Bypass Draft EIS (June 2000) shall be replaced with the
traffic model described below. The TMODEL software shall be used in developing
the traffic model
Year
2000 Existing Conditions
The 2000 existing conditions SE
Bypass model shall be based on the CITY's Travel Model used for Concurrency
Testing. The CITY's Travel Model assumes a 1999 land use and year 2000 traffic
data. The CITY's Travel Model shall be utilized as the Year 2000 SE Bypass
Model.
Opening
Year 2005
A future year 2005 traffic model,
which will include a highway network of all freeways, freeway interchanges,
arterials and other streets in the study area shall be developed for use in
subsequent tasks for the SE Bypass SETS. The 2005 SE Bypass model shall be
developed using the CITY's Year 2000 Travel Model (used for Concurrency
Testing) along with the 2005 SR 900 Widening_ Model's
land use assumptions. The SR 900 Widening land use assumptions may be
adjusted; the CONSULTANT shalt notify the CITY if adjustments are applied to
the 2005 SE Bypass Model. The King County or PSRC Models may also be
referenced and used if applicable.
20.3.1.2. Land Use Assumptions For Transportation Modeling
Existing
Conditions Year 2000
The CONSULTANT shall summarize the
land use assumptions based on the CITY's Year 2000 Travel Model used for
concurrency testing.
Opening
Year 2005
Future year land use assumptions
shall be based on the Year 2005 SR 900 Widening Model and may be modified if
necessary. The CONSULTANT shall summarize (and update if necessary) the land
use assumptions for the Year 2005 SE Bypass Model.
The land use assumptions may differ from those used
for the Draft EIS, since those used in the 2005 SE Bypass model shall be based
on the more current information.
20.3.1.3. Model Network
Existing
Conditions Year 2000
For year 2000, one Model run (one
model run shall include both AM & PM traffic forecasts) shall be performed.
The PM peak hour generated trip tables from the 2000 SE Bypass model shall be
transposed and if necessary scaled to represent AM peak hour demand.
Additionally, the hourly volumes shall be balanced for the SE Bypass corridor.
The Model run shall
include:
·
2000 Model Run 1 - Year 2000
Existing_ Conditions: Year 1999
assumptions for land use shall be incorporated..
Opening
Year 2005
The transportation networks for
model year 2005 shall be developed from planned and programmed improvements to
be implemented by WSDOT, King County, and the City of Issaquah.
The CONSULTANT shall
review and revise the 2005 SE Bypass model network to provide continued
consistency with adopted Plans.
For year 2005, up to two
(2) model runs (one model run shall include both AM & PM traffic forecasts)
shall be performed. The PM peak hour generated trip tables from the 2005 SE
Bypass model shall be transposed and if necessary scaled to represent AM peak
hour demand. Additionally, the hourly volumes shall be balanced for the SE
Bypass corridor.
Each model run shall contain
different assumptions regarding programmed and planned roadway projects.
The Model runs include:
·
2005 Model Run 1-Year 2005 No
Action: Included shall be the following projects: North SPAR, South SPAR,
Sunset Interchange modification, and SR 900 widening. Baseline 2005
assumptions for land use shall be incorporated.
·
2005 Model Run 2 - Year 2005
Full Build. Included shall be the
following projects: NSPAR, SSPAR, Sunset, SR 900, and SE Bypass (with no
widening of SR 18)
20.3.1.4. Future Alternative Alignment Travel Demand Forecasts
Based on future land use
assumptions supplied by the CITY and on the definition of the roadway
alignment alternatives, year 2005 travel demand forecasts shall be prepared
using the traffic model. For the 2005 build scenario, the proposed build
alternative alignment (based on the work completed through Phase 1) shall be
considered.
Available output from TMODEL includes specific roadway
volumes, intersection volumes and select link data for the PM Peak hour. The
trip tables generated for the PM peak hour shall then be transposed and
possibly scaled in order to generate the AM Peak hour volumes. For the 2005
build scenario, the traffic information extracted from the 2005 build model
shall be applied to the recommended proposed design alignment alternative (as
determined in Phase 1).
PRODUCTS
The CONSULTANT shall provide the CITY a copy
of the TMODEL electronic files with a brief annotation for model year runs
2030, 2005, and 2000.
20.3.1.5. Modal Share Sensitivity
As part of development of the
2005 SE Bypass Model (No-Action and Build Scenarios), the CONSULTANT shall
prepare a summary of the various travel demand management assumptions
incorporated into the 2005 SE Bypass Model. Most travel demand management
assumptions shall be based primarily on the assumptions made in the SR 900
Widening model along with the CITY's Travel Model used for concurrency
testing, and possibly the PSRC model. The travel demand management assumptions
shall be presented in the SEIS.
20.3.1.6. Intersection/Roadway Operations
The CONSULTANT shall
conduct intersection/roadway operational analysis of key
intersections/roadways (see below). The Synchro software shall be utilized in
performing the traffic operational analyses. The operational analyses shall be
conducted for the AM and PM peak hours and intersection LOS along with
intersection delay (sec/veh) shall be recorded.
Year
2000 Existing Conditions and Year 2005
No Action
The CONSULTANT shall perform
intersection analysis for up to twenty-five (25) intersections as determined
by the CITY and CONSULTANT. The AM and PM peak hours shall be analyzed for
each intersection; the LOS and intersection delay shall be recorded.
The-intersections that shall be analyzed are (as-per agreement with the CITY):
·
SR 900 & NW Sammamish
·
SR 900 &.I-90 WB Ramps
·
SR 900 & EB Ramps
·
SR 900 & Gilman
·
SR 900 & Maple
·
E Sammamish & 56th
·
Issaquah-Fall City & E. Lk.
Sammamish
·
Front St. & WB Ramps
·
Front St. & EB Ramps
·
Front St & Gilman
·
Front St & Sunset
·
Issaquah-Fall City & Black Nugget
Rd
·
Issaquah-Fall City & Issaquah
Pine
·
Sunset & WB 1-90 Ramps
·
Sunset & EB 1-90 Ramps
·
E Sammamish & 43`d
·
Front Street & Clark
·
Front St & Dogwood – South
·
Front St & Dogwood – North
·
Sunset & Second
·
Front St & Second
·
SR 900 & Newport
·
E. Lake Sammamish & Black Nugget
·
Second Avenue SE & Bush Street
·
Issaquah-Hobart Rd & May Valley
Rd
Year
2005 Build
The proposed Build alternative as
determined in Phase 1 shall be analyzed for the year 2005. The proposed
roadway combination is defined as inclusion of one north alignment alternative
and the south alignment alternative. In terms of traffic operations, all three
North Alignments shall operate similarly; therefore, one roadway combination
(a north alignment and the south alignment) shall be analyzed. Up to four (4)
versions (or iterations) shall be conducted. A roadway combination version (or
iteration) may include:
·
Modifications to the number of
lanes assigned at a particular intersection or corridor
·
Modifications to design lengths
(this can be either storage lengths or distance between intersections)
The Synchro software shall be utilized in determining
corridor and intersection operations for the year 2005 build roadway
combination as well as the twenty-five (25) intersections as listed in the
"Year 2000 Existing Conditions and Year 2005 No Action" section (above).
