Issaquah Issues

 

  _______________

Home

SE Bypass
- A Chronology

EIS Analysis
- Adequacy Review

Iss. Environ. Council
Biological Assessment Peer Review

Issaquah Voices

SE Bypass EIS Analysis
Adequacy Review

There is an ongoing discussion relating to the determination of "adequacy" of the FEIS.  The Mayor is taking the position that the Staff has that responsibility and it rests with the SEPA Official.  But the SEPA Official is the Planning Director and he has not been involved in the preparation or evaluation of the environmental documentation.  The Public Works Engineering Director has been the one preparing the documentation and presumably will be the one to evaluate its "adequacy."  Since the Issaquah Municipal Code requires that the Planning Director act as the SEPA Official in the absence of written authorization from the Mayor to the contrary, and no such authorization exists, this constitutes a direct violation of Issaquah Municipal Code.

From a pure contractual point of view I argue that the determination of "adequacy" is the responsibility of the City Council.  State Statute assigns contractual authority for the city to the City Council.  There is no disagreement that the City Council has the final responsibility for the "build/no-build" decision.  There is also no disagreement that the environmental documentation has been prepared under a contract with the consulting firm of Parsons Brinckerhoff, Quade and Douglas.  Therefore, the City Council is the appropriate body for assessing the "adequacy" of the various environmental documents for the purpose of supporting the "build/no-build" decision.

The reader should know that the Statement of Work (SOW) between the City of Issaquah and Parsons Brinckerhoff, Quade & Douglas has been changed eleven times so far.  As the contractual authority for the City, one would expect that the City Council would have approved the details of each change.  In fact, the City Council has only voted on five of the changes and often without any details of the change.  I argue that this is a clear violation of State Statute.

The Mayor is arguing that several of the environmental studies for the project were deferred until the permit phase of the project.  Change Order #10 is said to be the source of Council Authorization for such deferrals.  A review of Change Order #10 will show that it authorizes the update of several studies to include the impacts of the new South Alignment C configuration.  There is no discussion in the text relating to the deferral of any work previously authorized for the project.

There is also a second version of Change Order #10 that would require even less update of the environmental documentation.  I refer to this second version as Change Order #10v2.  The problem with this second version is that it is dated several days after the City Council voted to adopt the earlier version of Change Order #10.  That said, there is also no discussion in the text relating to the deferral of any work previously authorized for the project.  Thus I conclude that the City Council has every right to expect the FEIS to meet their needs for making the "build/no-build" decision – the FEIS should be "adequate" for their purposes.

When the City of Issaquah adopted its Land Use Code in April of 1996, the city imposed the State Environmental Policy Act (SEPA) provisions as the standard of determination for the significance of environmental impacts resulting from projects within its jurisdiction.  This provision includes use of the SEPA Checklist as a means of evaluating the significance of a project.  When the SE Bypass was initially scoped to determine the elements of the affected environment for analysis in December of 1996, the SEPA Checklist was not used – a direct violation of Issaquah Municipal Code.

The following tabulation uses the questions from the SEPA Checklist to achieve an objective evaluation of the Technical Reports which analyze the impacts to the various elements of the affected environment.  There are also a few questions which are not taken from the checklist, but still have relevance to the citizens of Issaquah.

The column headed by “Covered by SOW?” refers to the Statement of Work directing the efforts Parsons Brinckerhoff, Quade & Douglas – the consulting firm actually carrying out the environmental analysis of the SE Bypass Project.  The column headed “Answered?” is an evaluation of the applicable technical report content relating to the Checklist questions.  Finally, the column headed “Adequate?” is an attempt to grade the report content in terms of preparing the reader for the build/no-build question faced by each of our City Councilors.

Issaquah’s Municipal Code (Title 18.10) requires EIS’s to contain an Analysis of the Economy, the Social policy, and the Cost-Benefit of all projects in the City found to have significant potential impact to the environment.  The Economic and Social elements are addressed in the EIS documents for the SE Bypass.  The Cost-Benefit Analysis is not provided – another direct violation of Issaquah Municipal Code.