Additionally, the year 2000 Existing Conditions and the year 2005 No Action
intersections as described above shall also be analyzed using the Synchro
software.
The CONSULTANT is assuming
that the preferred alternative may be constructed in two stages where Stage 1
involves construction of a two-lane roadway and Stage 2 involves widening the
initial two-lane facility to four lanes. For the Build Scenario, the
CONSULTANT shall determine the projected year in which traffic volumes
indicate that a four-lane roadway would be necessary in order to adequately
accommodate traffic demand on the SE Issaquah Bypass.
20.3.1.7. Mitigation Measures
Qualitative analyses shall be performed by the
CONSULTANT to identify and discuss the potential effectiveness of measures
designed to mitigate any significant adverse impacts of each of the
alternatives.
20.3.1.8. Draft Transportation Study
The CONSULTANT shall
prepare a Draft Transportation Study to document the results of the new
traffic modeling and analysis. The Draft Transportation Study shall build on
the analysis started under the Phase 1 Transportation Study. Ten (10) copies
of the Draft Study shall be provided for review and comments.
PRODUCTS
Draft Transportation Study for review by the City and other agencies (10
copies)
20.3.1.9. Final Transportation Study
Following review of the
Draft Transportation Study, the CONSULTANT shall revise the Draft
Transportation Study to incorporate review comments. Fifteen (15) copies of
the Final Transportation Study shall be provided.
PRODUCTS
Final Transportation Study (15 copies)
20.3.2. Biological Assessment
The CONSULTANT shall review and revise the Biological
Assessment (BA) prepared for the June 2000 Draft EIS. The BA shall be revised
to describe the impacts of the new alternatives on federally listed, proposed,
and candidate species and designated and proposed critical habitat present in
the project vicinity. The CONSULTANT shall submit 10 copies of the Preliminary
Revised Draft BA to the CITY for review and comment. The CONSULTANT shall
revise the document and provide ten (10) copies of the Revised Draft BA for
distribution with the Preliminary Supplemental Draft EIS to the USACE, USFWS,
EPA, NMFS, Ecology and WDFW.
PRODUCTS
·
Preliminary Revised Draft BA
(10 copies)
·
Revised Draft BA (10 copies)
20.3.3. Supplemental Draft EIS
The CONSULTANT shall
prepare a Supplemental Draft EIS to present new information on proposed
project alternatives and traffic analysis based on the outcome of the Phase I
work plan. The Supplemental Draft EIS shall follow a format consistent with
guidance in the revised WSDOT Environmental Procedures Manual (July
2001), guidance in the "Interagency Working Agreement to Integrate Special
Aquatic Resources (404) Permit Requirements into the NEPA and SEPA processes
in the State of Washington, (NEPA/SEPA/404 Merger Agreement), and FHWA
Technical Advisory T6640.8A. The CITY will provide close coordination with
WSDOT and FHWA throughout the process. The Supplemental Draft EIS is
anticipated to include the following sections and appendices (however, the
final organization and format may change in response to the CITY's needs):
20.3.3.1. Introductory Material
The following sections of
the June 2000 Draft EIS shall be revised, as appropriate:
·
Cover Sheet
·
Title Sheet
·
Fact Sheet
·
Table of Contents
·
List of Tables
·
List of Figures
20.3.3.2. Summary
The Summary section from the June 2000 Draft EIS shall
be revised to include a brief description of the proposed action, other
governmental agency's actions in the geographic area, a summary of
alternatives and options considered, summary of major environmental impacts
(in table format with proposed mitigation measures), areas of concern or
controversy, unresolved issues, list of required permits, and a list of other
actions required for the proposed project.
20.3.3.3. Chapter 1: Purpose and Need for the Action
This chapter shall be revised to identify and describe
the proposed action and the transportation problems or other needs the
proposed action is intended to address. This discussion shall clearly identify
the need for the project.
20.3.3.4. Chapter 2: Alternatives
This chapter shall be
revised to describe the process used to identify various alternatives, the
range of alternatives considered, and the alternatives that were eliminated
from further consideration. Chapter 2 shall include-the NEPA 404 Alternatives
Analysis and Aquatic Resource Avoidance Analysis consistent with the
requirements of the NEPA/SEPA/404 Merger Agreement. The analysis shall
describe alternatives considered but rejected (and reason why) including
efforts to minimize or avoid impacts to aquatic resources, and shall identify
a preferred alternative, if known. A table shall be included that compares the
various impacts of each alternative.
Alternatives to be
analyzed in the Supplemental Draft EIS include:
·
No Action (no-build) Alternative
·
Alternative 1 (North A with a new
south alignment)
·
Alternative 2 (North B with a new
south alignment)
·
Alternative 3 (North C with a new
south alignment)
A detailed description of
the alternatives selected for analysis in the Supplemental Draft EIS shall be
provided, together with updated information on estimated project costs and
construction timing. The description of the alternative design concepts shall
be in sufficient detail to allow identification of the specific
characteristics of each design concept to be evaluated. These characteristics
include roadway layout, intersection configurations, structural features, and
other roadway related facilities. Maps, alignment drawings, road sections,
cost estimates, a proposed construction schedule with milestones, and other
exhibits shall be used to describe and allow a comparison between the
alternatives.
20.3.3.5. Chapter 3: Affected Environment
This chapter shall be revised to update the
description of the existing social and environmental setting for the area
affected by the alternatives presented in the Supplemental Draft EIS. The
following elements of the environment shall be reviewed and updated as
necessary: study area, local geography, geology and soils, hydrologic systems
and floodplains, wetlands, fish and wildlife habitat, land use, regional and
community growth, historic and archaeological elements, hazardous waste, and
visual quality. It shall also discuss the adopted land use and transportation
plans as they relate to the proposed project, including the City's Traffic
Concurrency Ordinance. These discussions shall be limited to data,
information, issues, and values that will have a bearing on possible impacts,
mitigation measures, and on the selection of an alternative.
20.3.3.6. Chapter 4: Environmental Consequences
This chapter shall be
revised to document the direct project impacts, future operational impacts,
secondary and cumulative impacts, construction activity impacts and mitigation
measures associated with each of the three new build alternatives and the
no-action alternative.
Direct project
impacts are those impacts
associated with the footprint or right-of-way of each alternative.
Future operational
impacts are those impacts
resulting from ongoing operation of the project that are anticipated to
occur between the year of opening (2005)
and the design year (2030). _-‑
Secondary impacts
are those that are "caused by an
action and are later in time or farther removed in distance but are still
reasonably foreseeable" (40 CFR 1508.8). These impacts, which usually result
from the initial action, include changes in land use, water quality, economic
vitality, and population density.
Cumulative impacts are those that "result from the
incremental consequences of an action when added to other past and reasonable
foreseeable future actions" (40 CFR 1508.7). The cumulative effects of an
action may be undetectable when viewed in the individual context of direct and
even secondary impacts but can nonetheless add to other disturbances and
eventually lead to a measurable environmental change.
Construction
activity impacts are limited to
construction process impacts that are temporary in nature and typically
limited to the immediate project area (e.g., construction noise, dust, traffic
controls, etc.). The CONSULTANT is assuming that the preferred alternative
will be constructed in two stages: Stage 1 will involve construction of a
two-lane roadway; Stage 2 will involve widening the initial two-lane facility
to four lanes.
The environmental elements
listed below shall be reanalyzed for each of the alternatives addressed in the
Supplemental Draft EIS:
·
Air Quality
·
Noise
·
Energy
·
Geology and Soils
·
Hydrological Systems
·
Floodplains
·
Water Quality
·
Wetlands
·
Vegetation and Wildlife
·
Fisheries
·
Threatened and Endangered Species
·
Land Use
·
Social Elements
·
Economic Elements
·
Displacement and Relocation
·
Historic and Cultural Resources
·
Hazardous Waste
·
Visual Quality
The CONSULTANT shall
prepare draft and final technical reports for Air Quality and Noise only.
Draft technical reports shall be submitted to the CITY and the STATE for
review and comment. No additional revisions to previously prepared discipline
reports are included. Any other discipline report changes would be considered
"extra work."
The CONSULTANT shall not
perform floodplain modeling work (HEC-RAS) as part of this work plan.
Floodplain impact analysis and preliminary design for the SEIS alternatives
performed by the CONSULTANT shall be based on the recently updated
floodplain information (Montgomery Water Group, 2001) provided to the
CONSULTANT by the CITY. Any HEC-RAS analysis would be considered "extra
work".
PRODUCTS
·
Draft and Final Air Quality
Reports (10 copies each of Draft and Final)
·
Draft and Final Noise Reports
(15 copies each of Draft and Final)
20.3.3.7. Chapter 5: Comments and Coordination
The CONSULTANT shall update this chapter to summarize
the results of additional coordination with federal, state, and local
agencies, their level of involvement, and any unresolved issues or areas of
conflict. This section shall also include a summary of additional public
involvement activities conducted as part of the Supplemental Draft EIS.
20.3.3.8. Chapter 6: Section 4(f) Evaluation
The CONSULTANT shall update and revise the Section
4(f) evaluation to reflect the impacts (both during construction and
operation) associated with the new build alternatives. The CONSULTANT shall
identify and evaluate location and design alternatives which would avoid each
and all Section 4(0 properties; explain whether any avoidance alternatives
which were eliminated from further study are "feasible and prudent" and if
not, explain why; discuss all possible measures which are available to
minimize impacts on Section 4(f) properties, including commitments made and
monitoring procedures to minimize harm.
20.3.3.9. Response to Comments on
Draft EIS
The CONSULTANT shall review and prepare responses to
over 1,000 comments received on the Draft EIS in letters and recorded
testimony at the Draft EIS public hearing. It is assumed that many of the
comments received are similar in content and a response to one will be
appropriate for many others. It is also assumed that many of the comments will
no longer be relevant because several of the alternatives presented in the
Draft EIS are no longer being considered. Copies of the comment letters and
recorded public testimony, along with the responses to those comments, shall
be presented in an appendix to the Supplemental Draft EIS. During this task
the CONSULTANT shall also review one (1) "constituent proposal" and provide a
written response to be included in an appendix to the Supplemental Draft EIS.
20.3.3.10. Closing Sections/Appendices
The CONSULTANT shall
prepare closing documentation for the SETS, including the following
information:
·
Principal Contributors
·
Studies Performed
·
Supplemental Draft EIS
Distribution List
·
Transportation Studies
·
Supplemental Alternatives
Analysis
·
Historic Site Documentation
20.3.3.11. Preliminary Supplemental Draft EIS
The CONSULTANT shall
produce a preliminary Supplemental Draft EIS and submit ten (10) copies to the
CITY for review and comment. The CONSULTANT shall revise the document and
provide fifteen (15) copies of the preliminary Supplemental Draft EIS
(including the revised Wetland and Streams Technical Memorandum and Biological
Assessment) to the CITY for distribution to the USACE, USFWS, EPA, NMFS,
Ecology and WDFW.
PRODUCTS
·
Preliminary Supplemental Draft
EIS for CITY review (10 copies)
·
Preliminary Supplemental Draft
EIS for review by agencies (15 copies)
20.3.3.12. Camera-Ready Supplemental Draft EIS
The CITY will provide one consolidated set of comments
on the Preliminary Supplemental Draft EIS to the CONSULTANT. It is assumed
that agencies will submit comments separately. The CONSULTANT shall make
requested revisions and prepare a camera-ready Supplemental Draft EIS for
review by the CITY. The Supplemental Draft EIS shall include an initial
wetland mitigation plan if a preferred alternative is known, otherwise a
conceptual mitigation plan shall be included in the Supplemental Draft EIS.
PRODUCTS
Camera-ready copy of the Supplemental Draft EIS for CITY approval (1
copy).
20.3.3.13. Reproduction and Distribution
Upon approval of the camera-ready Supplemental Draft
EIS by the CITY, the CONSULTANT shall reproduce 200 copies of the final
Supplemental Draft EIS for distribution. The CITY will provide the
distribution list. The CITY will be responsible for distributing the document
to the agencies and the public.
PRODUCTS
200 copies of the Supplemental Draft EIS for submittal to the CITY for
distribution.
20.3.4. Public Hearing
A joint public hearing on the Supplemental
Draft EIS and the Section 404 permit application will be conducted
within-0-days following_ publication of the -Supplemental Draft EIS. The
CONSULTANT shall prepare materials for the hearing and provide originals to
the CITY for reproduction and distribution. Relevant CONSULTANT activities
shall include:
·
Assist the CITY in preparing the
public hearing packet
·
Assist the CITY in preparing up
to ten (10) graphic display boards • Develop a Synchro demonstration showing
future traffic operations • Provide technical staff to attend the Public
Hearing
It is assumed that up to four (4) CONSULTANT
team staff shall attend the public hearing.. It is also assumed that the CITY
will be responsible for arranging the meeting place, arranging for a court
reporter, preparing the public notice for the joint Supplemental Draft EIS/Section
404 Public Hearing Notice, and all other activities related to meeting
organization and/or preparation.
20.3.5. Final EIS
20.3.5.1. Respond to Comments on the Supplemental Draft EIS
The CITY will provide the CONSULTANT with copies of
the letters received with comments on the Supplemental Draft EIS. The CITY
will also provide the CONSULTANT with a copy of the transcript recording
public testimony received at the public hearing. Revisions to the Supplemental
Draft EIS shall be based on the comment letters, public hearing testimony and
agency comments received during the review period.