Air Quality

Questions to Answer

SOW – Air Quality

Air Quality Technical Report, 1998-10-20

Air Quality Technical Memorandum, 2000-04

Air Quality Technical Report, 2003-12 Draft

Covered by SOW? Answered? Adequate?
What types of emissions to the air would result from the proposal (i.e., dust, automobile, odors, industrial wood smoke) during construction and when the project is completed? If any, generally describe and give approximate quantities if known. (Env. Checklist Question) Y Y N (1)
Are there any off-site sources of emissions or odor that may affect your proposal? If so, generally describe. (Env. Checklist Question) N N N
Proposed measures to reduce or control emissions or other impacts to air, if any: (Env. Checklist Question) N N N
  1. The SOW does not require any actual measurements at the site.  The report does not provide any actual measurements from the nearest monitoring stations.  The report contains only estimates to the nearest .1 unit which makes them appear more precise than they actually are.  In 2006 the 24 hour standard is changing from 65 to 35 ug/m3.  The Report indicates this standard is 150.

Biological Resources
(wildlife and vegetation)
Fisheries Resources

Questions to Answer

SOW – Biological Resources

SOW - Fisheries

Biological Resources (Wildlife and Vegetation) Technical Report, 1998-09

Biological Resources Supplementary Technical Memorandum, 2000-05-25

SDEIS Biological Assessment, 2004-06-01

Covered by SOW? Answered? Adequate?
Check or circle types of vegetation found on the site:
Deciduous tree: alder, maple, aspen, other
Evergreen tree: fir, cedar, pine, other
shrubs, grass, pasture, Crop of grain
Wet soil plants: cattail, buttercup, bullrush, skunk cabbage, other
Water plants: water lily, eelgrass, milfoil, other
Other types of vegetation(Env. Checklist Question)
Y Y Y
What kind and amount of vegetation will be removed or altered? (Env. Checklist Question) Y Y Y
List threatened or endangered species known to be on or near the site. (Env. Checklist Question) Y Y Y
Proposed landscaping, use of native plants, or other measures to preserve or enhance vegetation on the site, if any: (Env. Checklist Question) N N N
Circle any birds and animals which have been observed on or near the site or are known to be on or near the site: (Env. Checklist Question) Y Y Y
List any threatened or endangered species known to be on or near the site. (Env. Checklist Question) Y Y Y
Is the site part of a migration route? If so, explain. (Env. Checklist Question) N N N
Proposed measures to preserve or enhance wildlife, if any: (Env. Checklist Question) Y Y Y

Energy

Questions to Answer

SOW - Energy

Covered by SOW? Answered? Adequate?
What kinds of energy (electric, natural gas, oil, wood stove, solar) will be used to meet the completed project's energy needs? Describe whether it will be used for heating, manufacturing, etc. (Env. Checklist Question) Y N(1) N(1)
Would your project affect the potential use of solar energy by adjacent properties? If so, generally describe. (Env. Checklist Question) Y N(1) N(1)
What kinds of energy conservation features are included in the plans of this proposal? List other proposed measures to reduce or control energy impacts, if any: (Env. Checklist Question) Y N(1) N(1)
  1. While the SOW states, “The CONSULTANT will prepare an analysis of the direct and indirect energy impacts and the energy conservation potential of each of the alternatives.”, the SOW does not require a deliverable product to present the findings of the analysis.

Floodplains

Questions to Answer

SOW - Floodplains

Floodplains Technical Report, 1998-12-10

Floodplains Technical Memorandum, 2000-03

Covered by SOW? Answered? Adequate?
Cause flooding? Y N(1) N
Increase flooding severity? Y N(1) N
Does the proposal lie within a 100-year floodplain? If so, note location on the site plan. (Env. Checklist Question) Y Y N(2)
  1. The Report and Supplement acknowledge that the project will increase stormwater runoff, but states that the runoff would be detained and released at pre-project rates.  No other discussion is offered.