The CONSULTANT shall
compile a summary of comments received on the Supplemental Draft EIS, provide
responses to comments, and make recommendations, if necessary, on the need for
additional studies, additional mitigation or changes to the design. For
budgeting purposes, it is assumed that there will be a maximum of 100 comment
letters with 10 comments each for a total of 1,000 comments. If there are more
than 100 comment letters or 1,000 comments, the extra level of effort to
address comments shall be considered "extra work."
20.3.5.2. Revise Environmental Analysis
The CONSULTANT shall
revise the discussion of elements of the environment in the EIS to reflect
changes in the project design, impacts, and proposed or required mitigation
that have occurred since publication of the Supplemental Draft EIS, or in
response to review comments on the Supplemental Draft EIS. Any proposed
additional studies, detailed analyses, or changes in design shall be
considered "extra work."
20.3.5.3. Preliminary Final EIS Document
The CONSULTANT shall
produce a preliminary Final EIS and submit ten (10) copies to the CITY for
review and comment. The CONSULTANT shall revise the document and provide
fifteen (15) copies of the preliminary Final EIS (including the final
alternatives analysis, identification of the preferred alternative and
apparent least environmentally damaging practicable alternative, and apparent
final wetland mitigation plan) to the CITY for distribution to the USACE,
USFWS, EPA, NMFS, Ecology and WDFW. The Final EIS shall incorporate changes
that reflect changes in the project scope, impacts,---technical analysis and
mitigation analysis that have occurred since the Supplemental Draft EIS. The
Final EIS shall include comments received on the Supplemental Draft EIS, a
summary of the comments, responses to comments, and an updated fact sheet.
PRODUCTS
·
Preliminary Final EIS for CITY review (10 copies)
·
Preliminary Final EIS for
review by agencies (15 copies)
20.3.5.4. Camera-Ready Final EIS
The CITY will provide one consolidated set of comments
on the preliminary Final EIS to the CONSULTANT. It is assumed that reviewing
agencies will submit comments to the CITY separately. The CONSULTANT shall
revise the preliminary Final EIS in response to the comments received from the
CITY and reviewing agencies. The CONSULTANT shall prepare a camera-ready Final
EIS and the CITY will conduct a second review to check and approve the changes
and authorize reproduction and issuance of the Final EIS.
PRODUCTS
Camera-ready copy of the Final EIS for City approval (1 copy)
20.3.5.5. Reproduction and Distribution
The CONSULTANT shall make
the second round of minor revisions based on the review and approval of the
camera-ready Final EIS and reproduce 200 copies of the Final EIS for
distribution. The CITY will provide the distribution list for the Final EIS.
The CITY will be responsible for distributing the document to agencies and the
public.
PRODUCTS
200 copies of the Final EIS for submittal to the CITY for distribution.
20.3.6. Record of Decision
The CONSULTANT shall
assist the CITY in preparing the draft NEPA Record of Decision (ROD) and shall
address any Final EIS comments received from FHWA.
PRODUCTS
·
Draft Record of Decision (1
copy)
·
Final Record of Decision (1
copy)
20.3.7. Respond to
Miscellaneous Public Comments
If directed by the CITY,
the CONSULTANT shall prepare responses to public comments on deliverables
prepared under this work plan. It is assumed that the CONSULTANT shall spend
four (4) hours responding to up to ten (10) public comments. Additional effort
by the CONSULTANT to respond to more than ten (10) comments shall be
considered "extra work".
20.4. NEPA/SEPA/404 MERGER ACTIVITIES
The CONSULTANT shall
provide project coordination to comply with the "Interagency Working Agreement
to Integrate Special Aquatic Resources (404) Permit Requirements into the NEPA
and SEPA processes in the State of Washington," (NEPA/SEPA/404 Merger
Agreement).
20.4.1. NEPA/SEPA/404 Merger Concurrence
The CONSULTANT shall
coordinate with regulatory agencies to gain concurrence on the preliminary
Supplemental Draft EIS regarding project alternatives to be evaluated in the
Supplemental Draft EIS, preliminary preferred alternative, and initial and
detailed wetland mitigation plans. The CONSULTANT shall coordinate project
team attendance at meetings with the regulatory agencies and document the
discussions and decisions in the form of written meeting notes. Additional
studies required to obtain concurrence from the regulatory agencies, including
development and analysis of additional alternatives (or variations thereof),
shall be considered "extra work." Note: Preparation of the final
version of the Supplemental Draft EIS cannot proceed without issuance of a
letter of concurrence from the 404 Merger agencies on the project alternatives
to be evaluated in the Supplemental Draft EIS.
One (1) CONSULTANT staff
person shall attend up to two (2) meetings with 404 Merger agencies to gain
concurrence on the project alternatives to be evaluated in the Supplemental
Draft EIS and to gain concurrence on the apparent final mitigation plan and
preferred alternativeAeast environmentally damaging alternative to be included
in the preliminary Final EIS. Additional meetings, studies or revisions to
alternatives that may be needed to obtain concurrence shall be considered
"extra work." Note: Publication of the Final EIS cannot occur without
issuance of a letter of concurrence from the 404 Merger agencies on the
preferred alternative/least environmentally damaging alternative.
20.4.2. Initial Mitigation Plan
Upon issuance of the
Agency Concurrence Letter regarding alternatives to be evaluated in the
Supplemental Draft EIS and identification of the preferred alternative, the
CONSULTANT shall conduct a preliminary investigation of candidate mitigation
sites to determine if there are suitable sites to support the required
mitigation. Upon identification of candidate sites, the CONSULTANT shall
prepare a draft Initial Mitigation Plan for the preferred alternative, as
described in Appendix F of the NEPA/SEPA/404 Merger Agreement. The Draft Plan
shall identify unavoidable impacts to aquatic resources; establish the goals
and objectives of the mitigation; the timing of the mitigation; a general
description of the candidate sites; and proposed monitoring of the mitigation.
The Draft Plan shall be submitted to the CITY for review and comment.
The Draft Initial
Mitigation Plan shall be revised to address the CITY's comments. The revised
Plan shall be submitted to the CITY for distribution to other 404 Merger
agencies for review and comment. The CITY will provide consolidated comments
on the Plan to the CONSULTANT. The CONSULTANT shall conduct a site visit with
the USACE to review candidate sites. The CONSULTANT shall prepare a final
Initial Mitigation Plan for inclusion in the Draft Supplemental EIS.
PRODUCTS
·
Draft Initial Wetlands
Mitigation Plan for CITY review (10 copies)
·
Draft Initial Wetlands
Mitigation Plan for agency review (15 copies)
·
Final Initial Wetlands
Mitigation Plan for inclusion in the Supplemental Draft EIS (one camera
ready copy)
20.4.3. Section 404 Permit
Application
Prior to submittal of the Preliminary Supplemental
Draft EIS, two (2) members of the CONSULTANT team shall attend one (1)
pre-application meeting with the USACE to identify issues of concern and
confirm Section 404 permitting requirements and scheduling. The CONSULTANT
shall then prepare draft Section 404 permit application materials for
submittal to the CITY. The CITY will submit the permit application to the
USACE. Prior to publication of the Final EIS, the CONSULTANT shall prepare a
final Section 404 permit application for submittal to the USACE. The final
application shall include a Detailed Mitigation Plan and Report.
PRODUCTS
·
Draft Section 404 Wetland
Permit Application
·
Final Section 404 Wetland
Permit Application
20.4.4. Detailed Mitigation
Plan and Report
Prior to publication of
the Final EIS, the CONSULTANT shall prepare a draft Detailed Mitigation Plan
and Report for the preferred alternative, as described in Appendix F of the
NEPA/SEPA/404 Merger Agreement. The Draft Detailed Mitigation Plan shall
include a summary of wetland impacts, description of proposed mitigation and
mitigation site(s), mitigation design (hydrology source, grading plan, soil
preparation, planting plan, and schedule), standards of success, and
monitoring and contingency plans. The Draft --Plan shall be submitted to the
CITY for review and comment. The Draft Plan shall be revised to address the
CITY's comments. The revised Plan shall be submitted to the CITY for
distribution to the 404 Merger agencies with the preliminary Final EIS.
Upon issuance of
concurrence on the preliminary Final EIS by the reviewing agencies, the
CONSULTANT shall prepare a Final Detailed Mitigation Plan for inclusion in the
Final EIS. Because the level of effort for the Final Wetland Mitigation Plan
is not known at this time, preparation of a Final Mitigation Plan is not
included in this work plan. Preparation of a Final Mitigation Plan shall be
considered °extra work". Note: The Final Wetland Mitigation Plan is
normally completed after the Detailed Mitigation Plan has been
circulated to the 404 Merger agencies. It incorporates comments from
agencies and the public (and commitments made in the Final EIS). The Final
Wetland Mitigation Plan is the document of record for the Section 404 permit.
The final plan must be approved by Ecology, WDFW, and the COE.
PRODUCTS
·
Preliminary Draft Detailed
Wetland Mitigation Plan and Report (10 copies)
·
Draft Detailed Wetland
Mitigation Plan and Report (15 copies)
·
Final Detailed Wetland
Mitigation Plan and Report (one camera ready copy)
20.5. PRELIMINARY DESIGN
20.5.1 Supplemental Survey
and Mapping
The CONSULTANT shall collect additional field survey
to update the existing mapping that will enable development of the preliminary
design to the level necessary to provide a clear idea of the environmental
impacts. Except for critical culverts, underground utilities shall not be
surveyed or mapped. The CONSULTANT shall update the existing base map with the
additional supplemental survey data. This supplemental survey data shall be
developed in metric units. The survey work shall conform to NAND 83/91 and to
the vertical datum used by the CITY for this project.
PRODUCTS
Updated Aerial Base Mapping
20.5.2 Geotechnical
Feasibility Memorandum
The CONSULTANT shall
investigate existing geotechnical conditions in the study area to support the
preliminary design task. These investigations include review of geotechnical
data gathered previously by the CONSULTANT team and a visual site inspection
of the new southern alignment to evaluate existing conditions. The CONSULTANT
shall also conduct a visual site inspection along the three northern
alignments to observe current site conditions. The CONSULTANT shall prepare a
draft and final Geotechnical Feasibility Memorandum that identifies
preliminary slope support options including, but not limited to, mechanically
stabilized earth (MSE) walls, soldier pile walls, reinforced concrete walls,
and rockeries. No soil borings are included in this work plan. Any additional
geotechnical investigations beyond those described in this work plan shall be
considered "extra work".
PRODUCTS
·
Draft Geotechnical Feasibility
Memorandum (3 copies)
·
Final Geotechnical Feasibility
Memorandum (3 copies)
20.5.3 Design Memorandum
A Design Memorandum
summarizing the relevant geometric design criteria applicable to CITY
designated design or posted speed limits shall be prepared based on applicable
design standards and in accordance with the CITY'S Design Standards and the
WSDOT Local Agency Guidelines Manual, as well as the AASHTO Green Book (See
Attachment A). Particular emphasis shall be placed on identifying those
elements that may be subject to interpretation, engineering judgment or
modification due to adverse field conditions. The CONSULTANT shall review the
design elements with and seek approval by the CITY.
The Design Memorandum shall include documentation on
design decisions, design deviations, geotechnical and structural evaluations,
stormwater management issues and considerations, and a staged construction
proposal.
PRODUCTS
·
Draft Design Memorandum (3
copies)
·
Final Design Memorandum (3
copies)
20.5.4 Modify Alignments North A and North B
The CONSULTANT shall
continue to modify the design of alignments North A and North B; work
initiated during Phase 1 (Task 19.3.2 in Task Order No. 8). For EIS purposes,
the three north alignments (North A, North B and North C) can be matched with
the new south alignment (South C) to yield three different EIS alternatives
The CONSULTANT shall
refine the roadway template and channelization features for North A and North
B to reflect the traffic needs for the year 2030 (see Phase 1 Transportation
Study, Task 19.3.1, Task Order No. 8). Other design elements to be refined
shall include retaining wall locations and stormwater facilities, cross
sections, and slope lines. The CONSULTANT shall develop one (1) Typical
Section for alignment North A and one (1) Typical Section for alignment North
B.
If a revision in the
horizontal and vertical alignment of the planned East Sunset Way connection to
the SE Issaquah Bypass is required because of refinements to the SE Bypass
design, that effort shall be considered "extra work" and will be
covered by a future change order.
PRODUCTS
·
Plans, profiles and typical
sections for alignments North A and North B. Three (3) sets of 11 x 17
design drawings shall be provided.
20.5.5. Modify Alignment South
C
The CONSULTANT shall modify the preliminary design of
alignment South C completed during Phase 1 (Task 19.3.2 in Task Order No. 8)
to account for new floodplain elevation information provided to the CONSULTANT
by the CITY (Montgomery Water Group, 2001). If necessary, the CONSULTANT shall
refine the roadway template, including retaining walls and stormwater
facilities, develop new cross sections, and refine slope lines to allow
determination of potential impacts to wetlands, streams, floodplains, trails,
existing homes, school district property and other elements of the
environment. The CONSULTANT shall develop one (1) Typical Section to depict
the roadway prism for the South C alignment.
PRODUCTS
·
Plans, profiles and typical
sections for alignment South C. Three (3) sets of 11 x 17 design drawings
shall be provided.
20.5.6 Refine Preferred
Alternative
The CONSULTANT shall revise the horizontal and
vertical alignment of the Preferred Alternative (one iteration) in response to
comments received on the Supplemental Draft EIS. The CONSULTANT shall rerun
cross sections throughout the length of the vertical alignment revision and
revise slope lines to further determine their impact on the environment. The
design for the Preferred Alternative shall accommodate existing and proposed
pedestrian and bicycle facilities within the corridor, as well as appropriate
connections and extensions of existing trails. Type II bicycle lanes and
contiguous sidewalks are to be assumed.