  2. The Technical Report and Supplement provide figures showing the Floodplain.  The reader is left to extract relevant information from the page size figures.

Geologic Hazards

Questions to Answer Covered by SOW? Answered? Adequate?

Hazardous Materials

Questions to Answer

SOW - Site Assessment

Final Preliminary Environmental Site Assessment (Report not delivered)

Hazardous Materials Technical Report,  (Report not delivered)

Covered by SOW? Answered? Adequate?
Are there any environmental health hazards, including exposure to toxic chemicals, risk of fire and explosion, spill, or hazardous waste, that could occur as a result of this proposal? If so, describe. (Env. Checklist Question) Y N N(1)
Describe special emergency services that might be required. (Env. Checklist Question) N N N(1)
Proposed measures to reduce or control environmental health hazards, if any: (Env. Checklist Question) Y N N(1)
  1. The answer to this question would have been part of the Preliminary and/or Final Environmental Site Assessment Report required by the SOW, Section 7.10.  According to the City Clerk, in response to a Freedom of Information Act Request, the report does not exist.

Historic, Archaeological and Cultural Resources

Questions to Answer

SOW – Historic

Cultural Resources Technical Report, 1998-08-26

Cultural Resources Technical Memorandum, 2000-03

Resolution 1993-15 - Designating Issaquah Treasures

Covered by SOW? Answered? Adequate?
Damage historic/City treasures? N N N(1)
Are there any places or objects listed on, or proposed for, national, state, or local preservation registers known to be on or next to the site? If so, generally describe. (Env. Checklist Question) Y Y Y
Generally describe any landmarks or evidence of historic, archaeological, scientific, or cultural importance known to be on or next to the site. (Env. Checklist Question) Y Y Y
Proposed measures to reduce or control impacts, if any: (Env. Checklist Question) N N N
  1. Treasures #8 and #14 would both be damaged by the project.

Land Use and Social

Questions to Answer

SOW – Land Use

SOW - Social

SOW - Section 4(f) Resources

SOW - Economic

SOW - Displacements and Relocations

Land Use Technical Report, 1998-08-06

Land Use Technical Memo, 2000-06

Social Elements Technical Report, 1998-08-26

Social Elements Technical Memo, 2000-03

Final Section 4(f) Evaluation Report (Report not delivered)

Economics Technical Report

Displacements and Relocations Technical Report, 1998-08-28

Displacements and Relocations Technical Memo, 2000-03

Covered by SOW? Answered? Adequate?
What is the current use of the site and adjacent properties? (Env. Checklist Question) Y Y Y
Has the site been used for agriculture? If so, describe. (Env. Checklist Question) N N Y
Describe any structures on the site. (Env. Checklist Question) N N N
Will any structures be demolished? If so, what? (Env. Checklist Question) N Y N(1)
What is the current zoning classification of the site? (Env. Checklist Question) Y Y Y
What is the current comprehensive plan designation of the site? (Env. Checklist Question) N Y (2) Y
If applicable, what is the current shoreline master program designation of the site? (Env. Checklist Question) N Y N(3)
Has any part of the site been classified as an "environmentally sensitive" area? If so, specify. (Env. Checklist Question) Y N(4) N
Approximately how many people would reside or work in the completed project? (Env. Checklist Question) N/A N/A N/A
Approximately how many people would the completed project? (Env. Checklist Question) N/A(5) N/A N/A
Proposed measures to avoid or reduce displacement impacts, if any: (Env. Checklist Question) N N N
Proposed measures to ensure the proposal is compatible with existing and projected land uses and plans, if any: (Env. Checklist Question) N N N
Approximately how many units would be provided, if any? Indicate whether high, middle, or low-income housing. (Env. Checklist Question) N N N
Approximately how many units, if any, would be eliminated? Indicate whether high, middle, or low-income housing. (Env. Checklist Question) Y N(6) N
Proposed measures to reduce or control housing impacts, if any: (Env. Checklist Question) N N N
What designated and informal recreational opportunities are in the immediate vicinity? (Env. Checklist Question) Y Y Y
Would the proposed project displace any existing recreational uses? If so, describe. (Env. Checklist Question) Y Y Y
Proposed measures to reduce or control impacts on recreation, including recreation opportunities to be provided by the project or applicant, if any: (Env. Checklist Question) N N N
Would the project result in an increased need for public services (for example: fire protection, police protection, health care, schools, other)? If so, generally describe. (Env. Checklist Question) N N N
Proposed measures to reduce or control direct impacts on public services, if any. (Env. Checklist Question) N N N
Circle utilities currently available at the site: electricity, natural gas, water, refuse service, telephone, sanitary sewer, septic system, other. (Env. Checklist Question) N N N
Describe the utilities that are proposed for the project, the utility providing the service, and the general construction activities on the site or in the immediate vicinity which might be needed. (Env. Checklist Question) N N N
  1. There is discussion of relocations, but no specifics of the actual properties involved.