The CONSULTANT shall
coordinate with Issaquah School District officials to identify appropriate and
reasonable vertical alignments for the Preferred Alternative (including
possible noise berm) to address school district concerns over potential noise
impacts to Issaquah High School. One (1) meeting with three (3) people is
assumed for budgetary purposes.
PRODUCTS
·
Plans, profiles and typical
sections for the Preferred Alternative. Three (3) sets of 11 x 17 drawings
shall be provided.
20.5.7 Project Staging Description
It is anticipated that the
construction sequencing of the preferred alternative will occur in two
separate stages. The CONSULTANT shall prepare a narrative description of Stage
1 construction for a two-lane roadway with bike lanes in each direction and a
sidewalk on the southbound side only. Up to three (3) Typical Sections
shall be prepared depicting the two-lane roadway. It is assumed that the Stage
1 stormwater system would be generally the same as for the ultimate build out,
except that instead of a catch basin conveyance system, Phase 1 would use
roadside ditches. Retaining walls would be located to accommodate the ultimate
build-out of a four-lane roadway section. It is assumed that proposed
right-of-way acquisition would be sufficient to accommodate the ultimate
build-out of a four-lane roadway section.
PRODUCTS
Narrative Description of Stage 1 Construction, including three (3)
Typical Sections (3 sets of 11 x 17 drawings) shall be provided.
20.5.8 Cost Estimates
The CONSULTANT shall
prepare a preliminary cost estimate for each of the SEIS build alternatives.
Costs shall be based on standard bid item tables published by WSDOT and the
CITY. The CITY will provide estimated right-of-way costs based upon
right-of-way requirements identified by the CONSULTANT. A cost estimate for
Stage 1 (two-lane roadway) construction of the Preferred Alternative would be
considered °extra work".
PRODUCT
Preliminary cost estimates for SETS Build Alternatives (3 sets)
20.6. 6th AVENUE SE ALIGNMENT
The CONSULTANT shall
conduct additional transportation and environmental analysis and preliminary
design activities to include an additional southern alignment in the
Supplemental EIS. The additional southern alignment is assumed to
approximately follow the existing alignment of 6th Avenue
SE.
20.6.1. Transportation Study
The CONSULTANT shall
perform transportation analysis for an additional southern alignment that
would follow the centerline of existing 6th Avenue SE and
intersect with Issaquah-Hobart Road at approximately SE 96th
Street. The analysis shall include an additional run of the TMODEL travel
demand forecast for the 2030 build scenario and additional Synchro
intersection/roadway analysis for up to one alignment combination (i.e. the 6th
Avenue SE alignment with one north alignment). In addition, the
transportation analysis described in Task 20.3.1 of this work plan shall be
expanded to include analysis of the additional alternative for the opening
year of 2005.
20.6.2. Supplemental Draft EIS
The CONSULTANT shall
expand the discussion and analysis in the Supplemental Draft EIS to include an
additional southern alignment that follows the existing centerline of 6th
Avenue SE. The following sections of the EIS document shall be revised to
discuss the additional alternative:
·
Summary
·
Chapter 1 Purpose and Need for
the Action
·
Chapter 2 Alternatives
·
Chapter 3 Affected Environment
·
Chapter 4 Environmental
Consequences
·
Chapter 5 Comments and
Coordination
·
Chapter 6 Section 4(f) Evaluation
The impact analysis in the
Supplemental Draft EIS addressing the environmental elements listed-below
shall be expanded to include analysis of the additional southern alignment
that follows 6th Avenue SE:
·
Air Quality
·
Noise
·
Energy
·
Geology and Soils
·
Hydrological Systems
·
Floodplains
·
Water Quality
·
Wetlands
·
Vegetation and Wildlife
·
Fisheries
·
Threatened and Endangered Species
·
Land Use
·
Social Elements
·
Economic Elements
·
Displacement and Relocation
·
Historic and Cultural Resources
·
Hazardous Waste
·
Visual Quality
The Air Quality and Noise modeling efforts and related
technical reports shall be expanded to include the additional southern
alignment.
20.6.3. Final EIS
The CONSULTANT shall
address public and agency comments received on the Supplemental Draft EIS
related to the additional southern alternative. For budgeting purposes it is
assumed that the addition of the 6th Avenue southern alignment will
add approximately 25% to the level of effort assumed for this task in
20.3.6.1. The CONSULTANT shall revise the discussion of elements of the
environment in the EIS to reflect any changes in the project design, impacts
and proposed or required mitigation, as they relate to the additional
alternative.
20.6.4. NEPA/SEPA/404 Merger Activities
The CONSULTANT shall
coordinate with regulatory agencies to review and comment on the additional
southern alignment along 6'h Avenue SE. Additional studies required
to obtain concurrence from the regulatory agencies, or development and
analysis of additional alternatives, shall be considered "extra work."
One (1) CONSULTANT staff
person shall attend up to one (1) additional meeting with regulatory agencies
to gain concurrence on the preliminary Final EIS regarding the apparent final
mitigation plan and the preferred alternative/least environmentally damaging
alternative, as specified in the NEPA/SEPA/404 Merger Agreement. Additional
meetings, studies or revisions to alternatives that may be needed to obtain
concurrence shall be considered "extra work."
20.6.5. Preliminary Design
The CONSULTANT shall
supplement the preliminary design work described in Task 20.5 of this work
plan to include preliminary design of an additional 6t' Avenue SE
alignment. The 6'h Avenue SE alignment shall be designed to match
with any one of the three northern alignments (North A, North B, or North C)
to yield three different EIS alternatives. During this task the CONSULTANT
shall develop preliminary plan, profile, and typical section for an alignment
that reflects the traffic channelization needs for the year 2030.
Other design elements
shall include retaining walls and stormwater facilities, cross sections, and
slope lines. The CONSULTANT shall develop one (1) Typical Section for the 6`h
Avenue alignment.
PRODUCTS
·
Plan, profile and typical
section identifying the proposed project design for the additional southern
alignment shall be provided. Three (3) sets of drawings shall be provided.
20.6.6. Cost Estimate
The CONSULTANT shall
revise the preliminary cost estimates described in Task 20.5.5 to include the
additional 6t' Avenue alignment. Costs shall be based on standard
bid item tables published by WSDOT and the CITY. The CITY will provide
estimated right-of-way costs based upon right-of-way requirements identified
by the CONSULTANT.