  2. Both the Issaquah and King County Comprehensive Plans are discussed in the Final Land Use Technical Report.  The actual Land Use Designations are not covered except to say that the current zoning designations and uses would not be substantially changed.  Park Pointe is mentioned as a known change of density.

  3. The buffers required for projects in the vicinity of a Shoreline Designated waterway need to be updated.

  4. There are references to “Steep Slopes” and “Wetlands” though there is no specific discussion about these areas in terms of Critical Areas.

  5. This question is taken directly from the SEPA Environmental Checklist.  The question is an incomplete question.

  6. Relocations are discussed though not in sufficient detail to answer this question.

Noise

Questions to Answer

SOW - Noise

Noise Technical Report, 1998-08-27

Noise Technical Memorandum, 2000-04

Noise Technical Report, 2003-12

Covered by SOW? Answered? Adequate?
What types of noise exist in the area which may affect your project (for example: traffic, equipment, operation, other)? (Env. Checklist Question) (Env. Checklist Question) N/A(1) NA N/A
What types and levels of noise would be created by or associated with the project on a short-term or a long-term basis (for example: traffic, construction, operation, other)? Indicate what hours noise would come from the site. (Env. Checklist Question) (Env. Checklist Question) Y Y Y
Proposed measures to reduce or control noise impacts, if any: (Env. Checklist Question) (Env. Checklist Question) Y Y N(2)
  1. Since the project is about traffic, only traffic noise was discussed.

  2. The SOW required a more detailed analysis of the types and cost of mitigation than was presented.

Soils and Topography

Questions to Answer

SOW - Earth

Earth Technical Report, 1998-10-02

Earth Technical Memorandum, 2000-02-23

Covered by SOW? Answered? Adequate?
General description of the site (circle one): Flat, rolling, hilly, steep slopes, mountainous, other N Y Y
What is the steepest slope on the site (approximate percent slope)? (Env. Checklist Question) N N N
What general types of soils are found on the site (for example, clay, sand, gravel, peat, muck)? If you know the classification of agricultural soils, specify them and note any prime farmland. (Env. Checklist Question) N Y Y
Are there surface indications or history of unstable soils in the immediate vicinity? If so, describe. (Env. Checklist Question) N N N
Describe the purpose, type, and approximate quantities of any filling or grading proposed. Indicate source of fill. (Env. Checklist Question) N N N
Could erosion occur as a result of clearing, construction, or use? If so, generally describe. (Env. Checklist Question) N N N(1)
About what percent of the site will be covered with impervious surfaces after project construction (for example, asphalt or buildings)? (Env. Checklist Question) N N N
Proposed measures to reduce or control erosion, or other impacts to the earth, if any: (Env. Checklist Question) N N N
  1. The Earth Technical Report acknowledges the existence of Steep Slopes and the potential for slippage.  The report goes on to say that such slippage would have to be handled by “site-specific” mitigation measures and them offers none.

Transportation

Questions to Answer

SOW - Transportation

Transportation Technical Report, 1998-10-28

Transportation Technical Memorandum, 2000-03

Transportation Technical Report, 2003-12

Covered by SOW? Answered? Adequate?
Relieves congestion at SR 900 Interchange? (Purpose and Need Statement Question) Y(1)    
Relieves congestion at Front Street Interchange? (Purpose and Need Statement Question) Y(1)    
Relieves congestion on 2nd Ave. S.? (Purpose and Need Statement Question) Y(2)    
Relieves congestion on Front St. S.? (Purpose and Need Statement Question) Y(3)    
Relieves congestion in CBD? (Purpose and Need Statement Question) Y(3)    
Identify public streets and highways serving the site, and describe proposed access to the existing street system. Show on site plans, if any. (Env. Checklist Question) Y Y Y
Is site currently served by public transit? If not, what is the approximate distance to the nearest transit stop? (Env. Checklist Question) Y Y  
How many parking spaces would the completed project have? How many would the project eliminate? (Env. Checklist Question) N/A N/A N/A
Will the proposal require any new roads or streets, or improvements to existing roads or streets, not including driveways? If so, generally describe (indicate whether public or private). (Env. Checklist Question) Y(4) Y N(5)
Will the project use (or occur in the immediate vicinity of) water, rail, or air transportation? If so, generally describe. (Env. Checklist Question) Y Y N(6)
How many vehicular trips per day would be generated by the completed project? If known, indicate when peak volumes would occur. (Env. Checklist Question) N N(7) N
Proposed measures to reduce or control transportation impacts, if any: (Env. Checklist Question) N N N
  1. The SOW does not contain a specific reference to SR-900 or the SR-900 Interchange.  It does require analysis of the Interchange operations and I-90 Operations as part of the requirements of Task 7.  Task 15 was added by Change Order #5 and specifically requires analysis of the SR-900 Interchange.  Since Change Order #5 was initiated in July, 1999, the results of the analysis should be part of the DEIS and the SDEIS.

  2. Congestion on 2nd Ave is not addressed in the SOW until it was added as part of Change Order #8.  Change Order #8 involved tasking for the SDEIS.

  3. Congestion in the Commercial Business District on Front St. N. is not referenced in the SOW.  There is reference to analyzing the LOS at the intersection of Front/Gilman and Front/Sunset.

  4. The project is for a new road so the entire document is analyzing that impact.

  5. The analysis of the project does not demonstrate sufficient benefit to offset the environmental damage that results.

  6. The project does damage wetlands in the southend and has the potential to damage the Issaquah Creek, the North and South Tributary, and the East Fork of the Issaquah Creek.  This potential in not adequately discussed within the EIS.  (See the analysis of water quality and quantity impacts)

  7. Though not specifically required by the SOW, the tabulations of traffic volumes shows that the project does result in induced traffic flows.  These results are not specifically highlighted for the reader.

Visual

Questions to Answer

SOW - Visual

Covered by SOW? Answered? Adequate?
What is the tallest height of any proposed structure(s), not including antennas; what is the principal exterior building material(s) proposed? (Env. Checklist Question) Y N(1) N(1)
What views in the immediate vicinity would be altered or obstructed? (Env. Checklist Question) Y N(1) N(1)
Proposed measures to reduce or control aesthetic impacts, if any: (Env. Checklist Question) Y N(1) N(1)
What type of light or glare will the proposal produce? What time of day would it mainly occur? (Env. Checklist Question) Y N(1) N(1)
Could light or glare from the finished project be a safety hazard or interfere with views? (Env. Checklist Question) Y N(1) N(1)
What existing off-site sources of light or glare may affect your proposal? (Env. Checklist Question) Y N(1) N(1)
Proposed measures to reduce or control light and glare impacts, if any: (Env. Checklist Question) Y N(1) N(1)
  1. While the SOW states, “The CONSULTANT will provide an assessment of the visual impacts of each alternative.”, the SOW does not require a deliverable product to present the findings of the analysis.