ATTACHMENT A - DESIGN GUIDELINES
The CITY will designate the basic premises and
criteria for the design. Reports and plans, to the extent feasible, shall be
developed in accordance with the latest edition and amendments to the
following:
City of Issaquah Publications
·
Issaquah Design Standards
·
Critical Areas Ordinance
King County Publications
·
Road Standards 1994
·
General Special Provisions 1991
·
Surface Water Design Manual
·
Community Plan
·
Basin Studies
·
Sensitive Areas Ordinance
Washington State Publications
·
Standard Specifications for Road,
Bridge, and Municipal Construction (M41-10)
·
Standard Plans for Road, Bridge,
and Municipal Construction (M21-01)
·
Amendments and General Special
Provisions
·
Standard Item Table
·
Highway Design Manual
·
Bridge Design Manual
·
Construction Manual
·
Local Agency Guidelines
·
DOE Stormwater Management Manual
for the Puget Sound Basin
·
Hydraulics Manual
American Association of State Highway and Transportation Officials
Publications
·
A Policy on Geometric Design of
Highways and Streets (2000)
·
A Policy on Geometric Design of
Highways and Streets (1994) (Green Book)
·
Standard_ Specifications for
Highways Bridges, Twelfth Edition (1977)
·
A Guide for Highway Landscape and
Environmental Design (1970)
·
Highway Design and Operational
Practices Related to Highway Safety (1974) (Yellow Book)
·
Any American Association of STATE
Highway Officials policy applicable where said policy is not in conflict with
CITY standards
U.S. Department of Transportation Publications
·
Manual on Uniform Traffic
Control Devices for Streets and Highways
Other Publications
·
National Electrical Code
·
Transportation Research Board
Highway Capacity Manual (1994)
Change Order #11
Phase 2
Southeast Issaquah Bypass
Supplemental Environmental
Impact Statement
and Preliminary
Engineering Design
Change Order No. 11
June 5, 2003
INTRODUCTION AND ASSUMPTIONS
This work plan describes
additional Phase 2 activities for the Southeast Issaquah Bypass project. Phase
2 activities described herein build on work completed during Phase 1 (Change
Orders No. 8 and 9) and continuing during Phase 2 (Change Orders No. 10 and
11).
The
following tasks shall be performed as part of Change Order 11:
·
Update Project Management Plan
·
Prepare up to twenty (20) additional progress reports and billings
·
Conduct up to ten (10) additional EIS team coordination meetings
·
Participate in up to ten (10) additional coordination meetings
with the CITY, WSDOT and FHWA.
·
QA/QC major project deliverables
·
Revise March 2003 Draft Transportation Study
·
Revise March 2003 Draft Biological Assessment
·
Revise March 2003 Preliminary Supplemental Draft EIS in response
to additional review cycles by the CITY, WSDOT and FHWA.
·
Participate in one (1) additional briefing of the Signatory Agency
Committee
20.1.1.
Project Management Plan
The
CONSULTANT shall update the
project management plan to incorporate staffing changes, changes in deliverables
or other updates required by this work plan.
20.1.2.
Monthly Billings, Progress Reports and Schedule Updates
The
CONSULTANT shall prepare up to
twenty (20) additional monthly progress reports describing the status of the
project. These reports shall continue to report the following:
·
Significant
accomplishments
·
Potential
problem areas needing special attention or coordination
·
Actual work
progress compared with contractual obligations on a task by task basis
Billings shall continue to
be prepared by the CONSULTANT and submitted on a monthly basis. The CONSULTANT
shall monitor project progress and provide up to ten (10) MS Project schedule
updates.
PRODUCTS
·
Monthly Progress Reports and Monthly Billings (up to 20 assumed)
-
Updated MS Project
Schedule (up to 10 assumed)
20.1.3.
Direction, Meetings, and Coordination
20.1.3.1.
Team Coordination/General Direction
Periodic team coordination meetings shall be held to direct team efforts and
facilitate completion of project tasks identified in this work plan. This task
assumes up to ten (10) one-hour meetings attended by up to five 5 PB staff.
20.1.3.2.
Coordination Meetings
The
CONSULTANT shall attend up to ten (10) coordination meetings with Issaquah
staff, WSDOT and FHWA to review progress and discuss upcoming actions. Up to
two (2) CONSULTANT staff are assumed to attend each meeting. The meetings shall
be held at the CONSULTANT’S Seattle office or other location agreed to by all
parties. The CONSULTANT shall prepare meeting notes and action items following
each meeting.
20.1.3.3.
Coordination with Public Involvement Consultant
No
change.
20.2.
QUALITY
CONTROL
20.2.1.
Quality Assurance
Project deliverables shall
be reviewed by CONSULTANT team staff with expertise in the appropriate
discipline areas. This task also includes CONSULTANT team effort to review work
products prepared by SUBCONSULTANTS. This shall be an ongoing activity during
the duration of the project.
20.3.
Supplemental EIS
20.3.1.
Transportation Study
20.3.1.1.
Traffic Model Refinement
No change.
20.3.1.2.
Land Use Assumptions For Transportation Modeling
No change.
20.3.1.3.
Model Network
No change.
20.3.1.4.
Future Alternative Alignment Travel Demand Forecasts
No change.
20.3.1.5.
Modal Share Sensitivity
No change.
20.3.1.6.
Intersection/Roadway Operations
No change.
20.3.1.7.
Mitigation Measures
No change.
20.3.1.8.
Draft Transportation Study
No change.
20.3.1.9.
Final Transportation Study
The CONSULTANT shall revise
the March 2003 Draft Transportation Study following review by the CITY, WSDOT,
FHWA, Signatory Agency Committee (SAC) representatives and other resource
agencies. Fifteen (15) copies of the Final Transportation Study shall be
provided. Additional traffic modeling required to address comments on the Draft
or Final Transportation Study shall be considered Extra Work.
PRODUCTS
Final Transportation Study
(15 copies)
20.3.2.
Biological Assessment
The CONSULTANT shall revise
the Draft Biological Assessment prepared in March 2003 to address comments
received by WSDOT technical reviewers. The CONSULTANT shall submit five (5)
revised copies of the BA to WSDOT for distribution to FHWA, NMFS and USFWS. The
CONSULTANT shall revise the document in response to agency comments and submit
five (5) final copies of the BA for distribution to WSDOT, FHWA, NMFS and USFWS.
PRODUCTS
·
Revised Draft BA (5 copies)
·
Revised
Draft BA (5 copies)
20.3.3.
Supplemental Draft EIS
The
CONSULTANT shall prepare a Supplemental Draft EIS to present new information on
proposed project alternatives and traffic analysis based on the outcome of the
Phase I work plan. The Supplemental Draft EIS shall follow a format consistent
with guidance in the revised WSDOT Environmental Procedures Manual (July
2001), guidance in the “Interagency Working Agreement to Integrate Special
Aquatic Resources (404) Permit Requirements into the NEPA and SEPA processes in
the State of Washington,” (NEPA/SEPA/404 Merger Agreement), and FHWA
Technical Advisory T6640.8A. The CITY will provide close coordination with
WSDOT and FHWA throughout the process. The Supplemental Draft EIS is
anticipated to include the following sections and appendices (however, the final
organization and format may change in response to the CITY’s needs):
20.3.3.1.
Introductory Material
No change.
20.3.3.2.
Summary
No change.
20.3.3.3.
Chapter 1: Purpose and Need for the Action
No change.
20.3.3.4.
Chapter 2: Alternatives
No change.
20.3.3.5.
Chapter 3: Affected Environment
No change.
20.3.3.6.
Chapter 4: Environmental Consequences
No change.
20.3.3.7.
Chapter 5: Comments and Coordination
No change.
20.3.3.8.
Chapter 6: Section 4(f) Evaluation
No change.
20.3.3.9.
Response to Comments on Draft EIS
No change.
20.3.3.10.
Closing Sections/Appendices
No change.
20.3.3.11.
Preliminary Supplemental Draft EIS
The CONSULTANT shall revise
the March 2003 Preliminary Supplemental Draft EIS (Interoffice Working Version
#1) and supporting discipline reports to respond to cursory review comments
received from WSDOT and FHWA in April 2003, and technical review comments
received from WSDOT at the end of May 2003. The CONSULTANT shall take the lead
on resolving outstanding issues with the following agencies:
·
Interagency for Outdoor Recreation (IAC) to address issues related
to impacts on the Sportsmen’s Club
·
WSDOT and FHWA to address needed revisions to the Section 4(f)
Evaluation
·
WSDOT and SHPO to address impacts to the Sportsmen’s Club and
other Section 4(f) resources.
Twenty-five (25) copies of
the revised Preliminary Supplemental Draft EIS (Interoffice Working Version #1)
shall be submitted to WSDOT and CITY for review and comment. The CONSULTANT
shall revise the documents and submit two (2) copies to WSDOT for distribution
to FHWA. The CONSULTANT shall revise the documents in response to FHWA comments
and submit twenty-five (25) copies of the revised Preliminary Supplemental Draft
EIS to WSDOT for distribution to FHWA, Signatory Agency Committee (SAC)
representatives, and technical reviewers at USACE, USFWS, EPA, NMFS, Ecology and
WDFW.
PRODUCTS
-
Revised Preliminary
Supplemental Draft EIS for CITY and WSDOT review (25 copies)
·
Revised
Preliminary Supplemental Draft EIS for FHWA review (2 copies)
-
Revised Preliminary
Supplemental Draft EIS for distribution to FHWA, SAC agencies and federal
and state agency technical reviewers (25 copies)
-
Revised Preliminary
Supplemental Draft EIS for distribution to WSDOT and the CITY (5 copies)
20.3.3.12.
Camera-Ready Supplemental Draft EIS
The CONSULTANT shall meet
with the CITY, WSDOT and FHWA to review comments received on the Preliminary
Supplemental Draft EIS and to develop a strategy for proceeding with final
revisions. This work plan assumes the CONSULTANT will need to respond to a
limited number of comments that can be addressed with approximately 120 hours of
total labor. If additional hours are required, that effort would be considered
Extra Work. The CONSULTANT shall prepare a camera-ready version of the
Supplemental Draft EIS for review by the CITY, WSDOT and FHWA.
PRODUCTS
Camera-ready copy of the Supplemental Draft EIS (3 copies)
20.3.3.13.
Reproduction and Distribution
Upon approval of the
camera-ready Supplemental Draft EIS by FHWA, the CONSULTANT shall reproduce 200
copies of the Supplemental Draft EIS for distribution. The CITY will develop
the distribution list and be responsible for distributing the document to the
agencies and the public.
PRODUCTS
200 copies of the Supplemental Draft EIS for submittal to the CITY for
distribution.
20.3.4.
Public Hearing
No change.
20.3.5.
Final EIS
20.3.5.1.
Respond to Comments on the Supplemental Draft EIS
No
change.
20.3.5.2.
Revise Environmental Analysis
No
change.
20.3.5.3.
Preliminary Final EIS Document
The CONSULTANT shall
produce a preliminary Final EIS and submit twenty-five (25) copies to WSDOT and
the CITY for review and comment. The CONSULTANT shall revise the documents and
submit two (2) copies to WSDOT for distribution to FHWA. The CONSULTANT shall
revise the document in response to FHWA comments and provide twenty-five (25)
copies of the preliminary Final EIS to WSDOT for distribution to FHWA, SAC
representatives, and technical reviewers at USACE, USFWS, EPA, NMFS, Ecology and
WDFW.
PRODUCTS
-
Preliminary Final EIS
for CITY and WSDOT review (25 copies)
·
Preliminary
Final EIS for FHWA review (2 copies)
-
Preliminary Final EIS
for distribution to FHWA, SAC agencies and federal and state agency
technical reviewers (25 copies)
-
Preliminary Final EIS
for distribution to WSDOT and the CITY (5 copies)
20.3.5.4.
Camera-Ready Final EIS
The
CONSULTANT shall revise the preliminary Final EIS in response to the comments
received from the CITY, WSDOT, FHWA and reviewing agencies. The CONSULTANT
shall prepare a camera-ready Final EIS and the CITY will coordinate with WSDOT
and FHWA on a second review to check and approve the changes and authorize
reproduction and issuance of the Final EIS.
PRODUCTS
Camera-ready copy of the Final EIS (3 copies)
20.3.5.5.
Reproduction and Distribution
The CONSULTANT shall make
the second round of minor revisions based on the review and approval of the
camera-ready Final EIS and reproduce 200 copies of the Final EIS for
distribution. The CITY will provide the distribution list and be responsible
for distributing the document to agencies and the public.
PRODUCTS
200 copies of the Final EIS for submittal to the CITY for distribution.
20.3.6.
Record of Decision
No change.
20.3.7.
Respond to Miscellaneous Public Comments
No change.
20.4.
NEPA/SEPA/404 MERGER ACTIVITIES
The CONSULTANT shall
provide project coordination to comply with the “Interagency Working
Agreement to Integrate Special Aquatic Resources (404) Permit Requirements into
the NEPA and SEPA processes in the State of Washington,” (NEPA/SEPA/404
Merger Agreement).
20.4.1.
NEPA/SEPA/404 Merger Concurrence
Up to two (2) CONSULTANT
team members shall attend a SAC briefing before or during the agency review
period for the Preliminary Supplemental DEIS.
20.4.2.
Initial Mitigation Plan
No change.
20.4.3.
Section 404 Permit Application
No change.
20.4.4.
Detailed Mitigation Plan and Report
No
change.
20.5.1
Supplemental Survey and Mapping
No change.
20.5.2
Geotechnical Feasibility Memorandum
No change.
20.5.3
Design Memorandum
No change.
20.5.4
Modify Alignments North A and North B
No change.
20.5.5
Modify Alignment South C
No change.
20.5.6
Refine Preferred Alternative
No change.
20.5.7
Project Staging Description
No change.
20.5.8
Cost Estimates
No change.
20.6.
6th Avenue SE Alignment
The
CONSULTANT shall conduct additional transportation and environmental analysis
and preliminary design activities to include an additional southern alignment in
the Supplemental EIS. The additional southern alignment is assumed to
approximately follow the existing alignment of 6th Avenue SE.
20.6.1.
Transportation Study
No change.
20.6.2.
Supplemental Draft EIS
No change.
20.6.3.
Final EIS
No change.
20.6.4.
NEPA/SEPA/404 Merger Activities
No change.
20.6.5.
Preliminary Design
No change.
20.6.6.
Cost Estimate
No change.
|