Water Quality
(surface and ground water)

Questions to Answer

SOW – Water Quality

Water Quality Technical Report, 1998-09-09

Water Quality Technical Memorandum, 2000-05-30

Water Quality Technical Analysis, 2003-12

Covered by SOW? Answered? Adequate?
Pollute streams? Y Y N(1)
Is there any surface water body on or in the immediate vicinity of the site (including year-round and seasonal streams, saltwater, lakes, ponds, wetlands)? If yes, describe type and provide names. If appropriate, state what stream or river it flows into. (Env. Checklist Question) Y Y Y
Will the project require any work over, in, or adjacent to (within 200 feet) the described waters? If yes, please describe and attach available plans. (Env. Checklist Question) Y Y N(2)
Estimate the amount of fill and dredge material that would be placed in or removed from surface water or wetlands and indicate the area of the site that would be affected. Indicate the source of fill material. (Env. Checklist Question) Y N N
Will the proposal require surface water withdrawals or diversions? Give general description, purpose, and approximate quantities if known. (Env. Checklist Question) Y N N(3)
Does the proposal involve any discharges of waste materials to surface waters? If so, describe the type of waste and anticipated volume of discharge. (Env. Checklist Question) Y Y Y
Will ground water be withdrawn, or will water be discharged to ground water? Give general description, purpose, and approximate quantities if known. (Env. Checklist Question) Y N N(4)
Describe waste material that will be discharged into the ground from septic tanks or other sources, if any (for example: Domestic sewage; industrial, containing the following chemicals. . . ; agricultural; etc.). Describe the general size of the system, the number of such systems, the number of houses to be served (if applicable), or the number of animals or humans the system(s) are expected to serve. (Env. Checklist Question) Y Y Y
Describe the source of runoff (including storm water) and method of collection and disposal, if any (include quantities, if known). Where will this water flow? Will this water flow into other waters? If so, describe. (Env. Checklist Question) Y Y Y
Could waste materials enter ground or surface waters? If so, generally describe. (Env. Checklist Question) Y Y N(5)
Proposed measures to reduce or control surface, ground, and runoff water impacts, if any: (Env. Checklist Question) Y Y N(6)
  1. Pollution of streams is acknowledged though not quantified in a way that the reader can understand.

  2. While acknowledging that work will occur within 200 feet of such waters, there is no plan offered for controlling pollutants.

  3. Surface water diversions are acknowledged.  Infiltration facilities will alter the location and amount of aquifer recharge.  The potential damage to aquifer recharge is not analyzed.

  4. The report commits to maintaining pre-project recharge to the aquifer, but does not analyze or estimate the location and quantity of recharge volumes.

  5. The discussion of potential pollutant impacts is too superficial to be of any use.

  6. There is discussion of water control measures that might be employed at a very superficial level.  There is no detail or commitment to any particular plan or outcome.

Waterways and Hydrological Systems
(surface and groundwater quantity)

Questions to Answer

SOW – Waterways and Hydrological Systems

Waterways and Hydrologic Systems Technical Report, 1998-09-09

Waterways and Hydrologic Systems Technical Memorandum, 2000-05-30

Covered by SOW? Answered? Adequate?
Intercept groundwater flows? Y N N(1)
Reduce aquifer recharge? Y N N(1)
  1. The documentation relies on the Wellhead Protection Plan for much of the analysis yet it does not even include all the details as to the portion of aquifer recharge associated with the project area.  The north end of the project has a great potential of intercepting groundwater flows and altering their final destinations.  The surface water runoff could also be diverted from its current recharge destination.
    The Earth Technical Report contains boring records which report groundwater levels at several boring locations both in the north and south end of the project.  The report does not attempt to quantify the groundwater flows at or near the finished project roadway surface even though such encounters are clearly probable.

Wetlands

Questions to Answer

SOW - Wetlands

Wetland Technical Report, 1998-09-28

Wetlands Technical Memorandum, 2000-05-24

Wetland Mitigation Plan, 2003-10

Covered by SOW? Answered? Adequate?
Degrade existing wetlands? Y Y N(1)
  1. Both the Technical Report and Supplement Memorandum indicate degradation of wetlands, but the mitigation measures proposed are superficial at best.